M P Dory Co: ODOT bid record
M P Dory Co submitted 127 bids on Ohio DOT contracts in the data, from 27 FEB 2020 to 12 NOV 2026, and was the low bidder on 39 of them (31%). When it was not low, its total sat a median +14% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $41,829,833
- Latest bid
- 12 NOV 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 26 | 5 | 19% |
| 2021 | 17 | 5 | 29% |
| 2022 | 21 | 7 | 33% |
| 2023 | 19 | 5 | 26% |
| 2024 | 17 | 6 | 35% |
| 2025 | 17 | 8 | 47% |
| 2026 | 10 | 3 | 30% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| District 10 | 14 | 4 | 29% |
| District 5 | 14 | 4 | 29% |
| FRA | 10 | 8 | 80% |
| District 6 | 8 | 1 | 13% |
| District 9 | 7 | 3 | 43% |
| CUY | 6 | 5 | 83% |
| District 7 | 6 | 2 | 33% |
| District 4 | 5 | 0 | 0% |
| LIC | 4 | 3 | 75% |
| MRG | 3 | 0 | 0% |
| MEG | 2 | 1 | 50% |
| District 11 | 2 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 74 | 74 (100%) | $1.00 | $1.00 |
| Anchor assembly, MGS type T | 606E26550 | EACH | 63 | 29 (46%) | $1,150.00 | $1,260.00 |
| Removal of ground mounted post support and disposal | 630E86002 | EACH | 47 | 29 (62%) | $15.00 | $23.50 |
| Guardrail, type MGS with long posts | 606E15100 | FT | 44 | 22 (50%) | $21.00 | $23.60 |
| Removal of ground mounted sign and reerection | 630E85100 | EACH | 36 | 22 (61%) | $50.00 | $75.00 |
| Guardrail, type MGS | 606E15050 | FT | 51 | 19 (37%) | $20.00 | $22.73 |
| Maintenance of traffic for shoulder closure | 614E13900 | EACH | 25 | 19 (76%) | $150.00 | $175.00 |
| Guardrail rebuilt, type MGS, as per plan | 606E16051 | FT | 23 | 18 (78%) | $14.50 | $16.50 |
| Guardrail removed | 202E38000 | FT | 55 | 16 (29%) | $2.50 | $2.50 |
| Removal of ground mounted sign and disposal | 630E84900 | EACH | 42 | 16 (38%) | $12.00 | $20.00 |
| Anchor assembly, MGS type B | 606E26050 | EACH | 31 | 16 (52%) | $2,050.00 | $2,225.00 |
| Ground mounted support, no. 3 post | 630E03100 | FT | 38 | 15 (39%) | $12.50 | $15.20 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Lake Erie Construction Company | 111 | 63 of 111 |
| PDK Construction Inc | 28 | 21 of 28 |
| Cleveland Barricading Systems LLC | 21 | 13 of 21 |
| Cuyahoga Fence LLC | 18 | 10 of 18 |
| Perram Electric Inc | 16 | 14 of 16 |
| Complete General Construction Company | 16 | 14 of 16 |
| Miller Cable Company | 13 | 9 of 13 |
| Jess Howard Electric Co | 5 | 1 of 5 |
| A & A Safety Inc | 5 | 2 of 5 |
| Trafftech Inc | 4 | 4 of 4 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260499 | DEL | DEL-/UNI-SIGN-FY2027 (SIGNING) | 3 of 3 | $792,822 | +92% |
| 12 NOV 2026 | 260522 | MUS | MUS-Flat Sheet Signs 2027 (SIGNING) | 1 of 2 | $2,046,794 | Low, 13% under the second |
