ODOT contract 250157 bid tabulation
HAM-IR 471-00.00 Type 3 ER (BRIDGE REPAIR). Let by Ohio DOT on March 27, 2025, HAM. 5 bids received; low bid $1,168,120 by Legend Painting Inc, -48% against the engineer's estimate of $2,235,000.
- Owner
- Ohio DOT
- Letting
- 27 MAR 2025
- Pay items
- 40
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Legend Painting Inc | $1,168,120 | Low | -48% |
| 2 | Elite Contractors Inc | $1,648,454 | +41% | -26% |
| 3 | 360 Construction Company Inc | $1,848,209 | +58% | -17% |
| 4 | Vimas Painting Company Inc | $2,278,550 | +95% | +2.0% |
| 5 | Euro Paint LLC | $2,442,179 | +109% | +9.0% |
Engineer's estimate: $2,235,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Legend Painting Inc | 2. Elite Contractors Inc | 3. 360 Construction Company Inc | 4. Vimas Painting Company Inc | 5. Euro Paint LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Special - existing conduit cleaned (202E75711) | FT | 550 | $90.91 | $30.00 | $35.00 | $50.00 | $10.00 |
| 2 | Fence, misc.: temporary chain link (607E98000) | FT | 1,860 | $2.50 | $2.50 | $2.50 | $3.00 | $2.50 |
| 3 | RPM (621E00100) | EACH | 9 | $325.00 | $325.00 | $325.00 | $350.00 | $330.00 |
| 6 | Sign attachment assembly (630E75000) | EACH | 11 | $450.00 | $450.00 | $450.00 | $500.00 | $450.00 |
| 7 | Sign, overhead extrusheet (630E80228) | EACH | 5 | $925.00 | $925.00 | $925.00 | $1,000.00 | $925.00 |
| 8 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 5 | $925.00 | $925.00 | $925.00 | $1,000.00 | $925.00 |
| 10 | Edge line, 6" (646E10010) | MI | 0.10 | $14,000 | $14,000 | $14,000 | $14,000 | $159,720 |
| 11 | Lane line, 6" (646E10110) | MI | 0.15 | $14,000 | $14,000 | $14,000 | $14,000 | $79,860 |
| 12 | Channelizing line, 12" (646E10310) | FT | 52 | $10.00 | $10.00 | $10.00 | $10.00 | $55.00 |
| 13 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $100.00 | $50.00 | $95.00 | $60.00 | $80.00 |
| 14 | Portable changeable message sign, as per plan (614E18601) | SNMT | 4 | $900.00 | $900.00 | $900.00 | $4,000.00 | $900.00 |
| 15 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $4,500.00 | $16,175 | $28,000 | $20,000 | $16,175 |
| 16 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,689 | $25.00 | $34.00 | $26.00 | $35.00 | $35.00 |
| 17 | Special - urethane top coat sealer (512E71500) | SY | 178 | $21.00 | $27.00 | $20.00 | $80.00 | $17.00 |
| 18 | Surface preparation of existing structural steel (514E00050) | SF | 30,100 | $5.00 | $8.00 | $8.00 | $15.00 | $17.81 |
| 19 | Field painting of existing structural steel, prime coat (514E00056) | SF | 30,100 | $1.00 | $2.00 | $4.00 | $2.00 | $3.00 |
| 20 | Field painting structural steel, intermediate coat (514E00060) | SF | 39,300 | $1.50 | $2.00 | $3.00 | $2.00 | $3.00 |
| 21 | Field painting structural steel, finish coat (514E00066) | SF | 39,300 | $1.25 | $2.00 | $2.00 | $2.00 | $3.00 |
| 22 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 37 | $60.00 | $150.00 | $150.00 | $200.00 | $50.00 |
| 23 | Final inspection repair (514E10000) | EACH | 12 | $135.00 | $200.00 | $200.00 | $400.00 | $50.00 |
| 24 | Pipe downspout, including specials, as per plan, 6 (518E51201) | FT | 560 | $87.50 | $97.75 | $97.75 | $110.00 | $97.75 |
| 25 | Special - composite fiber wrap system (519E00100) | SF | 1,600 | $26.00 | $26.00 | $30.00 | $38.00 | $39.00 |
| 26 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $4,500.00 | $16,320 | $28,000 | $20,000 | $16,320 |
| 27 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,681 | $25.00 | $34.00 | $26.00 | $35.00 | $35.00 |
| 28 | Special - urethane top coat sealer (512E71500) | SY | 167 | $21.00 | $27.00 | $20.00 | $80.00 | $17.00 |
| 29 | Surface preparation of existing structural steel (514E00050) | SF | 40,900 | $5.00 | $8.00 | $8.00 | $15.00 | $12.57 |
| 30 | Field painting of existing structural steel, prime coat (514E00056) | SF | 40,900 | $1.00 | $2.00 | $4.00 | $2.00 | $3.00 |
| 31 | Field painting structural steel, intermediate coat (514E00060) | SF | 40,900 | $1.50 | $2.00 | $3.00 | $2.00 | $3.00 |
| 32 | Field painting structural steel, finish coat (514E00066) | SF | 40,900 | $1.25 | $2.00 | $2.00 | $2.00 | $3.00 |
| 33 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 49 | $60.00 | $150.00 | $150.00 | $200.00 | $50.00 |
| 34 | Final inspection repair (514E10000) | EACH | 12 | $135.00 | $200.00 | $200.00 | $400.00 | $50.00 |
| 35 | Pipe downspout, including specials, as per plan, 6 (518E51201) | FT | 565 | $87.50 | $97.75 | $97.75 | $110.00 | $97.75 |
| 36 | Special - composite fiber wrap system (519E00100) | SF | 1,500 | $26.00 | $26.00 | $30.00 | $38.00 | $39.00 |
| 37 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $50,000 | $30,000 | $40,000 | $18,000 |
| 38 | Maintaining traffic (614E11000) | LS | 1 | $50,000 | $80,000 | $75,000 | $60,000 | $100,000 |
| 39 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,000.00 | $1,000.00 | $2,000.00 | $5,000.00 | $6,000.00 |
| 40 | Mobilization (624E10000) | LS | 1 | $59,542 | $50,000 | $40,000 | $100,000 | $79,900 |
| 100 | Concrete repair by epoxy injection (512E10600) | FT | 45 | $140.00 | $140.00 | $125.00 | $100.00 | $225.00 |
| 101 | Patching concrete structure (519E11100) | SF | 4 | $150.00 | $1,000.00 | $650.00 | $350.00 | $1,000.00 |
| 102 | Concrete repair by epoxy injection (512E10600) | FT | 70 | $140.00 | $140.00 | $125.00 | $100.00 | $225.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of March 27, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.