ODOT contract 250099 bid tabulation
PIC-SR 762-11.18 (SPOT PATCHING / PAVEMENT REPAIR). Let by Ohio DOT on February 13, 2025, PIC. 5 bids received; low bid $1,967,344 by Shelly Company, -34% against the engineer's estimate of $2,971,000.
- Owner
- Ohio DOT
- Letting
- 13 FEB 2025
- Pay items
- 65
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly Company | $1,967,344 | Low | -34% |
| 2 | Strawser Paving Co Inc | $2,162,760 | +10% | -27% |
| 3 | Kokosing Construction Company Inc | $2,179,967 | +11% | -27% |
| 4 | Axis Civil Construction LLC | $2,272,933 | +16% | -23% |
| 5 | Shelly & Sands Inc | $2,525,226 | +28% | -15% |
Engineer's estimate: $2,971,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly Company | 2. Strawser Paving Co Inc | 3. Kokosing Construction Company Inc | 4. Axis Civil Construction LLC | 5. Shelly & Sands Inc |
|---|---|---|---|---|---|---|---|---|
| 1 | Pavement removed, as per plan (202E23001) | SY | 741 | $19.75 | $29.00 | $37.00 | $16.00 | $55.00 |
| 2 | Pipe removed (202E34900) | FT | 3,283 | $9.35 | $6.50 | $9.00 | $1.80 | $10.50 |
| 3 | Guardrail removed, as per plan (202E38001) | FT | 3,168 | $2.00 | $2.00 | $2.00 | $2.00 | $2.00 |
| 4 | Anchor assembly removed, type E, as per plan (202E42011) | EACH | 4 | $175.00 | $135.00 | $135.00 | $175.00 | $175.00 |
| 5 | Bridge terminal assembly removed, as per plan (202E47001) | EACH | 4 | $125.00 | $60.00 | $60.00 | $125.00 | $125.00 |
| 6 | Excavation (203E10000) | CY | 253 | $61.00 | $19.00 | $76.00 | $28.00 | $85.00 |
| 7 | Embankment (203E20000) | CY | 216 | $47.50 | $48.00 | $21.00 | $21.00 | $82.50 |
| 8 | Subgrade compaction (204E10000) | SY | 1,391 | $2.85 | $3.50 | $4.75 | $2.00 | $5.00 |
| 9 | Excavation of subgrade (204E13000) | CY | 3,106 | $38.00 | $46.00 | $23.00 | $18.00 | $56.90 |
| 10 | Granular material, type C (204E30020) | CY | 3,106 | $57.00 | $68.00 | $50.00 | $75.00 | $63.00 |
| 11 | Geogrid (204E51000) | SY | 9,346 | $1.75 | $5.00 | $1.50 | $2.00 | $2.50 |
| 12 | Linear grading, as per plan (209E60201) | STA | 34.60 | $75.00 | $75.00 | $94.00 | $75.00 | $85.00 |
| 13 | Guardrail, type MGS (606E15050) | FT | 3,487.50 | $18.50 | $17.60 | $17.60 | $18.50 | $18.50 |
| 14 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 4 | $2,400.00 | $2,380.00 | $2,380.00 | $2,400.00 | $2,400.00 |
| 15 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,400.00 | $2,450.00 | $2,450.00 | $2,400.00 | $2,400.00 |
| 16 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $19,500 | $33,320 | $10,080 | $27,000 | $13,500 |
| 17 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 113 | $85.00 | $74.00 | $96.00 | $70.00 | $65.00 |
| 18 | Rock channel protection, type C with filter (601E32200) | CY | 6 | $350.00 | $380.00 | $300.00 | $155.00 | $600.00 |
| 19 | Topsoil (659E00300) | CY | 144 | $120.00 | $70.00 | $30.00 | $110.00 | $125.00 |
| 20 | Seeding and mulching (659E10000) | SY | 1,317 | $3.50 | $2.60 | $3.50 | $2.60 | $3.50 |
| 21 | Repair seeding and mulching (659E14000) | SY | 65 | $6.00 | $2.60 | $6.00 | $2.60 | $6.00 |
| 22 | Inter-seeding (659E15000) | SY | 65 | $5.00 | $2.60 | $5.00 | $2.60 | $5.00 |
| 23 | Commercial fertilizer (659E20000) | TON | 0.18 | $750.00 | $1,250.00 | $750.00 | $1,250.00 | $750.00 |
| 24 | Lime (659E31000) | ACRE | 0.27 | $10.00 | $150.00 | $10.00 | $150.00 | $10.00 |
| 25 | Water (659E35000) | MGAL | 7 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 26 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 27 | Concrete masonry (602E20000) | CY | 0.90 | $2,825.00 | $4,200.00 | $4,000.00 | $3,200.00 | $4,500.00 |
| 28 | 6" unclassified pipe underdrains (605E13300) | FT | 20 | $33.25 | $12.00 | $20.00 | $35.00 | $65.00 |
| 29 | 6" base pipe underdrains (605E14000) | FT | 3,232 | $15.00 | $12.00 | $19.00 | $15.00 | $35.00 |
| 30 | 6" conduit, type F (611E01500) | FT | 40 | $20.00 | $12.00 | $55.00 | $28.00 | $50.00 |
| 31 | 15" conduit, type C (611E06100) | FT | 184 | $85.50 | $120.00 | $135.00 | $80.00 | $145.00 |
| 32 | Catch basin, no. 3 (611E98150) | EACH | 1 | $3,685.00 | $4,800.00 | $6,000.00 | $5,000.00 | $4,750.00 |
| 33 | Catch basin, no. 3A (611E98180) | EACH | 2 | $2,985.00 | $3,800.00 | $4,500.00 | $4,600.00 | $4,000.00 |
| 34 | Precast reinforced concrete outlet (611E99710) | EACH | 4 | $320.00 | $150.00 | $600.00 | $375.00 | $650.00 |
| 35 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 479 | $78.50 | $80.00 | $150.00 | $145.00 | $95.00 |
| 36 | Partial depth pavement repair (asphalt concrete base), as per plan (251E01041) | SY | 8 | $800.00 | $185.00 | $850.00 | $252.00 | $95.00 |
| 37 | Full depth pavement sawing (252E01500) | FT | 17,490 | $1.50 | $1.25 | $1.59 | $1.60 | $0.25 |
| 38 | Pavement repair, as per plan (253E02001) | CY | 5,087 | $180.25 | $185.00 | $205.00 | $225.00 | $215.00 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 145 | $203.00 | $300.00 | $255.00 | $355.00 | $225.00 |
| 40 | Aggregate base (304E20000) | CY | 232 | $76.00 | $115.00 | $170.00 | $280.00 | $165.00 |
| 41 | Non-tracking tack coat (407E20000) | GAL | 138 | $3.90 | $4.40 | $2.80 | $5.00 | $3.50 |
| 42 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 35 | $295.00 | $575.00 | $550.00 | $495.00 | $235.00 |
| 43 | Curb, type 6, as per plan (609E26001) | FT | 3,334 | $21.00 | $18.00 | $22.00 | $20.50 | $27.00 |
| 44 | RPM (621E00100) | EACH | 84 | $65.00 | $62.00 | $65.00 | $65.00 | $65.00 |
| 45 | Raised pavement marker removed (621E54000) | EACH | 84 | $4.50 | $1.00 | $1.00 | $5.00 | $15.00 |
| 46 | Barrier reflector, type 2, 2-way (626E00110) | EACH | 57 | $12.00 | $12.00 | $12.00 | $12.00 | $12.00 |
| 47 | Edge line, 6" (644E00104) | MI | 1.78 | $4,791.00 | $4,791.00 | $4,791.00 | $4,791.00 | $4,200.00 |
| 48 | Center line (644E00300) | MI | 1.83 | $5,350.00 | $5,350.00 | $5,350.00 | $5,350.00 | $5,400.00 |
| 49 | Channelizing line, 8" (644E00400) | FT | 100 | $2.90 | $2.90 | $2.90 | $2.90 | $2.00 |
| 50 | Transverse/diagonal line (644E00700) | FT | 948 | $7.30 | $7.30 | $7.30 | $7.30 | $7.00 |
| 51 | Removal of pavement marking (644E30000) | FT | 8,232 | $0.35 | $0.35 | $0.35 | $0.35 | $0.55 |
| 52 | Removal of pavement marking (644E30000) | FT | 294 | $5.00 | $5.00 | $5.00 | $5.00 | $2.00 |
| 53 | Removal of pavement marking (644E30030) | MI | 2.59 | $1,848.00 | $1,848.00 | $1,848.00 | $1,848.00 | $2,600.00 |
| 54 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 72 | $80.00 | $82.00 | $75.00 | $85.00 | $110.00 |
| 55 | Special - work zone traffic signal (614E11300) | EACH | 8 | $3,000.00 | $2,750.00 | $2,750.00 | $2,200.00 | $3,500.00 |
| 56 | Work zone marking sign (614E12460) | EACH | 12 | $100.00 | $85.00 | $125.00 | $200.00 | $100.00 |
| 57 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,500.00 | $900.00 | $900.00 | $750.00 | $1,500.00 |
| 58 | Work zone center line, class III, 642 paint (614E21550) | MI | 1.83 | $1,050.00 | $1,705.00 | $1,705.00 | $1,705.00 | $1,705.00 |
| 59 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 6.96 | $1,075.00 | $900.00 | $900.00 | $900.00 | $1,300.00 |
| 60 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 100 | $5.50 | $1.50 | $1.50 | $1.50 | $1.50 |
| 61 | Work zone stop line, class III, 642 paint (614E26610) | FT | 168 | $6.00 | $5.00 | $5.00 | $5.00 | $8.00 |
| 62 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,000.00 | $15,000 | $9,000.00 | $13,000 | $10,389 |
| 63 | Maintaining traffic (614E11000) | LS | 1 | $49,250 | $100,000 | $86,179 | $50,000 | $155,742 |
| 64 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $9,500.00 | $13,200 | $6,000.00 | $3,000.00 | $15,000 |
| 65 | Mobilization (624E10000) | LS | 1 | $75,000 | $100,000 | $108,000 | $100,000 | $100,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of February 13, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.