ODOT letting results, October 23, 2025
29 contracts let by Ohio DOT on October 23, 2025, $74,304,395 in low bids, a median of 3 bidders per contract. On the 29 with an engineer's estimate, the low bid came in under it 17 times; median low bid -3.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 29
- Low bids, total
- $74,304,395
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250496 | ERI-SR 2-24.50 (FOUR LANE RESURFACING) | ERI | 3 | Gerken Paving Inc | $12,841,483 | $12,842,123 | 0.0% | -3.0% | ODOT |
| 250459 | CRA-US 30-08.42 (BRIDGE REPAIR) | CRA | 4 | Shelly & Sands Inc | $7,642,888 | $7,823,265 | +2.0% | -15% | ODOT |
| 250500 | LAK-US 6-02.06 Super (BRIDGE REPAIR) | LAK | 3 | J D Williamson Construction Co Inc | $7,000,047 | $7,440,546 | +6.0% | +8.0% | ODOT |
| 250504 | MUS-/LIC-IR 70-00.76/28.91 (FOUR LANE RESURFACING) | MUS | 3 | Shelly Company | $5,998,675 | $6,181,669 | +3.0% | +4.0% | ODOT |
| 250489 | CLI-SR 350-07.91 (MINOR RECONSTRUCTION) | CLI | 2 | John R Jurgensen Company | $5,985,706 | $6,988,627 | +17% | -8.0% | ODOT |
| 250495 | DAR-PAVE-FY26 (TWO LANE RESURFACING) | DAR | 2 | Walls Bros Asphalt Co Inc | $4,258,356 | $4,907,863 | +15% | -8.0% | ODOT |
| 250488 | BUT-SR 747-00.00 (FOUR LANE RESURFACING) | BUT | 2 | John R Jurgensen Company | $3,671,089 | $4,069,750 | +11% | +7.0% | ODOT |
| 250486 | BEL-SR 147-04.90 (TWO LANE RESURFACING) | BEL | 3 | Shelly & Sands Inc | $3,495,534 | $3,995,934 | +14% | +6.0% | ODOT |
| 250501 | MIA-IR 75-04.92 (SPOT PATCHING / PAVEMENT REPAIR) | MIA | 3 | Eagle Bridge Co | $2,885,015 | $3,013,310 | +4.0% | +16% | ODOT |
| 250498 | HAN-SR 37-06.47 (TWO LANE RESURFACING) | HAN | 4 | Shelly Company | $2,483,258 | $2,566,712 | +3.0% | -8.0% | ODOT |
| 250494 | D10-General System GR FY2026 (GUARDRAIL REBUILDING) | District 10 | 3 | PDK Construction Inc | $2,243,023 | $2,419,389 | +8.0% | -2.0% | ODOT |
| 250514 | MAH-/TRU SIGN FY2026 (Systematic) (SIGNING) | MAH | 2 | Lake Erie Construction Company | $1,928,550 | $2,129,611 | +10% | -8.0% | ODOT |
| 250497 | GEA-SR 88/US 422-02.05/15.52 (FOUR LANE RESURFACING) | GEA | 5 | Ronyak Paving Inc | $1,595,505 | $1,684,336 | +6.0% | +5.0% | ODOT |
| 250491 | GUE-/GUE-SR 93/SR 541/SR 658 VAR (CHIP SEAL) | GUE | 2 | Shelly Company | $1,569,175 | $1,760,145 | +12% | +3.0% | ODOT |
| 250493 | D07-BP FY26 (BRIDGE PAINTING) | District 7 | 8 | Euro Paint LLC | $1,475,840 | $1,550,773 | +5.0% | -6.0% | ODOT |
| 250499 | JEF-SR 7-30.92 (CULVERT REPLACEMENT) | JEF | 6 | Marucci & Gaffney Excavating Co | $1,467,579 | $1,570,112 | +7.0% | -3.0% | ODOT |
| 250503 | MRG-SR 555-23.05 (BRIDGE REPLACEMENT (1 BRIDGE)) | MRG | 4 | Black Horse Bridge Construction Inc | $1,381,825 | $1,451,279 | +5.0% | -11% | ODOT |
| 250487 | BRO-US 62-27.42 (CULVERT REPLACEMENT) | BRO | 5 | John R Jurgensen Company | $1,244,448 | $984,259 | -21% | +25% | ODOT |
| 250512 | FRA-EXPO CENTER/OHC-FY2026 (PARKING AREAS) | FRA | 7 | Shelly Company | $1,024,417 | $1,110,197 | +8.0% | -17% | ODOT |
| 250508 | D09-CS FY2026 (CRACK SEALING) | District 9 | 2 | Scodeller Construction Inc | $798,024 | $1,191,560 | +49% | +2.0% | ODOT |
| 254029 | LAW-SR 140-00.09 (CULVERT REPLACEMENT) | LAW | 2 | Axis Civil Construction LLC | $678,613 | $716,538 | +6.0% | +19% | ODOT |
| 250506 | WAR-SR 123-09.66 (CHIP SEAL) | WAR | 5 | Shelly Company | $499,119 | $582,332 | +17% | -13% | ODOT |
| 250490 | COL-SR 164-01.66 (CULVERT REPLACEMENT) | COL | 9 | S.T.A.R.T., LLC | $478,188 | $484,876 | +1.0% | -4.0% | ODOT |
| 250502 | MOT-S. Dixie RSF Ph. 2 (TWO LANE RESURFACING) | MOT | 2 | Barrett Paving Materials Inc | $396,330 | $398,832 | +1.0% | +3.0% | ODOT |
| 250507 | D02-RPM FY2026 (RAISED PAVEMENT MARKERS) | District 2 | 4 | W L Markers Inc | $389,306 | $399,497 | +3.0% | +2.0% | ODOT |
| 250492 | D03-BH FY2026(A) (BRIDGE REPAIR) | District 3 | 4 | BCC Ohio Inc | $353,609 | $399,408 | +13% | -12% | ODOT |
| 250513 | HUR-SR 303-02.42 (CULVERT REPLACEMENT) | HUR | 8 | Great Lakes Demolition Company | $213,607 | $218,770 | +2.0% | -6.0% | ODOT |
| 250510 | ERI-US 6-11.36 (PRUNING/OR TREE/BRUSH REMOVAL) | ERI | 3 | Edwards Land Clearing Inc | $179,185 | $241,255 | +35% | -19% | ODOT |
| 250509 | D09-HS FY2026 (HERBICIDAL SPRAYING) | District 9 | 3 | Deangelo Contracting Services LLC | $126,003 | $135,905 | +8.0% | -5.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.