ODOT contract 250493 bid tabulation

D07-BP FY26 (BRIDGE PAINTING). Let by Ohio DOT on October 23, 2025, District 7. 8 bids received; low bid $1,475,840 by Euro Paint LLC, -5.6% against the engineer's estimate of $1,564,000.

Owner
Ohio DOT
Letting
23 OCT 2025
Pay items
42
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Euro Paint LLC$1,475,840Low-6.0%
2Apbn Inc$1,550,773+5.0%-1.0%
3360 Construction Company Inc$1,630,177+10%+4.0%
4Vimas Painting Company Inc$1,686,089+14%+8.0%
5Elite Contractors Inc$1,759,229+19%+12%
6Panther Industrial Painting LLC$1,978,478+34%+27%
7Legend Painting Inc$2,140,773+45%+37%
8Corrosion Resistance LTD$2,264,947+53%+45%
ODOT contract 250493: bids by rank

Engineer's estimate: $1,564,000.

Bid tabulation

LinePay itemUnitQuantity1. Euro Paint LLC2. Apbn Inc3. 360 Construction Company Inc4. Vimas Painting Company Inc5. Elite Contractors Inc6. Panther Industrial Painting LLC
1Seeding and mulching (659E10000)SY1,556$3.45$3.45$3.45$2.00$5.00$1.00
2Repair seeding and mulching (659E14000)SY78$2.50$2.50$2.50$1.00$20.00$1.00
3Commercial fertilizer (659E20000)TON0.21$680.00$680.00$680.00$2,000.00$500.00$1,000.00
4Water (659E35000)MGAL9$1.00$1.00$1.00$50.00$50.00$100.00
5Erosion control (832E30000)EACH20,000$1.00$1.00$1.00$1.00$1.00$1.00
6Law enforcement officer with patrol car for assistance (614E11110)HR400$80.00$100.00$95.00$60.00$100.00$200.00
7Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH6$2,100.33$2,100.33$2,100.33$2,500.00$2,500.00$3,000.00
8Detour signing (614E12420)LS1$5,452.65$5,452.65$5,452.65$10,000$6,000.00$10,000
9Barrier reflector, type 1 (one way) (614E13310)EACH26$14.14$14.14$14.14$15.00$15.00$25.00
10Object marker, one way (614E13350)EACH26$23.51$23.51$23.51$25.00$25.00$25.00
11Portable barrier, unanchored (622E41100)FT1,300$50.34$50.34$50.34$58.00$51.00$50.00
12Surface preparation of existing structural steel (514E00050)SF7,381$20.89$10.00$18.00$20.00$15.00$18.00
13Field painting of existing structural steel, prime coat (514E00056)SF7,381$4.64$7.00$7.00$4.00$5.00$4.00
14Field painting structural steel, intermediate coat (514E00060)SF7,381$4.65$7.00$5.00$4.00$5.00$4.00
15Field painting structural steel, finish coat (514E00066)SF7,381$4.64$7.00$4.00$3.00$5.00$4.00
16Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR12$50.00$100.00$150.00$200.00$150.00$300.00
17Final inspection repair (514E10000)EACH4$50.00$100.00$200.00$300.00$150.00$500.00
18Surface preparation of existing structural steel (514E00050)SF17,576$13.92$10.00$12.00$16.00$14.00$14.00
19Field painting of existing structural steel, prime coat (514E00056)SF17,576$3.09$5.00$6.00$3.00$3.50$4.00
20Field painting structural steel, intermediate coat (514E00060)SF17,576$3.09$3.00$3.00$2.00$3.50$4.00
21Field painting structural steel, finish coat (514E00066)SF17,576$3.09$3.00$2.50$2.00$3.00$4.00
22Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR26$50.00$100.00$150.00$200.00$150.00$300.00
23Final inspection repair (514E10000)EACH8$50.00$100.00$200.00$300.00$150.00$500.00
24Surface preparation of existing structural steel, as per plan (514E00051)SF445$54.15$100.00$75.00$220.00$300.00$150.00
25Field painting of existing structural steel, prime coat, as per plan (514E00057)SF445$12.78$50.00$50.00$70.00$60.00$50.00
26Field painting structural steel, intermediate coat, as per plan (514E00061)SF445$12.78$50.00$25.00$55.00$60.00$50.00
27Field painting structural steel, finish coat, as per plan (514E00067)SF445$12.78$50.00$25.00$55.00$60.00$50.00
28Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR1$50.00$100.00$1.00$300.00$150.00$500.00
29Final inspection repair (514E10000)EACH1$50.00$100.00$1.00$300.00$150.00$1,000.00
30Nylon reinforced neoprene sheeting (516E25000)SF14$844.96$332.15$215.00$400.00$500.00$1,000.00
31Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY326$50.00$50.00$42.00$40.00$60.00$80.00
32Removal of existing coatings from concrete surfaces (512E74000)SY209$112.54$50.00$40.00$55.00$30.00$150.00
33Surface preparation of existing structural steel (514E00050)SF18,665$13.10$10.00$14.00$16.00$14.00$14.00
34Field painting of existing structural steel, prime coat (514E00056)SF18,665$2.92$5.00$6.00$3.00$3.50$2.50
35Field painting structural steel, intermediate coat (514E00060)SF18,665$2.92$3.00$3.00$2.00$3.50$2.50
36Field painting structural steel, finish coat (514E00066)SF18,665$2.92$3.00$2.50$2.00$3.00$2.50
37Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR28$50.00$100.00$150.00$200.00$150.00$300.00
38Final inspection repair (514E10000)EACH9$50.00$100.00$200.00$300.00$150.00$500.00
39Premium on railroads' protective public liability and property damage liability insurance (100E00300)LS1$5,000.00$10,000$5,000.00$8,000.00$20,000$20,000
40Premium for contract performance bond and for payment bond (103E05000)LS1$15,000$25,000$30,000$28,000$30,000$100,000
41Maintaining traffic (614E11000)LS1$93,180$143,310$150,000$140,000$100,000$145,000
42Mobilization (624E10000)LS1$50,600$80,850$40,000$70,000$100,000$200,000
ODOT contract 250493: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 23, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy