ODOT letting results, October 17, 2024
26 contracts let by Ohio DOT on October 17, 2024, $55,859,579 in low bids, a median of 3 bidders per contract. On the 26 with an engineer's estimate, the low bid came in under it 17 times; median low bid -5.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 26
- Low bids, total
- $55,859,579
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 240477 | WYA-US-US 23/US 30-10.26/09.12 (FOUR LANE RESURFACING) | WYA | 3 | Kokosing Construction Company Inc | $6,814,114 | $8,192,030 | +20% | -8.0% | ODOT |
| 240468 | HAS-US 250-04.20 (TWO LANE RESURFACING) | HAS | 2 | Shelly & Sands Inc | $6,415,515 | $6,850,945 | +7.0% | +18% | ODOT |
| 240473 | COS-/MUS-SR 16/SR 83-11.74/12.75 (TWO LANE RESURFACING) | COS | 1 | Shelly Company | $5,379,794 | -10% | ODOT | ||
| 240464 | FUL-SR 120-14.08 Replacement (CULVERT REPLACEMENT) | FUL | 1 | Vernon Nagel Inc | $3,898,021 | +10% | ODOT | ||
| 240467 | HAM-SR 126-11.30 (BRIDGE REPAIR) | HAM | 2 | Prus Construction Company | $3,894,537 | $7,009,164 | +80% | +53% | ODOT |
| 240476 | WAY-US 30-19.469 (FOUR LANE RESURFACING) | WAY | 4 | Kokosing Construction Company Inc | $3,556,397 | $3,944,695 | +11% | -10% | ODOT |
| 240471 | MAR-SR 423/SR 231-00.04/00.02 (TWO LANE RESURFACING) | MAR | 2 | Kokosing Construction Company Inc | $3,097,940 | $3,149,916 | +2.0% | -21% | ODOT |
| 240460 | BEL-SR 7-22.23 (BRIDGE REPAIR) | BEL | 2 | Marucci & Gaffney Excavating Co | $3,047,476 | $3,489,034 | +14% | +19% | ODOT |
| 240466 | HAM-IR 74-08.38/09.11 (BRIDGE REPAIR) | HAM | 7 | Elite Contractors Inc | $2,979,935 | $3,568,840 | +20% | -22% | ODOT |
| 240457 | ALL-IR 75/SR 117/SR 309-VAR. (TWO LANE RESURFACING) | ALL | 1 | Shelly Company | $2,779,993 | +6.0% | ODOT | ||
| 240463 | FAI-SR 159-00.00 (TWO LANE RESURFACING) | FAI | 1 | Shelly Company | $2,559,665 | -5.0% | ODOT | ||
| 240470 | LOG-US-US 33-10.71 (MICROSURFACING) | LOG | 2 | Strawser Construction Inc | $1,988,482 | $2,462,499 | +24% | -4.0% | ODOT |
| 240474 | TRU-SR 7/SR 7D-08.74/00.00 (TWO LANE RESURFACING) | TRU | 5 | Shelly & Sands Inc | $1,499,033 | $1,573,000 | +5.0% | -5.0% | ODOT |
| 240479 | D04-SIGN FY2025 (Systematic) (SIGNING) | District 4 | 3 | Cleveland Barricading Systems LLC | $1,264,262 | $1,428,725 | +13% | -8.0% | ODOT |
| 240459 | AUG-SR 65-00.00 (TWO LANE RESURFACING) | AUG | 2 | Shelly Company | $1,235,341 | $1,360,000 | +10% | -3.0% | ODOT |
| 240482 | D12-MOW FY2025 (MOWING) | District 12 | 2 of 3 | Linkel Company | $977,977 | $1,025,100 | +5.0% | -3.0% | ODOT |
| 240469 | JAC-US 35-04.33 (CULVERT REPLACEMENT) | JAC | 3 | Axis Civil Construction LLC | $888,960 | $1,145,789 | +29% | -9.0% | ODOT |
| 240475 | WAS-SR 339-08.64 (CULVERT REPLACEMENT) | WAS | 6 | Buds Inc | $843,743 | $877,773 | +4.0% | -6.0% | ODOT |
| 244020 | ROS-SR 207-04.75 (BRIDGE REPAIR) | ROS | 5 | R C Construction Company and Son Inc | $586,885 | $598,390 | +2.0% | -16% | ODOT |
| 240480 | D06-ELEC FY25 (LIGHTING) | District 6 | 4 | Perram Electric Inc | $545,645 | $582,014 | +7.0% | +5.0% | ODOT |
| 240462 | COS-CR 271-06.26 (SIGNALIZATION) | COS | 9 | Cornerstone Electric Inc | $428,712 | $457,781 | +7.0% | -18% | ODOT |
| 240472 | MED-IR 76-11.83 (LIGHTING) | MED | 7 | Cornerstone Electric Inc | $295,341 | $347,500 | +18% | -19% | ODOT |
| 240461 | BUT-SR 4/SR 129-09.30/02.30 (CULVERT REPLACEMENT) | BUT | 4 | BCC Ohio Inc | $271,459 | $303,930 | +12% | +1.0% | ODOT |
| 240478 | CLE-East Fork Resurfacing FY25 (PARKING AREAS) | CLE | 4 | Roberts Paving Inc | $260,635 | $295,990 | +14% | -16% | ODOT |
| 240465 | HAM-CR 358-04.36 (MISCELLANEOUS) | HAM | 4 | Sunesis Construction Co | $220,463 | $221,942 | +1.0% | +45% | ODOT |
| 240481 | D09-HS FY2025 (HERBICIDAL SPRAYING) | District 9 | 2 | Allen Chase Enterprises, Inc | $129,253 | $201,535 | +56% | +23% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.