ODOT contract 260417 bid tabulation

LOR-SR 611-03.44 (BRIDGE PAINTING). Let by Ohio DOT on October 29, 2026, LOR. 7 bids received; low bid $17,153,185 by Corrosion Resistance LTD, -18% against the engineer's estimate of $21,000,000.

Owner
Ohio DOT
Letting
29 OCT 2026
Pay items
98
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Corrosion Resistance LTD$17,153,185Low-18%
2Vimas Painting Company Inc$17,298,439+1.0%-18%
3360 Construction Company Inc$21,867,795+27%+4.0%
4Liberty Maintenance Inc$23,289,999+36%+11%
5Legend Painting Inc$23,910,962+39%+14%
6Euro Paint LLC$27,204,570+59%+30%
7Elite Contractors Inc$33,935,018+98%+62%
ODOT contract 260417: bids by rank

Engineer's estimate: $21,000,000.

Bid tabulation

LinePay itemUnitQuantity1. Corrosion Resistance LTD2. Vimas Painting Company Inc3. 360 Construction Company Inc4. Liberty Maintenance Inc5. Legend Painting Inc6. Euro Paint LLC
1Clearing and grubbing, as per plan (201E11001)LS1$300,000$20,000$205,000$27,550$105,000$105,000
2Walk removed (202E30000)SF220$10.00$4.00$3.50$21.08$3.50$3.50
3Guardrail removed (202E38000)FT144$5.00$6.00$5.00$6.56$6.00$5.00
4Bridge terminal assembly removed (202E47000)EACH3$110.00$120.00$110.00$144.31$110.00$110.00
5Fence removed (202E75000)FT400$4.00$5.00$4.00$5.25$5.00$4.00
6Gate removed (202E75250)EACH2$220.00$250.00$220.00$288.62$240.00$220.00
7Guardrail, type MGS (606E15050)FT100$35.60$36.00$35.60$46.70$36.50$35.60
8Anchor assembly, MGS type T (606E26550)EACH1$2,445.00$2,500.00$2,445.00$3,207.61$2,545.00$2,445.00
9MGS bridge terminal assembly, type 1 (606E35002)EACH1$3,920.00$4,000.00$3,920.00$5,142.67$4,050.00$3,920.00
10Fence, type CLT (607E23000)FT565$37.00$38.00$37.00$48.54$40.00$37.00
11Gate, type CLT (607E61200)EACH2$1,885.00$2,000.00$1,885.00$2,472.94$1,985.00$1,885.00
12Fenceline seeding and mulching (607E70000)FT565$2.00$3.00$2.00$2.62$2.70$2.00
134" concrete walk (608E10000)SF220$15.00$14.00$12.00$21.08$13.50$12.00
14Special - bollard (690E50600)EACH10$1,380.00$2,000.00$1,380.00$1,810.43$1,750.00$1,380.00
15Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00$1.00$1.00
16Catch basin frame and grate, as per plan (611E98651)EACH3$2,000.00$2,500.00$1,950.00$3,279.76$1,950.00$1,950.00
17Pavement planing, asphalt concrete(T=1.5") (254E01000)SY245$60.00$27.00$20.00$32.80$27.00$25.00
18Non-tracking tack coat (407E20000)GAL22$3.50$7.00$50.00$6.56$6.50$5.00
19Asphalt concrete surface course, 9.5 MM, type A (4 (442E22000)CY12$4,200.00$2,700.00$2,800.00$3,489.66$3,500.00$2,660.00
20Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH17$850.00$800.00$850.00$1,115.12$750.00$710.00
21Special - maintain existing lighting (625E40000)LS1$10,150$15,000$10,150$13,316$4,135.00$4,135.00
22Luminaire removed (625E75506)EACH23$280.00$250.00$280.00$367.33$231.00$230.89
23Arc flash calculations and label(EX. CC-1) (625E76000)EACH1$1,500.00$3,000.00$1,500.00$1,967.86$2,800.00$2,795.00
24Lighting, misc.:bridge-mounted marine navigation L (625E98000)EACH6$5,900.00$4,500.00$5,900.00$7,740.23$3,200.00$3,195.00
25Lighting, misc.:replace junction box (625E98000)EACH2$6,350.00$5,000.00$6,350.00$8,330.59$4,000.00$3,950.00
26Lighting, misc.:replace lighting control center (625E98000)EACH1$9,800.00$15,000$9,800.00$12,857$22,000$10,075
27Special - maintain existing navigation lighting (690E98400)LS1$9,780.00$20,000$9,780.00$12,830$1,500.00$1,270.00
28Edge line, 6" (646E10010)MI2.10$3,420.00$3,420.00$3,420.00$4,486.71$3,420.00$3,420.00
29Center line (646E10200)MI0.34$4,565.00$4,600.00$4,565.00$5,988.85$4,565.00$4,565.00
30Transverse/diagonal line (646E10600)FT584$8.10$9.00$8.10$10.63$8.10$8.10
