ODOT contract 260475 bid tabulation
WOO-IR 75-13.83 Deck Replacement (BRIDGE REPAIR). Let by Ohio DOT on October 29, 2026, WOO. 3 bids received; low bid $2,769,748 by Eagle Bridge Co, -9.3% against the engineer's estimate of $3,055,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 81
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $2,769,748 | Low | -9.0% |
| 2 | Miller Bros Const Inc | $3,022,171 | +9.0% | -1.0% |
| 3 | Mosser Construction Inc | $3,499,851 | +26% | +15% |
Engineer's estimate: $3,055,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Miller Bros Const Inc | 3. Mosser Construction Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $22,500 | $15,050 | $16,560 |
| 2 | Pavement removed (202E23000) | SY | 1,919 | $8.00 | $4.25 | $3.30 |
| 3 | Guardrail removed (202E38000) | FT | 3,367 | $2.00 | $2.00 | $7.00 |
| 4 | Excavation (203E10000) | CY | 5,212 | $8.00 | $8.00 | $21.25 |
| 5 | Embankment (203E20000) | CY | 5,629 | $9.00 | $8.00 | $12.40 |
| 6 | Subgrade compaction (204E10000) | SY | 1,889 | $5.00 | $1.75 | $2.00 |
| 7 | Excavation of subgrade (204E13000) | CY | 339 | $8.00 | $13.50 | $20.00 |
| 8 | Granular material, type B (204E30010) | CY | 339 | $40.00 | $63.50 | $71.50 |
| 9 | Proof rolling (204E45000) | HR | 2 | $150.00 | $130.00 | $195.00 |
| 10 | Geotextile fabric (204E50000) | SY | 1,016 | $2.00 | $3.10 | $2.65 |
| 11 | Guardrail, type MGS with long posts (606E15100) | FT | 2,613 | $25.40 | $25.40 | $25.40 |
| 12 | Guardrail, type MGS with long posts, as per plan (606E15101) | FT | 500 | $29.80 | $29.80 | $29.80 |
| 13 | Rounded end section (606E20050) | EACH | 2 | $110.00 | $110.00 | $110.00 |
| 14 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,370.00 | $1,370.00 | $1,370.00 |
| 15 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,575.00 | $2,575.00 | $2,575.00 |
| 16 | Curb, type 4-C (609E24510) | FT | 104 | $50.00 | $66.36 | $24.00 |
| 18 | Soil analysis test (659E00100) | EACH | 2 | $450.00 | $40.00 | $100.00 |
| 19 | Topsoil (659E00300) | CY | 494 | $5.00 | $37.50 | $69.00 |
| 20 | Seeding and mulching (659E10000) | SY | 4,449 | $1.75 | $1.05 | $2.50 |
| 21 | Repair seeding and mulching (659E14000) | SY | 222 | $3.50 | $1.00 | $1.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.61 | $1,500.00 | $500.00 | $450.00 |
| 23 | Lime (659E31000) | ACRE | 0.92 | $1.00 | $0.50 | $100.00 |
| 24 | Water (659E35000) | MGAL | 24.03 | $20.00 | $0.10 | $1.00 |
| 25 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 638 | $208.00 | $208.00 | $208.00 |
| 26 | Aggregate base (304E20000) | CY | 478 | $60.00 | $74.00 | $91.00 |
| 27 | Tack coat (407E10000) | GAL | 407 | $1.00 | $1.00 | $1.00 |
| 28 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 274 | $255.00 | $255.00 | $255.00 |
| 29 | Barrier reflector, type 5 (BI-directional) (626E00116) | EACH | 38 | $14.10 | $14.10 | $5.00 |
| 30 | Edge line, 4", type 1 (642E00100) | MI | 0.40 | $2,500.00 | $2,500.00 | $2,500.00 |
| 31 | Center line, type 1 (642E00300) | MI | 0.20 | $2,500.00 | $2,500.00 | $2,500.00 |
| 32 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 100 | $145.00 | $107.57 | $75.00 |
| 33 | Detour signing (614E12420) | LS | 1 | $6,000.00 | $4,991.26 | $5,800.00 |
| 34 | Replacement sign (614E12500) | EACH | 5 | $175.00 | $239.36 | $75.00 |
| 35 | Replacement drum (614E12600) | EACH | 10 | $65.00 | $55.00 | $80.00 |
| 36 | Portable changeable message sign, as per plan (614E18601) | SNMT | 8 | $900.00 | $850.00 | $850.00 |
| 37 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $235,000 | $269,248 | $379,300 |
| 38 | Approach slab removed (202E22900) | SY | 184 | $40.00 | $39.55 | $58.96 |
| 39 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $22,500 | $34,481 | $8,150.00 |
| 40 | Epoxy coated reinforcing steel, as per plan (509E10001) | LB | 41,896 | $1.65 | $1.96 | $1.87 |
| 41 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 26,086 | $1.00 | $1.21 | $1.21 |
| 42 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 31,386 | $1.25 | $1.48 | $1.54 |
| 43 | No. 6 GFRP deformed bars (509E30040) | FT | 42,639 | $1.50 | $1.76 | $2.01 |
| 44 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 324 | $15.00 | $25.50 | $45.80 |
| 45 | Semi-integral diaphragm guide (511E33500) | EACH | 2 | $5,000.00 | $4,879.78 | $6,580.00 |
| 46 | Class QC2 concrete with QC/QA, bridge deck, as per plan (511E34447) | CY | 354 | $1,120.00 | $1,155.23 | $1,520.00 |
| 47 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 100 | $1,250.00 | $928.23 | $1,595.00 |
| 48 | Class QC1 concrete, abutment including footing (511E43510) | CY | 42 | $1,225.00 | $1,291.96 | $1,450.00 |
| 49 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 749 | $30.00 | $29.02 | $41.50 |
| 50 | Type 2 waterproofing (512E33000) | SY | 13 | $40.00 | $118.49 | $70.00 |
| 51 | Welded stud shear connectors (513E20000) | EACH | 3,465 | $3.70 | $4.00 | $3.70 |
| 52 | Surface preparation of existing structural steel (514E00050) | SF | 14,226 | $12.00 | $12.00 | $11.00 |
| 53 | Field painting of existing structural steel, prime coat (514E00056) | SF | 14,226 | $4.00 | $9.00 | $6.00 |
| 54 | Field painting structural steel, intermediate coat (514E00060) | SF | 14,226 | $4.00 | $4.00 | $6.00 |
| 55 | Field painting structural steel, finish coat (514E00066) | SF | 14,226 | $4.00 | $2.50 | $6.00 |
| 56 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 32 | $200.00 | $150.00 | $250.00 |
| 57 | Final inspection repair (514E10000) | EACH | 8 | $200.00 | $250.00 | $500.00 |
| 58 | Field painting, misc.: coating of beam ends (514E27702) | EACH | 10 | $4,000.00 | $2,500.00 | $5,900.00 |
| 59 | 1" preformed expansion joint filler (516E13600) | SF | 16 | $10.00 | $15.19 | $9.80 |
| 60 | 2" preformed expansion joint filler (516E13900) | SF | 106 | $14.00 | $11.18 | $17.50 |
| 61 | Semi-integral abutment expansion joint seal (516E14020) | FT | 93 | $40.00 | $41.52 | $63.25 |
| 62 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 15 | $3,000.00 | $3,652.29 | $4,788.00 |
| 63 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44301) | EACH | 10 | $3,150.00 | $3,814.38 | $4,367.00 |
| 64 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $61,250 | $40,446 | $51,200 |
| 65 | Porous backfill with geotextile fabric (518E21200) | CY | 62 | $130.00 | $157.88 | $98.58 |
| 66 | 6" perforated corrugated plastic pipe (518E40000) | FT | 102 | $20.00 | $14.18 | $15.00 |
| 67 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 103 | $20.00 | $18.40 | $16.00 |
| 68 | Special - composite fiber wrap system (519E00100) | SF | 933 | $65.00 | $85.00 | $95.00 |
| 69 | Patching concrete structure, as per plan (519E11101) | SF | 175 | $170.00 | $185.00 | $414.00 |
| 70 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25011) | SY | 197 | $425.00 | $553.55 | $445.00 |
| 71 | Type C installation (526E90030) | FT | 69 | $280.00 | $359.49 | $271.00 |
| 72 | Special - form liner (530E13000) | SF | 2,042 | $15.00 | $16.47 | $23.20 |
| 73 | Vandal protection fence, 6' straight, coated fabric (607E39900) | FT | 582 | $108.50 | $118.50 | $108.00 |
| 74 | Structure grounding system (625E33000) | EACH | 1 | $12,000 | $12,500 | $29,000 |
| 75 | Galvanic anode protection, as per plan (844E20001) | EACH | 113 | $45.00 | $50.00 | $110.00 |
| 76 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $30,000 | $14,302 | $18,864 |
| 77 | Maintaining traffic (614E11000) | LS | 1 | $80,000 | $161,251 | $62,500 |
| 78 | Construction layout stakes and surveying (623E10000) | LS | 1 | $17,500 | $20,160 | $44,530 |
| 79 | Mobilization (624E10000) | LS | 1 | $135,000 | $151,109 | $100,000 |
| 100 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 104 | $100.00 | $176.70 | $193.00 |
| 101 | Erosion control (832E30000) | EACH | 15,179 | $1.00 | $1.00 | $1.00 |
| 102 | Armorless preformed joint seal (516E10010) | FT | 69 | $70.00 | $56.77 | $18.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.