ODOT contract 250329 bid tabulation

D05-GR FY2026 (Ding N Dent) (GUARDRAIL REBUILDING). Let by Ohio DOT on June 26, 2025, District 5. 3 bids received; low bid $1,148,225 by Lake Erie Construction Company, -3.1% against the engineer's estimate of $1,185,000.

Owner
Ohio DOT
Letting
26 JUN 2025
Pay items
114
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Lake Erie Construction Company$1,148,225Low-3.0%
2Cuyahoga Fence LLC$1,186,443+3.0%0.0%
3M P Dory Co$1,218,491+6.0%+3.0%
ODOT contract 250329: bids by rank

Engineer's estimate: $1,185,000.

Bid tabulation

LinePay itemUnitQuantity1. Lake Erie Construction Company2. Cuyahoga Fence LLC3. M P Dory Co
1Guardrail removed (202E38000)FT10,000$2.00$2.00$2.00
2Bridge railing removed (202E38500)FT500$3.50$3.50$5.00
3Anchor assembly removed, type A (202E42000)EACH10$295.00$250.00$350.00
4Anchor assembly removed, type E (202E42010)EACH40$195.00$225.00$200.00
5Anchor assembly removed, type T (202E42040)EACH10$100.00$125.00$125.00
6Anchor assembly removed, type B (202E42050)EACH5$120.00$125.00$175.00
7Bridge terminal assembly removed (202E47000)EACH5$75.00$100.00$95.00
8Impact attenuator removed (202E47800)EACH2$325.00$300.00$199.00
9Embankment (203E20000)CY10$76.00$60.00$100.00
10Bridge railing rebuilt, as per plan (517E75501)FT1,000$16.40$18.00$12.50
11Guardrail, type 5 (606E13000)FT8,000$18.00$19.35$18.80
12Guardrail, type 5, using 9 foot posts (606E13030)FT100$24.40$25.00$25.00
13Guardrail, type 5A (606E13050)FT100$27.20$27.50$28.00
14Guardrail, type MGS (606E15050)FT1,000$20.40$21.00$20.00
15Guardrail, type MGS with long posts (606E15100)FT200$23.20$24.00$21.00
16Guardrail, barrier design, type 5 (606E15500)FT200$34.60$34.00$32.50
17Guardrail rebuilt, as per plan (606E16001)FT5,000$16.00$15.75$13.50
18Guardrail rebuilt, type MGS, as per plan (606E16051)FT750$17.20$16.50$14.00
19Guardrail, type 5, long-span (606E17290)FT25$29.20$25.00$32.00
20Guardrail, type MGS, long-span (606E17360)FT25$29.80$25.50$40.00
21Replace existing guardrail blockout (606E17700)EACH200$22.50$16.50$10.00
22Replace existing guardrail blockout, type MGS (606E17750)EACH100$24.50$18.50$15.00
23Guardrail post, as per plan (606E17901)EACH300$85.00$65.00$60.00
24Guardrail post, 9 feet (606E18500)EACH50$25.00$35.00$60.00
25Guardrail post, 9 feet, as per plan (606E18501)EACH30$90.00$90.00$60.00
26Anchor assembly, type A (606E25000)EACH10$1,250.00$1,300.00$1,500.00
27Anchor assembly, MGS type A (606E25550)EACH1$1,475.00$1,300.00$1,500.00
28Anchor assembly, type B (606E26000)EACH5$2,520.00$1,785.00$2,000.00
29Anchor assembly, MGS type B (606E26050)EACH1$2,575.00$1,885.00$2,500.00
30Anchor assembly, MGS type E (NCHRP 350 or MASH 201 (606E26150)EACH60$2,820.00$3,100.00$2,750.00
31Anchor assembly, type T (606E26500)EACH15$940.00$775.00$950.00
32Anchor assembly, MGS type T (606E26550)EACH5$1,250.00$950.00$1,200.00
33Anchor assembly rebuilt, type A, as per plan (606E27801)EACH12$700.00$700.00$1,000.00
34Anchor assembly rebuilt, type B, as per plan (12.5 (606E27841)EACH10$420.00$425.00$525.00
35Anchor assembly rebuilt, type B, as per plan (buff (606E27841)EACH5$110.00$115.00$185.00
36Anchor assembly rebuilt, type B, as per plan (cabl (606E27841)EACH2$175.00$175.00$275.00
37Anchor assembly rebuilt, type B, as per plan (wood (606E27841)EACH5$20.00$20.00$25.00
38Anchor assembly rebuilt, type B, as per plan (wood (606E27841)EACH10$135.00$125.00$95.00
