ODOT contract 260477 bid tabulation
ATB-IR 90 Vacant Rest Areas TP (PARKING AREAS). Let by Ohio DOT on October 29, 2026, ATB. 3 bids received; low bid $9,185,577 by Karvo Companies Inc, +7.8% against the engineer's estimate of $8,522,000.
- Owner
- Ohio DOT
- Letting
- 29 OCT 2026
- Pay items
- 129
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Karvo Companies Inc | $9,185,577 | Low | +8.0% |
| 2 | Great Lakes Construction Co | $9,242,650 | +1.0% | +8.0% |
| 3 | Anthony Allega Cement Contractor Inc | $9,514,041 | +4.0% | +12% |
Engineer's estimate: $8,522,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Karvo Companies Inc | 2. Great Lakes Construction Co | 3. Anthony Allega Cement Contractor Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $75,000 | $26,500 | $58,000 |
| 2 | Pavement removed (202E23000) | SY | 1,289 | $15.00 | $35.00 | $21.20 |
| 3 | Guardrail removed (202E38000) | FT | 264 | $2.40 | $2.40 | $2.55 |
| 4 | Catch basin removed (202E58100) | EACH | 1 | $500.00 | $950.00 | $1,385.30 |
| 5 | Special - pipe cleanout, 24" and under (202E70110) | FT | 260 | $5.00 | $20.00 | $20.00 |
| 6 | Special - pipe cleanout, 27" to 48" (202E70120) | FT | 1,010 | $5.00 | $22.00 | $25.00 |
| 7 | Fence removed (202E75000) | FT | 300 | $3.50 | $3.50 | $3.58 |
| 8 | Gate removed (202E75250) | EACH | 1 | $500.00 | $240.00 | $245.14 |
| 9 | Excavation (203E10000) | CY | 63,118 | $20.00 | $16.00 | $16.19 |
| 10 | Embankment (203E20000) | CY | 28,743 | $3.25 | $7.00 | $17.99 |
| 11 | Subgrade compaction (204E10000) | SY | 43,560 | $2.00 | $1.50 | $1.06 |
| 12 | Excavation of subgrade (204E13000) | CY | 16,814 | $32.00 | $33.00 | $24.39 |
| 13 | Embankment (204E20000) | CY | 16,814 | $8.00 | $4.00 | $12.36 |
| 14 | Proof rolling (204E45000) | HR | 8 | $300.00 | $500.00 | $345.54 |
| 15 | Guardrail, type MGS (606E15050) | FT | 325 | $26.00 | $26.00 | $27.61 |
| 16 | Anchor assembly, MGS type E, as per plan (606E26151) | EACH | 1 | $3,130.00 | $3,130.00 | $3,324.29 |
| 17 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,480.00 | $1,480.00 | $1,571.87 |
| 18 | Fence, type CLT (607E23000) | FT | 300 | $34.50 | $34.50 | $35.24 |
| 19 | Gate, type CLT (607E61200) | EACH | 1 | $1,820.00 | $1,820.00 | $1,858.99 |
| 20 | Fenceline seeding and mulching (607E70000) | FT | 350 | $3.75 | $3.75 | $1.53 |
| 21 | Fence, misc.:dumpster screen wall (607E98000) | FT | 76 | $215.00 | $215.00 | $219.61 |
| 22 | Special - bollard (690E50600) | EACH | 10 | $935.00 | $950.00 | $955.03 |
| 23 | Special - as-built construction plans (690E91000) | LS | 1 | $2,500.00 | $1,500.00 | $3,025.00 |
| 24 | Special - survey control verification (690E98400) | LS | 1 | $4,000.00 | $4,500.00 | $6,000.00 |
| 25 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 465 | $50.00 | $65.00 | $92.87 |
| 26 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 14 | $150.00 | $225.00 | $94.52 |
| 27 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 4 | $250.00 | $275.00 | $581.78 |
| 28 | Soil analysis test (659E00100) | EACH | 2 | $25.00 | $25.00 | $400.00 |
| 29 | Topsoil (659E00300) | CY | 3,218 | $15.00 | $25.00 | $30.55 |
| 30 | Seeding and mulching, class 1 (659E00500) | SY | 28,987 | $1.50 | $1.50 | $1.86 |
| 31 | Commercial fertilizer (659E20000) | TON | 3.91 | $250.00 | $250.00 | $1,500.00 |
| 32 | Lime (659E31000) | ACRE | 5.99 | $25.00 | $25.00 | $30.00 |
| 33 | Water (659E35000) | MGAL | 157 | $1.00 | $1.00 | $50.00 |
| 34 | Slope erosion protection (670E00500) | SY | 2,112 | $1.15 | $1.15 | $2.50 |
| 35 | Ditch erosion protection mat, type B (670E00720) | SY | 150 | $1.15 | $1.15 | $4.50 |
| 36 | Storm water pollution prevention plan (832E15000) | LS | 1 | $15,000 | $4,500.00 | $3,900.00 |
| 37 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $15,000 | $11,000 | $11,200 |
| 38 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $15,000 | $13,891 | $12,500 |
| 39 | Erosion control (832E30000) | EACH | 84,300 | $1.00 | $1.00 | $1.00 |
| 40 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 909 | $4.50 | $4.50 | $8.50 |
| 41 | Concrete masonry (602E20000) | CY | 2 | $2,575.00 | $2,400.00 | $3,979.57 |
| 42 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 29,051 | $12.50 | $17.50 | $15.23 |
| 43 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 430 | $15.00 | $21.00 | $30.93 |
| 44 | 6" conduit, type F (611E01500) | FT | 20 | $35.00 | $47.00 | $33.03 |
| 45 | 15" conduit, type B (611E05900) | FT | 1,095 | $110.00 | $135.00 | $126.80 |
| 46 | 15" conduit, type B (611E05900) | FT | 8 | $140.00 | $230.00 | $772.52 |
| 47 | 15" conduit, type C (611E06100) | FT | 465 | $85.00 | $110.00 | $116.32 |
| 48 | 21" conduit, type C (611E09100) | FT | 270 | $105.00 | $150.00 | $169.55 |
| 49 | 24" conduit, type B (611E10400) | FT | 89 | $140.00 | $220.00 | $265.94 |
| 50 | 42" conduit, type A, 706.02 (611E19200) | FT | 16 | $350.00 | $710.00 | $970.18 |
| 51 | Catch basin, no. 3A (611E98180) | EACH | 12 | $5,000.00 | $3,250.00 | $5,546.22 |
| 52 | Catch basin, no. 5 (611E98300) | EACH | 4 | $6,000.00 | $6,100.00 | $7,552.50 |
| 53 | Catch basin, no. 8 (611E98410) | EACH | 1 | $5,000.00 | $6,500.00 | $9,427.77 |
| 54 | Manhole, no. 3 (611E99574) | EACH | 5 | $10,000 | $8,000.00 | $15,521 |
| 55 | Precast reinforced concrete outlet (611E99710) | EACH | 7 | $400.00 | $490.00 | $531.96 |
| 56 | Pavement planing, asphalt concrete, variable depth (254E01000) | SY | 6,415 | $5.00 | $4.00 | $4.00 |
| 57 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 6,914 | $215.00 | $200.00 | $210.00 |
| 58 | Aggregate base (304E20000) | CY | 8,855 | $90.00 | $110.00 | $88.46 |
| 59 | Non-tracking tack coat (407E20000) | GAL | 5,719 | $3.50 | $4.00 | $4.00 |
| 60 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,986 | $275.00 | $270.00 | $275.00 |
| 61 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 3,310 | $230.00 | $245.00 | $245.00 |
| 62 | 6" non-reinforced concrete pavement, class QC 1P with QC/QA (452E10020) | SY | 69 | $90.00 | $230.00 | $186.30 |
| 63 | 10" non-reinforced concrete pavement, class QC 1P with QC/QA (452E14020) | SY | 234 | $115.00 | $200.00 | $141.11 |
| 64 | Curb, type 7 (609E28000) | FT | 5,253 | $22.00 | $37.00 | $36.27 |
| 65 | Void reducing asphalt membrane (vram) (872E10000) | FT | 7,709 | $4.00 | $5.00 | $5.00 |
| 66 | Connection, fused pull apart (625E00450) | EACH | 58 | $145.00 | $125.00 | $125.00 |
| 67 | Connection, unfused permanent (625E00480) | EACH | 42 | $100.00 | $125.00 | $125.00 |
| 68 | Light pole, conventional, AT18B40 (625E10490) | EACH | 20 | $4,750.00 | $4,600.00 | $4,600.00 |
| 69 | Light pole, conventional, AT20B40 (625E10490) | EACH | 9 | $4,750.00 | $4,700.00 | $4,700.00 |
| 70 | Light tower, misc.: light tower, BB45 (625E13500) | EACH | 12 | $22,500 | $20,000 | $20,000 |
| 71 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 29 | $2,000.00 | $1,500.00 | $1,500.00 |
| 72 | Light tower foundation, misc.: 36" X 8' deep (625E15700) | EACH | 12 | $4,000.00 | $5,000.00 | $5,000.00 |
| 73 | No. 1/0 AWG 2400 volt distribution cable (625E22900) | FT | 3,504 | $11.00 | $9.00 | $9.00 |
| 74 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 2,756 | $3.00 | $2.75 | $2.75 |
| 75 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,095 | $5.00 | $3.70 | $3.70 |
| 76 | Distribution cable, misc.: no. 3/0 AWG 600 volt (625E23308) | FT | 4,764 | $12.00 | $11.50 | $11.50 |
| 77 | No. 10 AWG pole and bracket cable (625E23400) | FT | 5,121 | $1.14 | $1.50 | $1.50 |
| 78 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 9,724 | $20.00 | $13.00 | $13.00 |
| 79 | Conduit, 3", 725.04 (625E25500) | FT | 285 | $45.00 | $35.00 | $35.00 |
| 80 | Conduit, concrete encased, 3" (625E25802) | FT | 2,256 | $20.00 | $20.00 | $20.00 |
| 81 | Conduit, concrete encased, 4" (625E25802) | FT | 3,076 | $20.00 | $25.00 | $25.00 |
| 82 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 29 | $575.00 | $400.00 | $400.00 |
| 83 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 18 | $1,375.00 | $1,100.00 | $1,100.00 |
| 84 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 6 | $1,750.00 | $1,300.00 | $1,300.00 |
| 85 | Trench, 24" deep (625E29002) | FT | 9,560 | $8.00 | $6.00 | $6.00 |
| 86 | Trench, 36" deep (625E29100) | FT | 2,666 | $9.15 | $7.50 | $7.50 |
| 87 | Pull box, 725.06, size 18 (625E30530) | EACH | 7 | $2,250.00 | $1,800.00 | $1,800.00 |
| 88 | Pull box, 725.08, 18" (625E30700) | EACH | 12 | $1,199.20 | $1,200.00 | $1,200.00 |
| 89 | Ground rod (625E32000) | EACH | 59 | $164.68 | $200.00 | $200.00 |
| 90 | Power service, as per plan (625E34001) | EACH | 4 | $13,500 | $15,000 | $15,000 |
| 91 | Underground warning/marking tape, as per plan (625E36011) | FT | 12,226 | $2.00 | $0.50 | $0.50 |
| 92 | Arc flash calculations and label (CC-'PR') (625E76000) | EACH | 1 | $2,176.00 | $500.00 | $500.00 |
| 93 | Arc flash calculations and label (CC-'WR') (625E76000) | EACH | 1 | $2,176.00 | $500.00 | $500.00 |
| 94 | Delineator, post ground mounted (620E00500) | EACH | 33 | $75.00 | $75.00 | $75.00 |
| 95 | Delineator, post ground mounted (620E00500) | EACH | 10 | $75.00 | $75.00 | $75.00 |
| 96 | Removal of delineator (620E31200) | EACH | 23 | $10.00 | $10.00 | $10.00 |
| 97 | RPM (621E00100) | EACH | 186 | $47.00 | $47.00 | $47.00 |