31Bike lane symbol marking (646E20600)EACH14$215.00$220.00$215.00$282.06$215.00$215.00
32Law enforcement officer with patrol car for assistance, as per plan (614E11111)HR50$125.00$140.00$100.00$131.19$150.00$80.00
33Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH8$2,400.00$2,400.00$2,329.85$3,056.54$2,340.00$2,329.00
34Barrier reflector, type 1ONE way (614E13310)EACH248$11.28$12.00$11.28$14.80$11.28$11.28
35Object marker, one way (614E13350)EACH248$21.97$22.00$21.97$28.82$21.97$21.97
36Work zone center line, class I, 807 paint (614E21050)MI1.40$4,440.00$4,440.00$4,440.00$5,824.85$4,440.00$4,440.00
37Work zone edge line, class I, 6", 807 paint (614E22056)MI4.30$3,375.00$3,400.00$3,375.00$4,427.67$3,375.00$3,375.00
38Work zone crosswalk line, class I, 12" (614E27010)FT60$6.00$7.00$6.00$7.87$6.00$6.00
39Portable barrier, unanchored (622E41100)FT12,295$18.00$30.00$18.00$44.63$18.00$34.02
40Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$490,000$620,000$655,000$1,167,594$415,800$265,000
41Removal misc.:I-section jacking support removal (P (202E98100)EACH14$4,200.00$3,500.00$2,750.00$3,607.74$4,530.50$3,485.00
42Removal misc.:rivet (202E98100)EACH96$510.00$500.00$325.00$426.37$552.00$425.00
43Sealing concrete bridge decks with HMWM resin (512E10300)SY1,639$18.00$15.00$14.00$16.87$14.00$14.00
44Concrete repair by epoxy injection (512E10600)FT288$110.00$120.00$110.00$126.51$110.00$500.00
45Special - sealingsealing edges of roadway (512E75000)FT3,536$15.00$14.00$13.50$19.68$13.50$13.50
46Structural steel, misc.:bridge railing bolt replac (513E95030)EACH38$610.00$620.00$200.00$262.38$656.89$505.30
47Structural steel, misc.:new bolt at select gusset (513E95030)EACH88$375.00$400.00$200.00$262.38$407.74$313.65
48Structural steel, misc.:new bolt in open hole (eas (513E95030)EACH262$135.00$170.00$110.00$144.31$127.07$97.75
49Structural steel, misc.:new bolt in open hole (roa (513E95030)EACH26$955.00$1,000.00$95.00$124.63$1,040.00$800.00
50Structural steel, misc.:truss gusset repair (513E95030)EACH7$4,878.00$6,000.00$4,175.00$5,477.20$3,937.70$3,029.00
51Surface preparation of existing structural steel (514E00100)LS1$4,900,000$5,200,000$6,204,480$10,149,520$8,800,000$9,800,000
52Field painting of existing structural steel, prime coat (514E00200)LS1$2,500,000$1,500,000$2,068,160$2,176,648$2,000,000$2,820,567
53Field painting structural steel, intermediate coat (514E00300)LS1$1,800,000$2,100,000$1,837,860$1,454,310$3,000,000$2,820,567
54Field painting structural steel, finish coat, as per plan (514E00401)LS1$1,900,000$2,100,000$1,378,395$1,495,515$3,000,000$2,820,567
55Grinding fins, tears, slivers on existing structural steel (514E00504)MNHR407$68.00$150.00$100.00$128.74$60.00$50.00
56Final inspection repair (514E10000)EACH174$75.00$200.00$150.00$327.98$250.00$50.00
57Field painting, misc.:epoxy intermediate coat on G (514E27700)SF4,688$6.40$8.00$11.00$2.71$18.00$4.00
58Field painting, misc.:high pressure water cleaning (514E27700)SF15,538$3.00$4.00$8.00$0.35$1.00$1.50
59Field painting, misc.:surface preparation of exist (514E27700)SF851$10.25$100.00$175.00$6.48$18.00$14.00
60Field painting, misc.:surface preparation of exist (514E27700)SF15,538$4.50$2.00$8.00$0.35$3.00$1.50
61Field painting, misc.:top finish coat on galvanize (514E27700)SF15,538$4.45$4.00$6.00$2.87$6.00$1.50
62Field painting, misc.:caulking (514E27710)FT32,144$9.00$5.00$10.00$15.28$10.00$25.00
63Field painting, misc.:field painting of existing S (514E27800)LS1$115,000$140,000$1,054,182$128,412$450,000$1,077,020
64Field painting, misc.:surface preparation of exist (514E27800)LS1$185,000$540,000$1,925,028$306,846$580,000$1,615,530
65Elastomeric strip seal without steel extrusions, as per plan (516E01301)FT134$125.00$110.00$370.00$140.56$100.00$100.00
66Preformed elastomeric compression joint seal (516E10000)FT44$205.00$200.00$191.00$309.23$191.00$191.00
67Preformed elastomeric compression joint seal (516E10000)FT223$235.00$220.00$209.00$288.15$209.00$209.00
68Structural joint or joint sealer, misc.:joint foam (516E14600)FT1,250$40.00$37.00$35.00$36.55$35.00$35.00
69Structural joint or joint sealer, misc.:repair dam (516E14600)FT14$1,120.00$1,800.00$1,120.00$1,469.33$891.47$685.75
70Joint sealer, as per plan (516E31001)FT89$31.00$32.00$30.00$56.22$30.00$30.00
71Elastomeric bearing pad, misc.:1/8" thick elastome (516E42600)FT178$72.00$500.00$247.00$94.46$400.00$237.00
72Railing, misc.:repair of retaining wall pedestrian (517E76302)EACH7$1,040.78$900.00$861.00$1,129.55$1,114.42$857.00
73Structure drainage, misc.:epair damaged deck drain (518E62100)FT7$1,088.05$1,000.00$1,150.00$1,508.69$1,189.50$915.00
74Structure drainage, misc.:NRNS flashing (deck drai (518E62100)FT504$772.93$510.00$650.00$852.74$598.00$460.00
75Structure drainage, misc.:NRNS flashing (deflectio (518E62100)FT340$1,070.21$580.00$925.00$1,213.51$663.00$510.00
76Structure drainage, misc.:NRNS flashing (lower lat (518E62100)FT160$357.00$340.00$225.00$295.18$390.00$300.00
77Structure drainage, misc.:forward abutment drainag (518E63300)LS1$9,000.00$40,000$75,000$98,393$18,720$14,400
78Patching concrete structure (519E11100)SF489$200.00$220.00$200.00$196.79$200.00$650.00
79Approach slabs, misc.:replace curb (526E98200)FT35$195.00$200.00$195.00$140.56$195.00$195.00
80Special - structurespilaster wall reconstruction (530E00200)LS1$50,000$42,000$40,000$65,595$40,000$40,000
81Special - structuressteel mesh removed and replace (530E00200)LS1$82,000$20,000$50,000$141.68$45,000$250,000
82Special - structurespigeon doors removed and reins (530E00400)EACH1,452$50.00$100.00$200.00$88.16$300.00$400.00
83Special - structuresplywood pigeon doors (530E00400)EACH300$90.00$100.00$150.00$54.32$400.00$200.00
84Special - structuresre-tensioning post tension rod (530E00400)EACH2$7,070.00$10,000$7,070.00$9,275.16$10,000$7,070.00
85Special - structuressteel pigeon doors (530E00400)EACH5$725.00$3,200.00$6,000.00$1,494.32$1,500.00$725.00
86Crushed aggregate slope protection (601E20010)CY283$135.00$140.00$135.00$196.79$135.00$135.00
87Structure grounding system, as per plan (625E33001)EACH3$3,900.00$7,000.00$3,900.00$5,116.43$6,717.00$3,350.00
88Patching concrete structures with trowelable mortar, as per plan (843E50001)SF10$300.00$350.00$300.00$281.12$300.00$850.00
89Latex modified concrete overlay, as per plan(1-1/2 (847E10101)SY8,741$109.00$110.00$112.50$148.99$108.00$108.00
90Latex modified concrete overlay (variable thickness), material only, as per plan (847E20101)CY49$850.00$900.00$850.00$1,546.17$850.00$850.00
91Test slab (847E30000)LS1$1,950.00$2,000.00$1,950.00$8,433.66$1,950.00$1,950.00
92Hand chipping (847E50000)SY89$180.00$200.00$180.00$203.81$180.00$180.00
93Department'S share of the dispute resolution advisor (100E51200)EACH30,000$1.00$1.00$1.00$1.00$1.00$1.00
94Premium for contract performance bond and for payment bond (103E05000)LS1$120,000$130,000$750,000$147,100$200,000$300,000
95CPM progress schedule (108E10000)LS1$30,000$50,000$50,000$41,981$15,000$15,600
96Maintaining traffic (614E11000)LS1$400,000$200,000$550,000$184,692$150,000$105,282
97Construction layout stakes and surveying (623E10000)LS1$20,000$18,000$30,000$3,135.45$5,000.00$10,880
98Mobilization (624E10000)LS1$500,000$800,000$800,000$1,047,340$1,000,000$435,850
ODOT contract 260417: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy