ODOT contract 264028 bid tabulation
HAN-SR 103-12.43 (BRIDGE REPAIR). Let by Ohio DOT on October 29, 2026, HAN. 4 bids received; low bid $581,103 by BCC Ohio Inc, -12% against the engineer's estimate of $660,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 64
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | BCC Ohio Inc | $581,103 | Low | -12% |
| 2 | Crawford Construction Company Inc | $593,528 | +2.0% | -10% |
| 3 | Vernon Nagel Inc | $609,245 | +5.0% | -8.0% |
| 4 | Advanced Excavating & Demolition LLC | $692,761 | +19% | +5.0% |
Engineer's estimate: $660,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. BCC Ohio Inc | 2. Crawford Construction Company Inc | 3. Vernon Nagel Inc | 4. Advanced Excavating & Demolition LLC |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $1,032.00 | $2,300.00 | $2,500.00 | $15,000 |
| 2 | Pavement removed (202E23000) | SY | 573 | $17.08 | $15.70 | $18.00 | $21.00 |
| 3 | Guardrail removed (202E38000) | FT | 250 | $2.52 | $12.30 | $4.00 | $2.50 |
| 4 | Excavation (203E10000) | CY | 163 | $12.90 | $58.00 | $50.00 | $45.00 |
| 5 | Embankment (203E20000) | CY | 72 | $12.90 | $85.30 | $20.00 | $30.00 |
| 6 | Subgrade compaction (204E10000) | SY | 848 | $2.58 | $2.00 | $1.00 | $6.00 |
| 7 | Pavement planing, asphalt concrete (T = var) (254E01000) | SY | 284 | $6.04 | $40.70 | $5.75 | $6.00 |
| 8 | Guardrail, type MGS, as per plan (606E15051) | FT | 68.75 | $52.08 | $44.00 | $18.95 | $50.00 |
| 9 | Anchor assembly, MGS type E (606E26150) | EACH | 2 | $3,108.00 | $3,250.00 | $2,800.00 | $3,000.00 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,554.00 | $1,600.00 | $1,400.00 | $1,500.00 |
| 11 | MGS bridge terminal assembly, type TST-2, as per plan (606E34601) | EACH | 4 | $3,276.00 | $3,432.00 | $2,800.00 | $3,300.00 |
| 12 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $2,310.00 | $935.00 | $3,500.00 | $4,000.00 |
| 13 | Post construction survey monument verification and report (623E51000) | LS | 1 | $2,310.00 | $935.00 | $3,500.00 | $4,000.00 |
| 14 | Special - mailbox support (690E50000) | EACH | 2 | $267.75 | $293.00 | $135.00 | $300.00 |
| 15 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $246.75 | $280.00 | $135.00 | $300.00 |
| 16 | Seeding and mulching (659E10000) | SY | 367 | $5.93 | $10.00 | $11.00 | $4.00 |
| 17 | Commercial fertilizer (659E20000) | TON | 0.05 | $1,081.60 | $1,150.00 | $850.00 | $500.00 |
| 18 | Water (659E35000) | MGAL | 1.98 | $2.63 | $5.80 | $1.00 | $0.10 |
| 19 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 20 | Aggregate drains (605E31100) | FT | 81 | $21.59 | $37.80 | $20.00 | $66.00 |
| 21 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 103 | $267.75 | $294.00 | $250.00 | $300.00 |
| 22 | Aggregate base (304E20000) | CY | 161 | $111.03 | $105.80 | $100.00 | $115.00 |
| 23 | Non-tracking tack coat (407E20000) | GAL | 142 | $1.05 | $6.60 | $6.00 | $5.00 |
| 24 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 77 | $315.00 | $358.00 | $325.00 | $340.00 |
| 25 | RPM (621E00100) | EACH | 4 | $777.00 | $985.00 | $1,175.00 | $1,100.00 |
| 26 | Raised pavement marker removed (621E54000) | EACH | 4 | $21.00 | $96.00 | $6.50 | $150.00 |
| 27 | Barrier reflector, type 2 (bidirectional) (626E00110) | EACH | 12 | $14.18 | $15.00 | $12.50 | $15.00 |
| 28 | Ground mounted support, no. 3 post (630E03100) | FT | 48 | $26.25 | $27.50 | $25.00 | $25.00 |
| 29 | Removal of ground mounted sign and disposal (630E84900) | EACH | 2 | $13.13 | $120.00 | $25.00 | $15.00 |
| 30 | Removal of ground mounted sign and reerection (630E85100) | EACH | 6 | $89.25 | $110.00 | $100.00 | $85.00 |
| 31 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $15.75 | $27.50 | $25.00 | $15.00 |
| 32 | Edge line, 6", type 1 (642E00104) | MI | 0.13 | $7,875.00 | $13,200 | $12,000 | $12,000 |
| 33 | Center line, type 1 (642E00300) | MI | 0.06 | $7,875.00 | $16,500 | $15,000 | $15,000 |
| 34 | Pavement repair (253E02000) | CY | 20 | $708.75 | $175.00 | $325.00 | $550.00 |
| 35 | Non-tracking tack coat (407E20000) | GAL | 20 | $1.05 | $10.00 | $6.00 | $5.00 |
| 36 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 10 | $63.00 | $225.00 | $500.00 | $510.00 |
| 37 | Compacted aggregate (617E10100) | CY | 50 | $137.25 | $50.00 | $100.00 | $140.00 |
| 38 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $42,524 | $39,000 | $25,000 | $55,000 |
| 39 | Approach slab removed (202E22900) | SY | 80 | $86.59 | $92.40 | $45.00 | $75.00 |
| 40 | Wearing course removed (202E23500) | SY | 156 | $7.61 | $7.00 | $10.00 | $20.00 |
| 41 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $3,663.60 | $11,200 | $15,000 | $7,500.00 |
| 42 | Epoxy coated steel reinforcement (509E10000) | LB | 5,455 | $2.28 | $1.81 | $1.90 | $2.00 |
| 43 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 88 | $30.08 | $30.00 | $28.00 | $23.00 |
| 44 | Class QC2 concrete, superstructure, as per plan (511E31611) | CY | 16 | $2,534.63 | $1,740.00 | $2,700.00 | $3,100.00 |
| 45 | Class QC1 concrete, abutment (511E45710) | CY | 11 | $2,144.01 | $1,540.00 | $1,500.00 | $1,500.00 |
| 46 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 72 | $43.11 | $40.00 | $40.00 | $50.00 |
| 47 | Concrete repair by epoxy injection, as per plan (512E10601) | FT | 10 | $177.00 | $84.00 | $200.00 | $150.00 |
| 48 | Prestressed concrete composite box beam bridge members, level 1, CB17-36, as per plan (515E12021) | EACH | 10 | $10,199 | $10,850 | $13,850 | $12,000 |
| 49 | Nylon reinforced neoprene sheeting (516E25000) | SF | 186 | $23.15 | $16.00 | $50.00 | $15.00 |
| 50 | 1/8" preformed bearing pad, type CDP (516E41100) | EACH | 20 | $53.16 | $56.00 | $70.00 | $25.00 |
| 51 | Elastomeric bearing with internal laminates only (neoprene), as per plan (516E43201) | EACH | 40 | $198.29 | $268.00 | $130.00 | $135.00 |
| 52 | Railing (three steel tube bridge railing) (517E70100) | FT | 56 | $501.90 | $539.00 | $445.00 | $500.00 |
| 53 | Porous backfill with geotextile fabric (518E21230) | LS | 1 | $4,596.00 | $3,200.00 | $6,000.00 | $3,500.00 |
| 54 | Special - steel drip strip (518E22300) | FT | 53 | $33.91 | $32.00 | $18.00 | $25.00 |
| 55 | Patching concrete structure, as per plan (519E11101) | SF | 10 | $197.70 | $461.00 | $175.00 | $400.00 |
| 56 | Reinforced concrete approach slabs (T=12"), as per plan (526E10001) | SY | 100 | $461.26 | $350.00 | $375.00 | $375.00 |
| 57 | Type A installation (526E90010) | FT | 63 | $364.81 | $188.00 | $180.00 | $225.00 |
| 58 | Patching concrete structures with trowelable mortar (843E50000) | SF | 10 | $1,423.21 | $183.00 | $170.00 | $225.00 |
| 59 | Polymer modified asphalt expansion joint system (846E00110) | CF | 26 | $519.69 | $650.00 | $775.00 | $700.00 |
| 60 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,047.40 | $8,700.00 | $7,500.00 | $12,500 |
| 61 | Maintaining traffic (614E11000) | LS | 1 | $3,264.00 | $5,050.00 | $5,000.00 | $35,000 |
| 62 | Field office, type B (619E16010) | MNTH | 4 | $4,255.50 | $800.00 | $1,700.00 | $1,200.00 |
| 63 | Construction layout stakes and surveying, as per plan (623E10001) | LS | 1 | $3,390.00 | $5,300.00 | $15,000 | $7,500.00 |
| 64 | Mobilization (624E10000) | LS | 1 | $1,050.00 | $39,700 | $30,000 | $35,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.