Euro Paint LLC: ODOT bid record
Euro Paint LLC submitted 21 bids on Ohio DOT contracts in the data, from 19 NOV 2020 to 29 OCT 2026, and was the low bidder on 3 of them (14%). When it was not low, its total sat a median +23% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $9,631,270
- Latest bid
- 29 OCT 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 1 | 0 | 0% |
| 2021 | 5 | 0 | 0% |
| 2022 | 3 | 0 | 0% |
| 2023 | 1 | 0 | 0% |
| 2024 | 4 | 1 | 25% |
| 2025 | 6 | 2 | 33% |
| 2026 | 1 | 0 | 0% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| District 7 | 3 | 2 | 67% |
| HAM | 3 | 0 | 0% |
| CUY | 2 | 0 | 0% |
| District 3 | 2 | 0 | 0% |
| ATH | 1 | 0 | 0% |
| WAS | 1 | 0 | 0% |
| GEA | 1 | 0 | 0% |
| District 9 | 1 | 0 | 0% |
| BEL | 1 | 0 | 0% |
| FUL | 1 | 0 | 0% |
| CLE | 1 | 0 | 0% |
| District 1 | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Final inspection repair | 514E10000 | EACH | 89 | 88 (99%) | $100.00 | $200.00 |
| Grinding fins, tears, slivers on existing structural steel | 514E00504 | MNHR | 95 | 27 (28%) | $100.00 | $110.00 |
| Erosion control | 832E30000 | EACH | 18 | 18 (100%) | $1.00 | $1.00 |
| Surface preparation of existing structural steel | 514E00050 | SF | 93 | 15 (16%) | $12.07 | $12.00 |
| Field painting of existing structural steel, prime coat | 514E00056 | SF | 93 | 13 (14%) | $2.50 | $2.65 |
| Final inspection repair, as per plan | 514E10001 | EACH | 9 | 9 (100%) | $100.00 | $150.00 |
| Field painting structural steel, intermediate coat | 514E00060 | SF | 95 | 8 (8%) | $2.50 | $3.00 |
| Object marker, one way | 614E13350 | EACH | 12 | 7 (58%) | $19.05 | $17.00 |
| Joint sealer | 516E31000 | FT | 8 | 7 (88%) | $23.41 | $20.00 |
| Portable changeable message sign, as per plan | 614E18601 | SNMT | 13 | 5 (38%) | $1,050.00 | $950.00 |
| Patching concrete structure, as per plan | 519E11101 | SF | 10 | 5 (50%) | $186.19 | $150.00 |
| Work zone impact attenuator, 24" wide hazards, (unidirectional) | 614E12380 | EACH | 10 | 5 (50%) | $2,100.00 | $2,280.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Elite Contractors Inc | 21 | 11 of 21 |
| 360 Construction Company Inc | 18 | 10 of 18 |
| Legend Painting Inc | 16 | 8 of 16 |
| Apbn Inc | 15 | 4 of 15 |
| Panther Industrial Painting LLC | 15 | 6 of 15 |
| KMX Painting Inc | 11 | 5 of 11 |
| Corrosion Resistance LTD | 11 | 4 of 11 |
| Vimas Painting Company Inc | 8 | 3 of 8 |
| Industrial Painting & Rigging Inc | 4 | 3 of 4 |
| M & J Construction Co of Pinellas County Inc | 3 | 0 of 3 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 29 OCT 2026 | 260417 | LOR | LOR-SR 611-03.44 (BRIDGE PAINTING) | 6 of 7 | $27,204,570 | +59% |
| 04 DEC 2025 | 250525 | HAM | HAM-US 50-03.76/19.03 (BRIDGE PAINTING) | 3 of 6 | $8,175,901 | +4.0% |
| 23 OCT 2025 | 250493 | District 7 | D07-BP FY26 (BRIDGE PAINTING) | 1 of 8 | $1,475,840 | Low, 5.0% under the second |
| 09 OCT 2025 | 250470 | MOT | MOT-BP FY26 (BRIDGE PAINTING) | 1 of 7 | $2,614,391 | Low, 6.0% under the second |
| 28 AUG 2025 | 250391 | CUY | CUY-IR 480-07.92/VAR Paint (BRIDGE PAINTING) | 3 of 9 | $5,337,817 | +4.0% |
| 24 APR 2025 | 250218 | GAL | GAL-US 35-17.43 & VARIOUS (BRIDGE PAINTING) | 2 of 5 | $2,401,159 | +5.0% |
| 27 MAR 2025 | 250157 | HAM | HAM-IR 471-00.00 Type 3 ER (BRIDGE REPAIR) | 5 of 5 | $2,442,179 | +109% |
| 14 NOV 2024 | 240518 | District 1 | D01-BP FY25 (BRIDGE PAINTING) | 4 of 9 | $2,191,548 | +23% |
| 17 OCT 2024 | 240466 | HAM | HAM-IR 74-08.38/09.11 (BRIDGE REPAIR) | 6 of 7 | $6,516,138 | +119% |
| 08 FEB 2024 | 240085 | District 7 | D07-BP/BH FY24 (BRIDGE PAINTING) | 1 of 7 | $5,541,039 | Low, 2.0% under the second |
| 25 JAN 2024 | 240046 | CLE | CLE-/CLI BP VAR 2024 (BRIDGE PAINTING) | 2 of 8 | $2,634,446 | +6.0% |
| 27 JUL 2023 | 230398 | FUL | FUL-US 20/US 20A-09.14/02.53 Bdg Paint (BRIDGE PAINTING) | 5 of 6 | $579,530 | +22% |
| 17 FEB 2022 | 220079 | BEL | BEL-IR 470-01.26 (BRIDGE PAINTING) | 3 of 7 | $816,848 | +13% |
| 13 JAN 2022 | 220010 | GEA | GEA-US 422-01.70/VAR Paint (BRIDGE PAINTING) | 6 of 10 | $2,927,032 | +35% |
| 13 JAN 2022 | 220032 | District 9 | D09-BH-FY2022 (B) (BRIDGE PAINTING) | 6 of 8 | $1,372,691 | +57% |
| 02 DEC 2021 | 210645 | District 7 | D07-BP FY22 (BRIDGE PAINTING) | 6 of 7 | $2,045,271 | +52% |
| 18 NOV 2021 | 210620 | District 3 | D03-BP-ERI Paint (BRIDGE PAINTING) | 3 of 6 | $4,047,421 | +20% |
| 18 NOV 2021 | 210621 | District 3 | D03-BP FY2022 (BRIDGE PAINTING) | 2 of 6 | $1,895,214 | +34% |
| 28 OCT 2021 | 210502 | CUY | CUY-IR 90-07.58/13.72 Paint (BRIDGE PAINTING) | 10 of 14 | $9,718,143 | +26% |
| 30 SEP 2021 | 210519 | WAS | WAS-SR 339-20.12 (BRIDGE REPAIR) | 2 of 11 | $1,018,936 | +4.0% |
| 19 NOV 2020 | 200536 | ATH | ATH-US 50-09.45 (BRIDGE PAINTING) | 7 of 8 | $1,995,663 | +18% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.