Strawser Paving Co Inc submitted 32 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 07 MAY 2026, and was the low bidder on 4 of them (13%). When it was not low, its total sat a median +11% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $4,766,495
- Latest bid
- 07 MAY 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 2 | 0 | 0% |
| 2021 | 5 | 0 | 0% |
| 2022 | 5 | 2 | 40% |
| 2023 | 1 | 0 | 0% |
| 2024 | 4 | 1 | 25% |
| 2025 | 12 | 1 | 8% |
| 2026 | 3 | 0 | 0% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| FRA | 10 | 1 | 10% |
| DEL | 7 | 3 | 43% |
| FAI | 6 | 0 | 0% |
| LIC | 3 | 0 | 0% |
| UNI | 2 | 0 | 0% |
| MAD | 2 | 0 | 0% |
| PIC | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 31 | 31 (100%) | $1.00 | $1.00 |
| Water | 659E35000 | MGAL | 26 | 19 (73%) | $1.00 | $1.00 |
| Proof rolling | 204E45000 | HR | 14 | 13 (93%) | $150.00 | $219.05 |
| Lime | 659E31000 | ACRE | 22 | 12 (55%) | $150.00 | $150.00 |
| Center line | 644E00300 | MI | 15 | 11 (73%) | $7,000.00 | $7,070.00 |
| Subgrade compaction | 204E10000 | SY | 24 | 10 (42%) | $1.62 | $3.00 |
| Stop line | 644E00500 | FT | 13 | 10 (77%) | $8.30 | $8.29 |
| Non-tracking tack coat | 407E20000 | GAL | 27 | 8 (30%) | $4.40 | $3.25 |
| Repair seeding and mulching | 659E14000 | SY | 20 | 8 (40%) | $1.56 | $1.25 |
| Seeding and mulching | 659E10000 | SY | 15 | 7 (47%) | $2.60 | $2.60 |
| Edge line, 6" | 644E00104 | MI | 12 | 7 (58%) | $5,070.50 | $5,000.00 |
| Law enforcement officer with patrol car for assistance | 614E11110 | HR | 17 | 6 (35%) | $75.00 | $80.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Shelly & Sands Inc | 22 | 13 of 22 |
| Shelly Company | 17 | 14 of 17 |
| Complete General Construction Company | 13 | 4 of 13 |
| Axis Civil Construction LLC | 12 | 7 of 12 |
| Double Z Construction Company | 8 | 2 of 8 |
| Trucco Construction Co Inc | 7 | 3 of 7 |
| Kokosing Construction Company Inc | 6 | 2 of 6 |
| Eclipse Co LLC | 5 | 1 of 5 |
| Cap-Stone & Associates Inc | 5 | 4 of 5 |
| Danbert Incorporated | 5 | 1 of 5 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 07 MAY 2026 | 260236 | FRA | FRA-SR 317/Williams Rd (INTERSECTION) | 3 of 3 | $445,486 | +32% |
| 23 APR 2026 | 260198 | FAI | FAI-SR 204-04.30 (INTERSECTION) | 2 of 4 | $2,161,199 | +1.0% |
| 19 FEB 2026 | 260110 | PIC | PIC-US 23-18.52 (SPOT SAFETY) | 2 of 5 | $350,475 | +16% |
| 13 NOV 2025 | 250521 | FAI | FAI-SR 158-04.20 (INTERSECTION) | 6 of 7 | $2,799,757 | +21% |
| 23 OCT 2025 | 250512 | FRA | FRA-EXPO CENTER/OHC-FY2026 (PARKING AREAS) | 2 of 7 | $1,110,197 | +8.0% |
| 28 AUG 2025 | 250393 | DEL | DEL-SR 750-02.57 (SPOT SAFETY) | 2 of 5 | $199,968 | +7.0% |
| 31 JUL 2025 | 250361 | MAD | MAD-US 42/CR 40/West Ave-Sidewalks (SIDEWALK) | 2 of 4 | $411,826 | +13% |
| 31 JUL 2025 | 250371 | FRA | FRA-US 33-28.61 (INTERSECTION) | 4 of 5 | $278,564 | +9.0% |
| 22 MAY 2025 | 250263 | UNI | UNI-US 42-03.91 (MINOR RECONSTRUCTION) | 4 of 6 | $8,388,383 | +5.0% |
| 24 APR 2025 | 250237 | DEL | DEL-SR 315 Drainage Improvements (CULVERT REPLACEMENT) | 2 of 5 | $242,542 | +3.0% |
| 24 APR 2025 | 258005 | DEL | DEL-SR 315-05.66 at Hyatts Rd (INTERSECTION) | 1 of 6 | $2,796,257 | Low, -1.0% under the second |
| 27 FEB 2025 | 250093 | LIC | LIC-CR 134-02.06 (MINOR RECONSTRUCTION) | 2 of 10 | $2,558,903 | +5.0% |
| 13 FEB 2025 | 250094 | LIC | LIC-CR 327-00.00 (BIKEWAYS) | 4 of 8 | $1,096,723 | +17% |
| 13 FEB 2025 | 250099 | PIC | PIC-SR 762-11.18 (SPOT PATCHING / PAVEMENT REPAIR) | 2 of 5 | $2,162,760 | +10% |
| 30 JAN 2025 | 250047 | FAI | FAI-SR 204-02.28 (INTERSECTION) | 3 of 5 | $931,073 | +11% |
| 19 DEC 2024 | 240577 | FRA | FRA-US 33-06.15 (at Hayden Run Rd) (MINOR RECONSTRUCTION) | 3 of 6 | $1,721,653 | +10% |
| 13 JUN 2024 | 240325 | FRA | FRA-US 40-15.27 (TWO LANE RESURFACING) | 1 of 3 | $746,630 | Low, 5.0% under the second |
| 18 APR 2024 | 240234 | FRA | FRA-SR 161-08.66 Olentangy River Rd (INTERSECTION) | 3 of 3 | $348,935 | +14% |
| 22 FEB 2024 | 240145 | LIC | LIC-TR 171-01.34 (Multiuse Path) (BIKEWAYS) | 5 of 5 | $1,402,028 | +62% |
| 09 MAR 2023 | 230150 | FRA | FRA-SR 256-00.01 (FOUR LANE RESURFACING) | 4 of 4 | $777,325 | +21% |
| 28 JUL 2022 | 220454 | DEL | DEL-ALUM CREEK BEACH PARKING LOT (PARKING AREAS) | 1 of 2 | $1,005,956 | Low, 16% under the second |
| 28 JUL 2022 | 220455 | DEL | DEL-ALUM CREEK MARINA (PARKING AREAS) | 1 of 3 | $217,651 | Low, 13% under the second |
| 31 MAR 2022 | 220207 | FAI | FAI-CR 9/TR 222-01.60/00.00 (SIDEWALK) | 5 of 6 | $436,681 | +28% |
| 31 MAR 2022 | 220226 | FRA | FRA-EXPO FY22 (PARKING AREAS) | 3 of 6 | $157,247 | +3.0% |
| 13 JAN 2022 | 220034 | MAD | MAD-LONDON FISH HATCHERY (PARKING AREAS) | 2 of 3 | $172,883 | +2.0% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.