ODOT letting results, May 9, 2024
35 contracts let by Ohio DOT on May 9, 2024, $58,780,848 in low bids, a median of 3 bidders per contract. On the 35 with an engineer's estimate, the low bid came in under it 19 times; median low bid -2.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 35
- Low bids, total
- $58,780,848
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240276 | MOT-SR 725-14.41 (MISCELLANEOUS) | MOT | 2 | John R Jurgensen Company | $5,538,743 | $5,707,019 | +3.0% | +13% | ODOT |
| 240277 | MOT-Vandalia Bike-way Connector (BIKEWAYS) | MOT | 5 | Brumbaugh Construction Inc | $4,355,000 | $4,649,499 | +7.0% | +12% | ODOT |
| 240272 | LOR-SR 611-00.01 (FOUR LANE RESURFACING) | LOR | 2 | Kokosing Construction Company Inc | $4,331,205 | $5,038,037 | +16% | +9.0% | ODOT |
| 240295 | D12-D4/D12 ITS Camera Additions (SIGNALIZATION) | District 12 | 5 | Perram Electric Inc | $4,249,429 | $4,492,000 | +6.0% | +25% | ODOT |
| 240263 | CUY-Eagle Avenue Bridge (DEMOLITION) | CUY | 3 | Ruhlin Company | $4,215,262 | $2,473,001 | -41% | +39% | ODOT |
| 240259 | ASD-US 42-03.78 (TWO LANE RESURFACING) | ASD | 2 | Kokosing Construction Company Inc | $4,145,366 | $4,388,386 | +6.0% | -5.0% | ODOT |
| 240285 | UNI-SR 736-04.06 Part 1 & 2 (BRIDGE REPAIR) | UNI | 7 | George J Igel & Co Inc | $3,654,556 | $3,680,590 | +1.0% | -5.0% | ODOT |
| 240274 | MEG-US 33-19.00 (MINOR RECONSTRUCTION) | MEG | 6 | Shelly Company | $3,466,086 | $3,943,784 | +14% | -13% | ODOT |
| 240288 | WAY-US 30-00.00 (FOUR LANE RESURFACING) | WAY | 2 | Kokosing Construction Company Inc | $3,009,162 | $3,569,963 | +19% | -15% | ODOT |
| 240284 | TUS-NP Shared Use Path Phase 1 (BIKEWAYS) | TUS | 2 | Shelly & Sands Inc | $2,882,943 | $2,953,035 | +2.0% | +18% | ODOT |
| 248003 | D12-GR FY2024 (GUARDRAIL REBUILDING) | District 12 | 2 | Cuyahoga Fence LLC | $2,654,030 | $2,707,320 | +2.0% | +15% | ODOT |
| 240290 | D04-PM FY2024 (West) (PAVEMENT MARKING) | District 4 | 2 | The Aero-Mark Company LLC | $2,500,000 | $2,798,578 | +12% | +3.0% | ODOT |
| 240289 | WOO-IR 280-05.07 Slide Repair (SLIDE REPAIR) | WOO | 4 | Great Lakes Demolition Company | $1,599,083 | $2,388,160 | +49% | -20% | ODOT |
| 244014 | DEF-/PAU-SR 111-0.37/23.82 (SLIDE REPAIR) | DEF | 2 | Advanced Excavating & Demolition LLC | $1,188,468 | $1,943,050 | +63% | -8.0% | ODOT |
| 240275 | MOT-Spinning Rd Improvement Ph 2 (TWO LANE RESURFACING) | MOT | 2 | John R Jurgensen Company | $1,147,452 | $1,180,610 | +3.0% | +13% | ODOT |
| 240291 | D04-SP FY2024 (West) (SPOT PATCHING / PAVEMENT REPAIR) | District 4 | 3 | Karvo Companies Inc | $1,075,000 | $1,089,724 | +1.0% | +9.0% | ODOT |
| 244012 | CAR-SR 332-10.40 (SIDEWALK) | CAR | 2 | Alan Stone Co Inc | $1,037,002 | $1,386,607 | +34% | +44% | ODOT |
| 240262 | COS-SR 751-03.86 (BRIDGE REPAIR) | COS | 1 | Stanley Miller Construction Company | $865,475 | +147% | ODOT | ||
| 240298 | PIK-SR 335-20.78 (SLIDE REPAIR) | PIK | 3 | Shelly & Sands Inc | $681,389 | $708,237 | +4.0% | -24% | ODOT |
| 240282 | STA-Middle Branch Trail (BIKEWAYS) | STA | 4 | Shelly Company | $610,811 | $632,807 | +4.0% | +16% | ODOT |
| 240281 | NOB-SR 147-09.93 (SLIDE REPAIR) | NOB | 4 | Alan Stone Co Inc | $573,870 | $624,379 | +9.0% | -21% | ODOT |
| 240287 | WAS-SR 550-14.30 (SLIDE REPAIR) | WAS | 3 | Ohio-West Virginia Excavating Co | $546,273 | $653,971 | +20% | -28% | ODOT |
| 240296 | FRA-IR 270 CRACKSEAL PPM-FY24 (CRACK SEALING) | FRA | 2 | Scodeller Construction Inc | $470,665 | $858,381 | +82% | +7.0% | ODOT |
| 240278 | MRG-Chesterhill Streetscape Ph 1 (SIDEWALK) | MRG | 3 | Shelly & Sands Inc | $469,943 | $478,049 | +2.0% | -1.0% | ODOT |
| 240273 | MED-SR 94-07.64 (TWO LANE RESURFACING) | MED | 4 | D L Smith Concrete LLC | $467,063 | $542,591 | +16% | -3.0% | ODOT |
| 240279 | MRG-SR 37-08.09 (SLIDE REPAIR) | MRG | 4 | Ohio-West Virginia Excavating Co | $462,188 | $487,003 | +5.0% | -21% | ODOT |
| 240280 | MRW-SR 229-05.43 (TWO LANE RESURFACING) | MRW | 2 | Kokosing Construction Company Inc | $451,939 | $551,046 | +22% | -2.0% | ODOT |
| 240271 | HAS-US 22-05.43 (SLIDE REPAIR) | HAS | 5 | Dennison Bridge Inc | $408,062 | $462,116 | +13% | -19% | ODOT |
| 240265 | D04-TSG FY2024 (SIGNALIZATION) | District 4 | 3 | Cornerstone Electric Inc | $399,980 | $458,808 | +15% | -18% | ODOT |
| 240297 | JAC-US 35-15.36 Slide (SLIDE REPAIR) | JAC | 6 | Alan Stone Co Inc | $308,561 | $331,331 | +7.0% | -11% | ODOT |
| 240294 | D09-GR-FY2024 (Safety) (GUARDRAIL REBUILDING) | District 9 | 2 | M P Dory Co | $289,126 | $353,125 | +22% | -30% | ODOT |
| 244015 | JEF-SR 7 Brilliant Park-N-Ride (PARKING AREAS) | JEF | 2 | Alan Stone Co Inc | $257,054 | $307,997 | +20% | +33% | ODOT |
| 240293 | D07-RPM FY24 (RAISED PAVEMENT MARKERS) | District 7 | 2 | W L Markers Inc | $236,373 | $251,899 | +7.0% | -20% | ODOT |
| 240283 | TUS-Miskimen Drive Sidewalks (SIDEWALK) | TUS | 3 | Stanley Miller Construction Company | $140,326 | $140,829 | 0.0% | +4.0% | ODOT |
| 240286 | UNI-SR 47-14.54 (SIDEWALK) | UNI | 2 | Brennstuhl Construction Inc | $92,966 | $138,697 | +49% | -15% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.