ODOT letting results, October 29, 2026

20 contracts let by Ohio DOT on October 29, 2026, $119,778,627 in low bids, a median of 4 bidders per contract. On the 20 with an engineer's estimate, the low bid came in under it 11 times; median low bid -9.0% against the estimate.

Owner
Ohio DOT
Contracts
20
Low bids, total
$119,778,627
Data through
12 NOV 2026

Contracts let that day

ContractProjectCountyBidsLow bidderLow bidSecond bidGapAgainst estimateSource
260453DEL-IR 71-00.00, FRA-IR 71-28.62 (FOUR LANE RESURFACING)DEL3Shelly & Sands Inc$23,183,469$28,219,896+22%0.0%ODOT
260417LOR-SR 611-03.44 (BRIDGE PAINTING)LOR7Corrosion Resistance LTD$17,153,185$17,298,439+1.0%-18%ODOT
260399CUY-US 422-16.20 Interchange (INTERCHANGE)CUY4Tri-Mor Corp$11,288,797$12,124,213+7.0%+3.0%ODOT
260474WAR-IR 71-00.00 (FOUR LANE RESURFACING)WAR2Barrett Paving Materials Inc$11,197,318$12,830,188+15%+9.0%ODOT
260477ATB-IR 90 Vacant Rest Areas TP (PARKING AREAS)ATB3Karvo Companies Inc$9,185,577$9,242,650+1.0%+8.0%ODOT
260467LAW-US 52-07.44 (SLIDE REPAIR)LAW2Allard Excavation LLC$8,751,687$8,878,603+1.0%+9.0%ODOT
260455ASD-OVERLAY VAR FY2027 (TWO LANE RESURFACING)ASD2Kokosing Construction Company Inc$6,659,917$6,865,632+3.0%-9.0%ODOT
260468MAH-SR 46-13.55 (PART 1 AND PART 2) (INTERSECTION)MAH4Shelly & Sands Inc$6,562,795$7,475,832+14%-9.0%ODOT
260471MOT-SR 835-02.57 (BRIDGE REPLACEMENT (1 BRIDGE))MOT5Eagle Bridge Co$5,570,980$5,914,491+6.0%-26%ODOT
260454ADA-SR 247-14.51/15.56 (BRIDGE REPLACEMENT (2 BRIDGES))ADA5D G M Inc$4,877,413$5,103,924+5.0%-16%ODOT
268021JEF-SR 7-32.95 (SLIDE REPAIR)JEF3Buds Inc$3,442,043$3,579,815+4.0%+10%ODOT
260475WOO-IR 75-13.83 Deck Replacement (BRIDGE REPAIR)WOO3Eagle Bridge Co$2,769,748$3,022,171+9.0%-9.0%ODOT
260461HAM-IR 275-11.40 (SLIDE REPAIR)HAM5Sunesis Construction Co$2,766,883$2,901,596+5.0%+8.0%ODOT
260456COL-EL Riverfront Trail Phase1.1 (SIDEWALK)COL2Shelly & Sands Inc$1,779,282$1,830,844+3.0%+12%ODOT
260469MOT-Johnson Station Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE))MOT6Double Z Construction Company$1,306,719$1,523,584+17%-13%ODOT
260476WOO-SR 281-11.91 Structure Repl (BRIDGE REPLACEMENT (1 BRIDGE))WOO7Great Lakes Demolition Company$952,236$1,003,615+5.0%-32%ODOT
264027CLI-/GRE Inverts FY27 (CULVERT REPLACEMENT)CLI3BCC Ohio Inc$791,078$999,343+26%+5.0%ODOT
264028HAN-SR 103-12.43 (BRIDGE REPAIR)HAN4BCC Ohio Inc$581,103$593,528+2.0%-12%ODOT
260465HOL-US 62-30.74 (SLIDE REPAIR)HOL5Dennison Bridge Inc$482,245$524,559+9.0%-16%ODOT
264029LAK-SR 283-03.29 Sidewalk (SIDEWALK)LAK4D L Smith Concrete LLC$476,153$545,972+15%-13%ODOT
ODOT contracts let on October 29, 2026, largest low bid first

Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy