ODOT letting results, April 18, 2024
34 contracts let by Ohio DOT on April 18, 2024, $106,469,681 in low bids, a median of 3 bidders per contract. On the 34 with an engineer's estimate, the low bid came in under it 23 times; median low bid -10% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 34
- Low bids, total
- $106,469,681
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240202 | CUY-IR 490-00.00 Major Rehab (PART 1 AND PART 2) (MAJOR RECONSTRUCTION) | CUY | 3 | Karvo Companies Inc | $61,858,000 | $66,093,253 | +7.0% | +35% | ODOT |
| 243004 | RIC-SR 13-11.01 (FOUR LANE RESURFACING) | RIC | 2 | Kokosing Construction Company Inc | $18,484,452 | $19,169,951 | +4.0% | -32% | ODOT |
| 240245 | ROS-US 50-19.35 (FOUR LANE RESURFACING) | ROS | 2 | Shelly & Sands Inc | $3,198,115 | $3,247,963 | +2.0% | +32% | ODOT |
| 240231 | BUT-SR 4-23.17 (BRIDGE REPAIR) | BUT | 2 | Eagle Bridge Co | $1,796,676 | $2,685,889 | +49% | +20% | ODOT |
| 240236 | HEN-SR 110-03.51 Slope Repair (SLIDE REPAIR) | HEN | 4 | Alan Stone Co Inc | $1,714,450 | $1,799,829 | +5.0% | +15% | ODOT |
| 244009 | D07-CR-FY24 (CULVERT REPLACEMENT) | District 7 | 1 | Fenson Contracting LLC | $1,707,790 | -8.0% | ODOT | ||
| 240248 | WAY-SR 57-10.32 (INTERSECTION) | WAY | 5 | Fechko Excavating LLC | $1,462,896 | $1,493,906 | +2.0% | -13% | ODOT |
| 240247 | TRU-SR 46/46D-15.08/00.00 (TWO LANE RESURFACING) | TRU | 3 | Shelly & Sands Inc | $1,206,196 | $1,255,000 | +4.0% | -10% | ODOT |
| 240252 | D04-SP FY2024 (East) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 4 | Karvo Companies Inc | $1,175,000 | $1,562,612 | +33% | -20% | ODOT |
| 240233 | D08-Bridge/Wall Repairs (SLIDE REPAIR) | District 8 | 4 | Sunesis Construction Co | $1,038,606 | $1,059,818 | +2.0% | -10% | ODOT |
| 240232 | CLE-SR 125-11.98 (INTERSECTION) | CLE | 3 | John R Jurgensen Company | $986,496 | $1,028,077 | +4.0% | -12% | ODOT |
| 240235 | GAL-TR 342-00.04 (BRIDGE REPLACEMENT (1 BRIDGE)) | GAL | 2 | Axis Civil Construction LLC | $949,787 | $980,374 | +3.0% | -11% | ODOT |
| 240251 | D02-ITS Maint FY 2024 (SIGNALIZATION) | District 2 | 3 | Perram Electric Inc | $899,188 | $1,183,000 | +32% | -30% | ODOT |
| 240230 | ATH-SR 144-06.04 (SLIDE REPAIR) | ATH | 4 | Alan Stone Co Inc | $805,394 | $904,252 | +12% | -23% | ODOT |
| 240237 | LIC-MR 297-00.03 (Loop Rd.) (RELOCATION) | LIC | 7 | Eclipse Co LLC | $797,615 | $889,697 | +12% | -22% | ODOT |
| 240244 | PRE-Type A Guardrail FY24 (GUARDRAIL REBUILDING) | PRE | 1 | Lake Erie Construction Company | $778,175 | +5.0% | ODOT | ||
| 240241 | MIA-Looney Road Resurfacing (TWO LANE RESURFACING) | MIA | 2 | Walls Bros Asphalt Co Inc | $644,477 | $645,000 | 0.0% | +1.0% | ODOT |
| 240246 | SCI-SR 335-(11.70)(12.00) (CULVERT REPLACEMENT) | SCI | 2 | R C Construction Company and Son Inc | $577,531 | $577,586 | 0.0% | -1.0% | ODOT |
| 240257 | MED-SR 57/SR 94-09.78/18.84 (CULVERT REPLACEMENT) | MED | 7 | Adena Corporation | $554,295 | $566,253 | +2.0% | -1.0% | ODOT |
| 240240 | MEG-CR 39-02.025 (BRIDGE REPLACEMENT (1 BRIDGE)) | MEG | 4 | D G M Inc | $543,733 | $591,182 | +9.0% | -23% | ODOT |
| 240239 | MAH-Stavich Trail (Phase 1) (BIKEWAYS) | MAH | 2 of 3 | $517,593 | $570,546 | +10% | -7.0% | ODOT | |
| 240250 | BEL-SR 379-06.34 (SLIDE REPAIR) | BEL | 4 | Dennison Bridge Inc | $507,590 | $568,116 | +12% | -26% | ODOT |
| 240238 | MAH-SR 14-09.18 (SLIDE REPAIR) | MAH | 4 | Ohio-West Virginia Excavating Co | $474,423 | $493,962 | +4.0% | -23% | ODOT |
| 240256 | LUC-ODNR Maumee Bay St Pk FY24 (MICROSURFACING) | LUC | 2 | Pavement Maintenance Systems LLC | $470,687 | $680,782 | +45% | +26% | ODOT |
| 244010 | MIA-/MER-IR 75/SR 119-16.91/13.74 (CULVERT REPLACEMENT) | MIA | 3 | BCC Ohio Inc | $461,445 | $552,643 | +20% | -16% | ODOT |
| 240255 | D12-TSG FY2024 (SIGNALIZATION) | District 12 | 2 | Trafftech Inc | $432,251 | $435,535 | +1.0% | +2.0% | ODOT |
| 240253 | D10-RPM FY2024 (RAISED PAVEMENT MARKERS) | District 10 | 2 | A & A Safety Inc | $412,799 | $427,512 | +4.0% | -2.0% | ODOT |
| 240258 | MIA-/MER-US 40/US 127-01.637/08.981 (SIGNALIZATION) | MIA | 3 | Miller Cable Company | $374,500 | $402,800 | +8.0% | +5.0% | ODOT |
| 244011 | WOO-SR 582-16.35 Bridge Repl. (CULVERT REPLACEMENT) | WOO | 4 | Advanced Excavating & Demolition LLC | $324,337 | $329,484 | +2.0% | -12% | ODOT |
| 240243 | MOE-TR 1206-00.01 (BRIDGE REPLACEMENT (1 BRIDGE)) | MOE | 3 | Ohio-West Virginia Excavating Co | $309,173 | $383,704 | +24% | -10% | ODOT |
| 240234 | FRA-SR 161-08.66 Olentangy River Rd (INTERSECTION) | FRA | 3 | Cap-Stone & Associates Inc | $304,871 | $326,330 | +7.0% | +38% | ODOT |
| 240229 | ADA-SR 32-11.98 & 11.99 Liners (CULVERT REPLACEMENT) | ADA | 3 | Axis Civil Construction LLC | $304,582 | $369,566 | +21% | -19% | ODOT |
| 240249 | ATH-Wallace O'Dowd WLA (MISCELLANEOUS) | ATH | 6 | Parker Corporation | $302,697 | $307,339 | +2.0% | +6.0% | ODOT |
| 240242 | MOE-CR VAR PM FY2024 (PAVEMENT MARKING) | MOE | 2 | The Aero-Mark Company LLC | $93,861 | $101,680 | +8.0% | -35% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.