ODOT contract 264029 bid tabulation
LAK-SR 283-03.29 Sidewalk (SIDEWALK). Let by Ohio DOT on October 29, 2026, LAK. 4 bids received; low bid $476,153 by D L Smith Concrete LLC, -13% against the engineer's estimate of $547,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 32
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | D L Smith Concrete LLC | $476,153 | Low | -13% |
| 2 | Cook Paving & Construction Co Inc | $545,972 | +15% | 0.0% |
| 3 | Geauga Highway Co | $582,892 | +22% | +7.0% |
| 4 | Madex Construction Co | $694,265 | +46% | +27% |
Engineer's estimate: $547,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. D L Smith Concrete LLC | 2. Cook Paving & Construction Co Inc | 3. Geauga Highway Co | 4. Madex Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $25,000 | $35,000 | $17,500 | $4,118.70 |
| 2 | Pavement removed (202E23000) | SY | 468 | $12.50 | $22.00 | $45.00 | $5.59 |
| 3 | Excavation (203E10000) | CY | 52 | $25.00 | $70.00 | $100.00 | $22.95 |
| 4 | Subgrade compaction (204E10000) | SY | 67 | $1.00 | $4.00 | $5.00 | $1.58 |
| 5 | Geotextile fabric, as per plan (204E50001) | SY | 123 | $1.25 | $3.00 | $10.00 | $5.58 |
| 6 | Linear grading (209E60200) | STA | 31 | $150.00 | $450.00 | $550.00 | $2,119.07 |
| 7 | 4" concrete walk, as per plan (608E10001) | SF | 10,127 | $14.00 | $14.00 | $10.00 | $22.54 |
| 8 | 6" concrete walk, as per plan (608E13001) | SF | 75 | $16.00 | $19.00 | $12.00 | $17.89 |
| 9 | Curb ramp (608E52000) | SF | 993 | $32.00 | $39.00 | $26.00 | $40.53 |
| 10 | Walkway, misc.: concrete integral curb and walk (608E98000) | SF | 2,944 | $20.00 | $24.00 | $15.00 | $33.58 |
| 11 | Special - mailbox removed and reset (690E50350) | EACH | 8 | $165.00 | $465.00 | $250.00 | $78.95 |
| 12 | Topsoil (659E00300) | CY | 165 | $55.00 | $65.00 | $75.00 | $52.63 |
| 13 | Seeding and mulching, class 1 (659E00500) | SY | 1,490 | $4.00 | $3.50 | $6.50 | $6.95 |
| 14 | Water (659E35000) | MGAL | 4 | $50.00 | $150.00 | $250.00 | $7.89 |
| 15 | Erosion control (832E30000) | EACH | 7,500 | $1.00 | $1.00 | $1.00 | $1.00 |
| 16 | Manhole adjusted to grade, as per plan (611E99655) | EACH | 6 | $725.00 | $700.00 | $1,200.00 | $436.84 |
| 17 | Special - miscellaneous metal (611E99820) | LB | 800 | $4.00 | $1.75 | $3.00 | $0.50 |
| 18 | Aggregate base (304E20000) | CY | 52 | $70.00 | $105.00 | $110.00 | $79.76 |
| 19 | 6" non-reinforced concrete pavement, class QC MS (452E10050) | SY | 253 | $85.00 | $120.00 | $168.00 | $72.16 |
| 20 | Service box adjusted to grade, as per plan (638E10901) | EACH | 13 | $385.00 | $355.00 | $550.00 | $178.95 |
| 21 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 30 | $18.00 | $20.00 | $18.00 | $26.63 |
| 22 | Sign, flat sheet (630E80100) | SF | 18 | $22.00 | $25.00 | $22.00 | $28.95 |
| 23 | Removal of pavement marking (642E30000) | FT | 525 | $8.00 | $10.00 | $5.95 | $2.32 |
| 24 | Stop line (646E10400) | FT | 50 | $14.00 | $17.00 | $14.00 | $28.95 |
| 25 | Crosswalk line, 12" (646E10510) | FT | 701 | $7.00 | $8.00 | $7.00 | $28.95 |
| 26 | Crosswalk line, 24", type A125 (647E20076) | FT | 332 | $25.00 | $30.00 | $24.00 | $19.68 |
| 27 | Pull box, misc.: pull box removed and replaced to (625E31600) | EACH | 2 | $1,500.00 | $1,000.00 | $1,600.00 | $436.84 |
| 28 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $7,000.00 | $10,000 | $26,200 |
| 29 | Maintaining traffic, as per plan (614E11001) | LS | 1 | $20,000 | $75,000 | $175,000 | $39,977 |
| 30 | Portable changeable message sign, as per plan (614E18601) | SNMT | 12 | $850.00 | $1,300.00 | $1,000.00 | $673.68 |
| 31 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $28,000 | $15,000 | $8,000.00 | $40,526 |
| 32 | Mobilization (624E10000) | LS | 1 | $53,500 | $18,750 | $25,000 | $49,715 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.