39Anchor assembly rebuilt, type E, as per plan (cabl (606E27851)EACH6$130.00$125.00$100.00
40Anchor assembly rebuilt, type E, as per plan (cabl (606E27851)EACH5$195.00$200.00$275.00
41Anchor assembly rebuilt, type E, as per plan (deep (606E27851)EACH15$460.00$400.00$385.00
42Anchor assembly rebuilt, type E, as per plan (deep (606E27851)EACH30$375.00$350.00$250.00
43Anchor assembly rebuilt, type E, as per plan (guar (606E27851)EACH5$985.00$950.00$1,100.00
44Anchor assembly rebuilt, type E, as per plan (hba (606E27851)EACH8$325.00$300.00$250.00
45Anchor assembly rebuilt, type E, as per plan (hba (606E27851)EACH15$325.00$250.00$200.00
46Anchor assembly rebuilt, type E, as per plan (post (606E27851)EACH6$170.00$165.00$100.00
47Anchor assembly rebuilt, type E, as per plan (stee (606E27851)EACH2$150.00$150.00$100.00
48Anchor assembly rebuilt, type E, as per plan (stru (606E27851)EACH6$155.00$150.00$150.00
49Anchor assembly rebuilt, type E, as per plan (wood (606E27851)EACH20$15.00$15.00$15.00
50Anchor assembly rebuilt, type E, as per plan (wood (606E27851)EACH30$100.00$100.00$40.00
51Anchor assembly rebuilt, type T (606E27900)EACH10$685.00$650.00$700.00
52Anchor assembly rebuilt, MGS type T (606E27910)EACH2$825.00$850.00$700.00
53Bridge terminal assembly, type TST (606E32160)EACH2$1,620.00$1,650.00$1,750.00
54Bridge terminal assembly rebuilt, type TST, as per plan (606E32171)EACH2$250.00$200.00$200.00
55Bridge terminal assembly rebuilt, type TST, as per plan (606E32171)EACH2$425.00$400.00$1,125.00
56Bridge terminal assembly rebuilt, type TST, as per plan (606E32171)EACH2$320.00$300.00$500.00
57Bridge terminal assembly, type 1 (606E35000)EACH5$1,280.00$850.00$1,600.00
58MGS bridge terminal assembly, type 1 (606E35002)EACH2$2,175.00$1,700.00$2,400.00
59Bridge terminal assembly rebuilt, type 1, as per plan (606E35011)EACH2$240.00$250.00$200.00
60Bridge terminal assembly rebuilt, type 1, as per plan (606E35011)EACH5$575.00$550.00$1,125.00
61Bridge terminal assembly rebuilt, type 1, as per plan (606E35011)EACH5$235.00$225.00$450.00
62MGS bridge terminal assembly rebuilt, type 1, as per plan (606E35013)EACH2$400.00$400.00$200.00
63MGS bridge terminal assembly rebuilt, type 1, as per plan (606E35013)EACH2$425.00$500.00$1,125.00
64MGS bridge terminal assembly rebuilt, type 1, as per plan (606E35013)EACH2$220.00$250.00$500.00
65Bridge terminal assembly, type 2 (606E35100)EACH2$425.00$425.00$500.00
66MGS bridge terminal assembly, type 2 (606E35102)EACH2$450.00$450.00$500.00
67Bridge terminal assembly, type 4 (606E35140)EACH2$725.00$800.00$950.00
68Bridge terminal assembly rebuilt, type 4, as per plan (606E35151)EACH6$240.00$250.00$200.00
69Bridge terminal assembly rebuilt, type 4, as per plan (606E35151)EACH15$85.00$90.00$350.00
7036" concrete anchor removed and replaced, as per plan (606E39001)EACH1$625.00$500.00$850.00
71Special - reshaping berm (606E50000)FT150$1.20$1.10$2.00
72Special - cable barrier (anchor trigger post) (606E54950)EACH2$775.00$725.00$2,500.00
73Special - cable barrier (line post) (606E54950)EACH500$90.00$125.00$145.00
74Special - cable barrier, replacement cable (606E55020)FT100$7.80$10.00$10.00
75Special - cable barrier, concrete line post foundation (606E55100)EACH40$345.00$300.00$375.00
76Special - cable barrier, concrete anchor foundation with sleeve (606E55110)EACH2$750.00$800.00$1,150.00