| 98 | Barrier reflector, type 3, one-way, white (626E00112) | EACH | 4 | $12.85 | $12.85 | $12.85 |
| 99 | Ground mounted support, no. 2 post (630E02100) | FT | 156.50 | $17.00 | $17.00 | $17.15 |
| 100 | Ground mounted support, no. 3 post (630E03100) | FT | 216.20 | $17.50 | $17.50 | $17.65 |
| 101 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 81.20 | $39.00 | $39.00 | $39.34 |
| 102 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 180.10 | $72.00 | $72.00 | $72.62 |
| 103 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 156.60 | $76.00 | $76.00 | $76.66 |
| 104 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 45.90 | $46.00 | $46.00 | $46.40 |
| 105 | Sign post reflector (630E08600) | EACH | 12 | $45.00 | $45.00 | $45.39 |
| 106 | Breakaway structural beam connection (630E09000) | EACH | 20 | $740.00 | $740.00 | $746.40 |
| 107 | Sign, flat sheet (630E80100) | SF | 162.30 | $20.00 | $20.00 | $20.17 |
| 108 | Sign, ground mounted extrusheet (630E80200) | SF | 648 | $28.50 | $28.50 | $28.75 |
| 109 | Ground mounted structural beam support foundation (630E84500) | EACH | 20 | $1,125.00 | $1,125.00 | $1,134.73 |
| 110 | Removal of ground mounted sign and disposal (630E84900) | EACH | 7 | $10.00 | $10.00 | $10.09 |
| 111 | Removal of ground mounted major sign and reerection (630E85600) | EACH | 2 | $445.00 | $445.00 | $448.85 |
| 112 | Removal of ground mounted post support and disposal (630E86002) | EACH | 7 | $15.00 | $15.00 | $15.13 |
| 113 | Removal of ground mounted structural beam support (630E86102) | EACH | 4 | $265.00 | $265.00 | $267.29 |
| 114 | Parking lot stall marking (646E20200) | FT | 9,044 | $2.10 | $2.10 | $2.10 |
| 115 | Wrong way arrow (646E20320) | EACH | 4 | $250.00 | $250.00 | $250.00 |
| 116 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 1.89 | $4,400.00 | $4,400.00 | $4,400.00 |
| 117 | Wet reflective epoxy pavement marking, channelizing line, 12" (807E12310) | FT | 3,625 | $1.30 | $1.30 | $1.30 |
| 118 | Wet reflective epoxy pavement marking, dotted line, 6" (807E12410) | FT | 3,745 | $0.90 | $0.90 | $0.90 |
| 119 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 1.89 | $3,200.00 | $3,200.00 | $3,200.00 |
| 120 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 3,745 | $0.75 | $0.75 | $0.75 |
| 121 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,625 | $0.95 | $0.95 | $0.95 |
| 122 | Work zone increased penalties sign (614E12484) | EACH | 4 | $250.00 | $195.00 | $251.86 |
| 123 | Water (616E10000) | MGAL | 261 | $1.00 | $50.00 | $59.77 |
| 124 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 16 | $650.00 | $585.00 | $653.57 |
| 125 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $50,000 | $75,000 | $38,194 |
| 126 | Maintaining traffic (614E11000) | LS | 1 | $50,000 | $50,000 | $315,647 |
| 127 | Field office, type C (619E16020) | MNTH | 8 | $3,000.00 | $3,500.00 | $3,067.96 |
| 128 | Construction layout stakes and surveying (623E10000) | LS | 1 | $200,000 | $68,600 | $93,500 |
| 129 | Mobilization (624E10000) | LS | 1 | $377,000 | $462,000 | $200,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 29, 2026. Compiled by Mirage Metrics.