| 01 OCT 2026 | 260446 | District 9 | D09-Guardrail Project FY2027 (GUARDRAIL REBUILDING) | 4 of 4 | $1,168,220 | +22% |
| 16 JUL 2026 | 260336 | District 5 | D05-GR FY2027 (Ding N Dent) (GUARDRAIL REBUILDING) | 2 of 2 | $1,296,346 | +10% |
| 11 JUN 2026 | 260289 | PER | PER-CR VAR GR FY2027 (GUARDRAIL REBUILDING) | 2 of 3 | $249,745 | 0.0% |
| 11 JUN 2026 | 260295 | District 6 | D06-GR-FY2027 (GUARDRAIL REBUILDING) | 2 of 2 | $899,476 | +8.0% |
| 11 JUN 2026 | 260300 | FRA | FRA-GR-FY2027 (GUARDRAIL REBUILDING) | 1 of 2 | $1,858,557 | Low, 24% under the second |
| 19 FEB 2026 | 260082 | District 10 | D10-Extrusheet Sign FY2026 (SIGNING) | 1 of 2 | $1,072,887 | Low, 11% under the second |
| 29 JAN 2026 | 260073 | District 9 | D09-GR-FY2026 (GUARDRAIL REBUILDING) | 3 of 3 | $1,089,287 | +19% |
| 15 JAN 2026 | 260030 | WYA | WYA-US 23-09.28 (SIGNING) | 3 of 3 | $388,930 | +54% |
| 18 DEC 2025 | 250584 | District 5 | D05-Guardrail FY2026 (GUARDRAIL REBUILDING) | 2 of 2 | $2,994,927 | +4.0% |
| 18 DEC 2025 | 250604 | District 7 | D07-GR FY 2026 (GUARDRAIL REBUILDING) | 1 of 2 | $511,844 | Low, 1.0% under the second |
| 23 OCT 2025 | 250494 | District 10 | D10-General System GR FY2026 (GUARDRAIL REBUILDING) | 2 of 3 | $2,419,389 | +8.0% |
| 09 OCT 2025 | 250483 | GUE | GUE-Flat Sheet Signs 2026 (SIGNING) | 1 of 3 | $1,420,663 | Low, 7.0% under the second |
| 14 AUG 2025 | 250386 | FRA | FRA-GR FY26 (GUARDRAIL REBUILDING) | 1 of 2 | $1,872,269 | Low, 15% under the second |
| 26 JUN 2025 | 250329 | District 5 | D05-GR FY2026 (Ding N Dent) (GUARDRAIL REBUILDING) | 3 of 3 | $1,218,491 | +6.0% |
| 26 JUN 2025 | 250331 | FRA | FRA-IR 70-12.14 FEN (FENCING) | 1 of 2 | $168,837 | Low, 61% under the second |
| 12 JUN 2025 | 250313 | District 6 | D06-GR FY26 (GUARDRAIL REBUILDING) | 2 of 2 | $765,376 | +7.0% |
| 22 MAY 2025 | 250272 | COL | COL-US 30/VAR-25.09/VAR,TUS-IR 77-13.00 (SIGNING) | 1 of 2 | $1,722,285 | Low, 1.0% under the second |
| 08 MAY 2025 | 250247 | FRA | FRA-US 23/VAR-23.26/VAR-SIGN (SIGNING) | 2 of 2 | $929,998 | +25% |
| 08 MAY 2025 | 250255 | LIC | LIC-SR 16-05.38 (MISCELLANEOUS) | 1 of 3 | $391,803 | Low, 4.0% under the second |
| 08 MAY 2025 | 250268 | District 12 | D12-SIGN FY2025 (SIGNING) | 2 of 2 | $343,821 | +4.0% |
| 24 APR 2025 | 250215 | District 5 | D05-Guardrail FY2025 (GUARDRAIL REBUILDING) | 1 of 3 | $1,859,786 | Low, 4.0% under the second |
| 13 FEB 2025 | 250110 | District 10 | D10-Extrusheet Sign FY2025 (SIGNING) | 1 of 2 | $813,279 | Low, 25% under the second |
| 30 JAN 2025 | 250045 | District 10 | D10-General System GR FY2025 (GUARDRAIL REBUILDING) | 2 of 3 | $2,415,809 | +8.0% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.