77Special - cable barrier, anchor post (606E55140)EACH5$575.00$600.00$700.00
78Special - cable barrier, splice (606E55180)EACH5$120.00$375.00$25.00
79Special - cable barrier, post reflector (606E55190)EACH80$10.00$6.00$12.50
80Special - cable barrier, tensioning (606E55200)EACH221$220.00$200.00$275.00
81Special - cable barrier, tensioning (606E55200)EACH25$220.00$200.00$175.00
82Special - cable barrier, anchor post reset (606E55220)EACH20$275.00$250.00$500.00
83Impact attenuator, type 1 (unidirectional) (606E60002)EACH2$8,950.00$6,800.00$7,800.00
84Impact attenuator, type 1 (bidirectional) (606E60012)EACH2$8,950.00$6,800.00$7,800.00
85Impact attenuator, type 2 (unidirectional) (variou (606E60022)EACH1$31,250$31,500$27,500
86Impact attenuator, type 2 (bidirectional) (various (606E60028)EACH1$31,650$32,000$29,500
87Impact attenuator, misc.: (1/4" X 18" X 24" soil P (606E61000)EACH2$55.00$50.00$50.00
88Impact attenuator, misc.: (3'-6" wood post #1, 2, (606E61000)EACH8$145.00$100.00$155.00
89Impact attenuator, misc.: (4'-6" foundation tube) (606E61000)EACH1$200.00$100.00$100.00
90Impact attenuator, misc.: (all components post # 4 (606E61000)EACH2$2,350.00$2,000.00$2,000.00
91Impact attenuator, misc.: (all components post #1 (606E61000)EACH1$2,420.00$2,250.00$3,250.00
92Impact attenuator, misc.: (belt nose assembly) (606E61000)EACH1$2,150.00$2,000.00$3,750.00
93Impact attenuator, misc.: (cartridge type I) (606E61000)EACH2$1,150.00$1,250.00$1,575.00
94Impact attenuator, misc.: (cartridge type II) (606E61000)EACH3$1,175.00$1,275.00$1,575.00
95Impact attenuator, misc.: (quad beam fender panel) (606E61000)EACH3$970.00$1,150.00$1,200.00
96Impact attenuator, misc.: (wood block 1'-2", post (606E61000)EACH10$75.00$50.00$20.00
97Guardrail, misc.: tubular backup (606E98000)FT50$96.00$86.00$85.00
98Guardrail, misc.: (type A anchor) (606E98100)EACH15$475.00$400.00$400.00
99Guardrail, misc.: (urgent repair) (606E98100)EACH30$575.00$600.00$1,000.00
100Guardrail, misc.:anchor assembly rebuilt, type A, (606E98100)EACH1$1,125.00$1,100.00$1,275.00
101Seeding and mulching, as per plan (659E10001)SY100$3.75$2.00$2.00
102Erosion control (832E30000)EACH1,000$1.00$1.00$1.00
103Barrier reflector, type 2 (1 way) (626E00110)EACH15$10.00$12.00$11.50
104Barrier reflector, type 2 (bidirectional) (626E00110)EACH15$10.00$12.00$12.00
105Law enforcement officer with patrol car for assistance (614E11110)HR50$55.00$85.00$75.00
106Maintenance of traffic, one lane closure on A two lane highway (614E13600)EACH200$295.00$300.00$300.00
107Maintenance of traffic, one lane closure on A four lane undivided highway (614E13700)EACH6$475.00$400.00$500.00
108Maintenance of traffic, one lane closure on A 4 lane or greater divided highway (614E13800)EACH25$650.00$600.00$1,200.00
109Maintenance of traffic for shoulder closure (614E13900)EACH250$155.00$200.00$200.00
110Railing (twin steel tube) (517E70000)FT25$195.00$185.00$225.00
111Railing (deep beam rail with steel tubular backup and type 2 steel posts and anchor bolts) (517E72300)FT200$125.00$125.00$135.00
112Railing (thrie beam retrofit) (517E72750)FT25$110.00$115.00$115.00
113Premium for contract performance bond and for payment bond (103E05000)LS1$5,820.00$17,500$7,500.00
114Mobilization (624E10000)LS1$39,250$45,000$40,000
ODOT contract 250329: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of June 26, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy