ODOT contract 250494 bid tabulation

D10-General System GR FY2026 (GUARDRAIL REBUILDING). Let by Ohio DOT on October 23, 2025, District 10. 3 bids received; low bid $2,243,023 by PDK Construction Inc, -1.8% against the engineer's estimate of $2,285,000.

Owner
Ohio DOT
Letting
23 OCT 2025
Pay items
18
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1PDK Construction Inc$2,243,023Low-2.0%
2M P Dory Co$2,419,389+8.0%+6.0%
3Lake Erie Construction Company$2,428,125+8.0%+6.0%
ODOT contract 250494: bids by rank

Engineer's estimate: $2,285,000.

Bid tabulation

LinePay itemUnitQuantity1. PDK Construction Inc2. M P Dory Co3. Lake Erie Construction Company
1Guardrail removed for storage, as per plan (202E38101)FT88,525$1.90$1.80$2.00
2Bridge railing removed (202E38500)FT2,087.50$1.80$3.50$2.40
3Bridge railing removed, as per plan (202E38501)FT2,512.50$1.60$1.00$6.00
4Guardrail, type MGS (606E15050)FT78,325$16.30$18.00$17.60
5Guardrail, type MGS half post spacing (606E15150)FT1,275$24.82$26.00$25.60
6Guardrail, type MGS, long-span (606E17360)FT25$33.70$30.00$28.20
7Rounded end section (606E20050)EACH3$55.00$65.00$75.00
8Anchor assembly, MGS type A (606E25550)EACH230$1,350.00$1,250.00$1,340.00
9Anchor assembly, MGS type E, MASH 2016 (606E26150)EACH49$2,200.00$2,250.00$2,400.00
10Anchor assembly, MGS type T (606E26550)EACH46$970.00$1,000.00$1,050.00
11Bridge terminal assembly, type 4 (606E35140)EACH83$550.00$850.00$750.00
12Special - reshaping berm (606E50000)FT87,700$0.05$0.25$0.10
13Barrier reflector, type 2, bidirectional (626E00110)EACH1,793$10.00$10.00$10.00
14Railing (deep beam rail with steel tubular backup and type 2 steel posts), as per plan (517E72307)FT2,087.50$74.70$80.00$70.00
15Railing faced (517E76200)FT2,512.50$10.10$10.00$10.00
16Premium for contract performance bond and for payment bond (103E05000)LS1$11,500$20,000$12,500
17Maintaining traffic (614E11000)LS1$22,400$15,000$32,100
18Mobilization (624E10000)LS1$11,600$25,000$40,000
ODOT contract 250494: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy