Asphalt concrete intermediate course, 19 MM, type A (446), ODOT 442E10100
Low bidders on ODOT contracts carried a median of $216.00 per CY for this item, over the 24 months to 12 NOV 2026, across 30 low bids. Half of all 96 bids fell between $212.30 and $275.75.
- Owner
- Ohio DOT
- Item
- 442E10100
- Unit
- CY
- Data through
- 12 NOV 2026
ODOT prints this item as “ASPHALT CONCRETE INTERMEDIATE COURSE, 19 MM, TYPE”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 24 | 24 | $135.72 | 72 | $160.00 |
| 2021 | 24 | 27 | $165.00 | 132 | $177.00 |
| 2022 | 18 | 22 | $202.50 | 79 | $210.00 |
| 2023 | 14 | 13 | $226.00 | 39 | $250.00 |
| 2024 | 8 | 8 | $220.00 | 19 | $255.00 |
| 2025 | 12 | 12 | $201.06 | 30 | $214.95 |
| 2026 | 16 | 16 | $231.00 | 63 | $250.00 |
Bid prices as published, not adjusted for inflation.
By quantity
| Quantity (CY) | Low bids | Low-bid median |
|---|---|---|
| 160 to 548 | 7 | $275.00 |
| 630 to 2,333 | 8 | $211.00 |
| 2,475 to 5,700 | 7 | $200.00 |
| 6,111 to 24,472 | 8 | $209.45 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Shelly & Sands Inc | 50 | 34 (68%) |
| Complete General Construction Company | 38 | 16 (42%) |
| Barrett Paving Materials Inc | 16 | 12 (75%) |
| Miller Bros Const Inc | 17 | 11 (65%) |
| Great Lakes Construction Co | 19 | 9 (47%) |
| Sunesis Construction Co | 18 | 8 (44%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260521 | GUE | 160 | $330.00 | $330.00 | 8 | Shelly & Sands Inc | ODOT |
| 29 OCT 2026 | 260399 | CUY | 1,264 | $360.00 | $343.50 | 4 | Tri-Mor Corp | ODOT |
| 29 OCT 2026 | 260477 | ATB | 3,310 | $230.00 | $245.00 | 3 | Karvo Companies Inc | ODOT |
| 15 OCT 2026 | 260484 | GAL | 1,713 | $226.25 | $226.25 | 3 | Allard Excavation LLC | ODOT |
| 01 OCT 2026 | 260440 | AUG | 2,610 | $230.00 | $244.00 | 5 | Helms and Sons Excavating | ODOT |
| 30 JUL 2026 | 268015 | PRE | 529 | $301.40 | $287.50 | 6 | R B Jergens Contractors Inc | ODOT |
| 21 MAY 2026 | 260268 | JAC | 526 | $255.00 | $265.50 | 4 | Shelly & Sands Inc | ODOT |
| 07 MAY 2026 | 260248 | SAN | 2,475 | $250.00 | $250.00 | 3 | Great Lakes Demolition Company | ODOT |
| 17 APR 2026 | 268004 | SUM | 548 | $273.06 | $215.00 | 3 | Anthony Allega Cement Contractor Inc | ODOT |
| 09 APR 2026 | 268005 | MED | 2,333 | $206.00 | $235.00 | 3 | Great Lakes Construction Co | ODOT |
| 26 MAR 2026 | 260076 | MAH | 24,472 | $232.00 | $232.00 | 3 | Karvo Companies Inc | ODOT |
| 26 MAR 2026 | 260148 | FRA | 499 | $291.00 | $291.00 | 3 | Complete General Construction Company | ODOT |
| 12 MAR 2026 | 260141 | ROS | 170 | $195.00 | $303.00 | 4 | Shelly & Sands Inc | ODOT |
| 12 MAR 2026 | 260141 | ROS | 1,241 | $176.00 | $200.00 | 4 | Shelly & Sands Inc | ODOT |
| 12 MAR 2026 | 268003 | AUG | 1,253 | n/a | $222.66 | 1 | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.