ODOT contract 250093 bid tabulation

LIC-CR 134-02.06 (MINOR RECONSTRUCTION). Let by Ohio DOT on February 27, 2025, LIC. 10 bids received; low bid $2,445,730 by Miller Bros Const Inc, -12% against the engineer's estimate of $2,789,000.

Owner
Ohio DOT
Letting
27 FEB 2025
Pay items
100
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Miller Bros Const Inc$2,445,730Low-12%
2Strawser Paving Co Inc$2,558,903+5.0%-8.0%
3Shelly Company$2,569,506+5.0%-8.0%
4Shelly & Sands Inc$2,652,154+8.0%-5.0%
5Law General Contracting Inc$2,665,252+9.0%-4.0%
6Trucco Construction Co Inc$2,790,364+14%0.0%
7Danbert Incorporated$2,908,205+19%+4.0%
8Double Z Construction Company$2,963,911+21%+6.0%
9Eclipse Co LLC$3,047,925+25%+9.0%
10Complete General Construction Company$3,114,629+27%+12%
ODOT contract 250093: bids by rank

Engineer's estimate: $2,789,000.

Bid tabulation

LinePay itemUnitQuantity1. Miller Bros Const Inc2. Strawser Paving Co Inc3. Shelly Company4. Shelly & Sands Inc5. Law General Contracting Inc6. Trucco Construction Co Inc
1Clearing and grubbing (201E11000)LS1$25,000$2,000.00$13,000$22,000$2,600.00$19,200
2Tree removed, 18" diameter (201E21800)EACH16$1,200.00$500.00$425.00$1,200.00$785.00$300.00
3Stump removed, 18", as per plan (201E26501)EACH2$250.00$375.00$675.00$250.00$524.00$1,180.00
4Pavement removed (202E23000)SY6,276$11.00$14.00$16.25$10.95$5.50$7.60
5Pavement removed (202E23000)SY571$10.00$27.00$16.35$18.00$21.00$23.00
6Curb and gutter removed (202E32500)FT22$10.00$50.00$22.50$12.00$16.00$43.00
7Pipe removed, 24" and under (202E35100)FT534$17.70$6.00$34.00$10.00$27.00$28.00
8Guardrail removed (202E38000)FT703$1.80$2.80$2.80$2.80$2.00$2.80
9Catch basin removed (202E58100)EACH1$800.00$600.00$560.00$150.00$297.00$690.00
10Fence removed (202E75000)FT158$4.00$5.00$3.50$3.50$3.50$10.90
11Excavation (203E10000)CY2,069$30.00$23.50$40.00$28.00$39.50$65.00
12Embankment (203E20000)CY1,034$7.50$9.50$28.75$16.00$21.00$9.40
13Subgrade compaction (204E10000)SY571$4.50$2.00$5.00$12.00$3.00$7.80
14Excavation of subgrade (204E13000)CY110$25.50$25.00$56.50$45.00$36.00$47.00
15Granular material, type B (204E30010)CY110$88.00$25.00$76.50$75.00$84.00$87.00
16Proof rolling (204E45000)HR8$140.00$100.00$245.00$250.00$156.00$350.00
17Geotextile fabric (204E50000)SY310$2.80$2.50$3.20$1.50$1.50$4.00
18Cement (206E10500)TON240$222.00$221.49$221.49$225.00$255.00$221.00
19Curing coat (206E11000)SY8,295$1.30$1.27$1.27$1.30$1.40$1.30
20Cement stabilized subgrade, 14 inches deep (206E15020)SY8,295$4.50$4.47$4.47$4.50$6.00$7.00
21Guardrail, type MGS (606E15050)FT879$20.40$22.00$22.00$22.00$24.00$22.00
22Anchor assembly, type E (606E26100)EACH8$2,485.00$2,500.00$2,500.00$2,500.00$2,892.00$2,500.00
23Anchor assembly, type T (606E26500)EACH4$1,340.00$1,000.00$1,000.00$1,000.00$1,560.00$1,000.00
24Combination curb and gutter, type 2 (609E12000)FT22$127.40$60.00$110.00$68.00$146.00$108.00
25Low strength mortar backfill (613E41200)CY25$205.00$250.00$225.00$185.00$177.00$213.00
26Special - mailbox removed and reset (690E50350)EACH7$194.00$400.00$210.00$450.00$146.00$750.00
27Soil analysis test (659E00100)EACH2$150.00$125.00$125.00$125.00$582.00$125.00
28Topsoil (659E00300)CY750$8.50$45.00$45.00$50.00$60.00$64.00
29Seeding and mulching, class 1 (659E00500)SY6,751$1.00$0.77$0.77$0.80$1.50$0.80
30Repair seeding and mulching (659E14000)SY338$1.00$0.80$0.80$0.80$1.50$0.80
31Inter-seeding (659E15000)SY338$1.00$0.80$0.80$0.80$2.50$0.80
32Commercial fertilizer (659E20000)TON0.61$1,250.00$891.38$891.38$895.00$1,400.00$890.00
33Lime (659E31000)ACRE1.39$150.00$155.50$155.50$160.00$175.00$156.00
34Water (659E35000)MGAL36$1.00$1.00$1.00$1.00$1.00$1.00
35Slope erosion protection (670E00500)SY2,300$2.50$1.26$1.26$1.30$3.00$1.30
36Storm water pollution prevention plan (832E15000)LS1$2,500.00$1,975.00$1,975.00$3,200.00$8,728.00$1,980.00
37Storm water pollution prevention inspections (832E15002)LS1$7,360.00$2,040.00$1,770.00$8,000.00$31,421$8,200.00
38Storm water pollution prevention inspection software (832E15010)LS1$2,500.00$8,000.00$8,000.00$14,750$2,100.00$19,600
39Erosion control (832E30000)EACH50,000$1.00$1.00$1.00$1.00$1.00$1.00
40Rock channel protection, type B with filter (601E32100)CY2.80$250.00$700.00$675.00$450.00$302.00$243.00
41Concrete masonry (602E20000)CY0.86$1,200.00$3,500.00$2,400.00$3,000.00$3,689.00$4,870.00
424" base pipe underdrains (605E06000)FT4,514$5.50$8.00$14.50$13.50$12.00$11.50
434" conduit, type E (611E00400)FT100$35.00$10.00$16.50$10.00$11.50$31.00
444" conduit, type F for underdrain outlet (611E00410)FT269$28.00$10.00$36.00$20.00$28.00$60.00
4512" conduit, type B (611E04400)FT5$300.00$100.00$182.00$375.00$136.00$371.00
4618" conduit, type B (611E07400)FT72$95.00$110.00$85.50$120.00$132.00$126.00
4724" conduit, type B (611E10400)FT383$140.00$120.00$100.50$160.00$128.00$170.00
48Catch basin, no. 2-3 (611E98510)EACH11$2,500.00$2,700.00$3,375.00$3,300.00$4,800.00$3,640.00
49Manhole, no. 3 (611E99574)EACH1$2,700.00$3,000.00$2,970.00$4,200.00$3,400.00$4,220.00
50Precast reinforced concrete outlet (611E99710)EACH1$200.00$700.00$325.00$250.00$238.00$2,000.00
51Pavement planing, asphalt concrete 3" (254E01000)SY395$31.75$25.00$23.00$31.75$15.50$30.00
52Asphalt concrete base, PG64-22, (449) (301E56000)CY1,996$174.75$165.00$174.75$175.00$210.00$167.00
53Aggregate base (304E20000)CY41$90.00$165.00$124.00$160.00$113.00$173.00
54Aggregate base (304E20000)CY1,860$75.00$70.00$69.25$88.00$78.00$90.00
55Non-tracking tack coat (407E20000)GAL1,001$3.90$3.00$3.90$3.90$5.50$3.00
56Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY285$217.75$220.00$217.75$217.75$261.00$223.00
57Asphalt concrete intermediate course, type 2, (449) (441E70300)CY399$200.75$210.00$200.75$200.75$250.00$215.00
58Asphalt concrete surface course, type 1, (449), (driveways) (441E70500)CY14$555.00$800.00$555.00$555.00$503.00$800.00
596" non-reinforced concrete pavement, class QC MS (452E10050)SY189$132.00$85.00$94.00$100.00$87.00$96.00
608" non-reinforced concrete pavement, class QC MS (452E12050)SY68$148.00$115.00$227.00$135.00$135.00$101.00
61Compacted aggregate (617E10100)CY305$90.00$50.00$118.00$105.00$76.00$123.00
628" water main polyvinyl chloride pipe and fittings, AWWA C900, DR14 (638E01710)FT125$123.00$280.00$123.00$200.00$211.00$387.00
6312" water main polyvinyl chloride pipe and fittings, AWWA C900, DR-14 (638E02750)FT2,070$133.00$178.00$133.00$185.00$121.00$187.00
648" gate valve and valve box (638E07900)EACH4$4,000.00$3,200.00$4,000.00$2,800.00$3,925.00$3,610.00
6512" gate valve and valve box (638E08100)EACH7$6,700.00$5,000.00$6,700.00$4,200.00$5,800.00$6,900.00
666" fire hydrant, as per plan (638E10201)EACH5$9,700.00$12,500$9,700.00$8,650.00$8,200.00$11,100
67Fire hydrant removed (638E10480)EACH4$1,000.00$500.00$1,000.00$400.00$360.00$3,650.00
68Special - cut and plug existing 8" water line, hea (638E20880)EACH4$3,000.00$1,200.00$3,000.00$985.00$765.00$1,970.00
69Water work, misc.:8" cap and plug (638E98000)EACH1$4,000.00$1,200.00$4,000.00$1,600.00$530.00$1,960.00
70Water work, misc.:12" water main HDPE directional (638E98600)FT150$500.00$250.00$500.00$185.00$290.00$304.00
71Ground mounted support, no. 3 post (630E03100)FT119.50$18.00$19.88$25.00$19.90$14.00$19.90
72Ground mounted support, no. 3 post, as per plan (630E03101)FT37.50$30.50$21.74$30.00$21.50$22.00$22.00
73Sign, flat sheet (630E80100)SF61.38$25.00$23.19$25.00$23.20$29.00$23.00
74Sign, flat sheet, as per plan (630E80101)SF33.50$34.50$26.04$35.00$26.05$37.00$26.00
75Removal of ground mounted sign and disposal (630E84900)EACH16$10.00$16.10$30.00$16.10$47.00$16.10
76Removal of ground mounted post support and disposal (630E86002)EACH14$20.00$21.47$30.00$21.50$70.00$21.00
77Edge line, 6" (644E00104)MI0.99$6,240.00$3,601.00$5,350.00$3,601.00$6,230.00$5,400.00
78Center line (644E00300)MI0.49$8,320.00$5,700.00$9,000.00$5,700.00$10,500$9,000.00
79Stop line (644E00500)FT53$9.50$13.00$11.50$13.00$13.50$11.50
80Law enforcement officer with patrol car for assistance (614E11110)HR20$90.00$70.00$80.00$100.00$64.00$130.00
81Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH14$2,280.00$2,400.00$2,400.00$2,200.00$2,560.00$2,200.00
82Detour signing (614E12420)LS1$8,000.00$8,000.00$8,000.00$10,500$13,180$17,600
83Work zone sign support (614E12440)EACH35$50.00$50.00$50.00$50.00$110.00$385.00
84Work zone marking sign (614E12460)EACH35$100.00$100.00$100.00$100.00$110.00$140.00
85Barrier reflector, type 1, 1 way (614E13310)EACH86$28.00$15.00$15.00$15.00$29.00$15.00
86Object marker, one way (614E13350)EACH86$32.00$18.00$18.00$16.00$35.00$25.00
87Portable changeable message sign, as per plan (614E18601)SNMT24$1,500.00$1,500.00$1,500.00$950.00$990.00$730.00
88Work zone edge line, class I, 6" (614E22010)MI1.89$1,800.00$1,800.00$1,490.00$1,800.00$1,650.00$6,300.00
89Roads for maintaining traffic (615E10000)LS1$35,000$23,000$15,000$34,000$5,250.00$40,300
90Pavement for maintaining traffic, class A (615E20000)SY1,340$64.00$100.00$75.00$65.00$94.00$80.00
91Water (616E10000)MGAL8$75.00$100.00$1.00$30.00$350.00$87.00
92Portable barrier, unanchored (622E41100)FT3,946$18.00$28.15$28.15$18.00$37.00$17.40
93Premium for contract performance bond and for payment bond (103E05000)LS1$18,000$20,400$12,500$16,500$29,000$17,500
94Maintaining traffic (614E11000)LS1$52,200$75,000$43,500$65,000$23,000$9,800.00
95Construction layout stakes and surveying (623E10000)LS1$30,400$10,000$35,000$27,000$32,000$9,900.00
96Mobilization, as per plan (624E10001)LS1$122,000$100,000$86,000$130,000$136,600$100,000
97Special - record construction drawings (690E98400)LS1$100.00$2,000.00$2,000.00$4,200.00$2,800.00$7,700.00
10012" conduit, type C (611E04600)FT250$60.00$100.00$59.25$79.00$49.00$80.00
10118" conduit, type C (611E07600)FT450$74.00$110.00$83.50$104.00$64.00$92.00
10224" conduit, type C (611E10600)FT737$95.00$120.00$107.00$135.00$76.00$122.00
ODOT contract 250093: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of February 27, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way