ODOT contract 260484 bid tabulation

GAL-US 35 Rest Areas TP (PARKING AREAS). Let by Ohio DOT on October 15, 2026, GAL. 3 bids received; low bid $3,951,942 by Allard Excavation LLC, -0.2% against the engineer's estimate of $3,959,000.

Owner
Ohio DOT
Letting
15 OCT 2026
Pay items
118
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Allard Excavation LLC$3,951,942Low0.0%
2Alan Stone Co Inc$4,228,003+7.0%+7.0%
3D G M Inc$4,243,649+7.0%+7.0%
ODOT contract 260484: bids by rank

Engineer's estimate: $3,959,000.

Bid tabulation

LinePay itemUnitQuantity1. Allard Excavation LLC2. Alan Stone Co Inc3. D G M Inc
1Clearing and grubbing, as per plan (201E11001)LS1$20,000$50,000$50,000
2Headwall removed (202E20010)EACH1$96.00$1,000.00$250.00
3Pavement removed (202E23000)SY3,886$11.00$15.00$10.00
4Walk removed (202E30000)SF22,216$2.00$1.00$1.00
5Curb removed (202E32000)FT2,839$12.00$2.50$2.50
6Pipe removed, 24" and under (202E35100)FT1,836$6.00$15.00$11.00
7Manhole removed (202E58000)EACH2$600.00$460.00$500.00
8Catch basin removed (202E58100)EACH11$250.00$460.00$300.00
9Fence removed (202E75000)FT110$2.00$4.50$7.00
10Valve box removed (202E75610)EACH1$148.00$390.00$400.00
11Removal misc.:bench removed for reuse (202E98100)EACH9$155.00$560.00$125.00
12Removal misc.:concrete ashtray removed for reuse (202E98100)EACH2$96.00$510.00$100.00
13Removal misc.:concrete planter box removed for reu (202E98100)EACH4$96.00$860.00$200.00
14Removal misc.:concrete trash can removed for reuse (202E98100)EACH11$148.00$390.00$150.00
15Removal misc.:grill removed for reuse (202E98100)EACH2$96.00$860.00$175.00
16Removal misc.:picnic table removed for resue (202E98100)EACH4$203.00$510.00$275.00
17Removal misc.:pavers removed (202E98200)FT966$2.00$25.00$3.00
18Removal misc.:landscaping removed (202E98300)SY106$4.00$50.00$12.00
19Removal misc.:rock channel protection removed (202E98300)SY19$23.00$120.00$40.00
20Excavation (203E10000)CY6,113$17.00$20.00$15.00
21Embankment (203E20000)CY6,199$10.00$10.00$23.00
22Subgrade compaction (204E10000)SY12,310$2.00$2.00$3.50
23Excavation of subgrade (204E13000)CY593$27.00$30.00$13.00
24Granular material, type C (204E30020)CY593$89.00$98.00$95.00
25Proof rolling (204E45000)HR4$280.00$1,000.00$75.00
26Geotextile fabric (204E50000)SY1,778$1.00$1.00$1.50
27Full depth pavement sawing (252E01500)FT2,087$2.00$4.00$3.50
28Fence, misc.:wooden slat fence (607E98000)FT100$207.00$250.00$235.00
296" concrete walk (608E13000)SF10,933$10.75$14.00$19.00
30Curb ramp (608E52000)SF1,164$18.00$23.00$25.00
31Preconstruction survey monument verification and report (623E50000)LS1$6,700.00$4,000.00$1,000.00
32Post construction survey monument verification and report (623E51000)LS1$6,700.00$4,000.00$1,000.00
33Special - bollard (690E50600)EACH8$1,070.00$700.00$700.00
34Inspection and compaction testing of unbound materials (878E25000)LS1$49,020$20,000$15,000
35Tied concrete block mat with type 1 underlayment (601E21050)SY9$91.00$120.00$200.00
36Tied concrete block mat with type 2 underlayment (601E21060)SY28$122.00$80.00$160.00
37Rock channel protection, type C with geotextile fabric (601E32204)CY3$165.00$500.00$400.00
38Soil analysis test (659E00100)EACH2$150.00$225.00$70.00
39Topsoil (659E00300)CY739$33.00$25.00$25.00
40Seeding and mulching (659E10000)SY6,655$1.00$1.50$2.00
41Repair seeding and mulching (659E14000)SY333$1.00$1.00$0.05
42Inter-seeding (659E15000)SY333$1.00$0.60$0.05
43Commercial fertilizer (659E20000)TON1.50$1,250.00$660.00$1,500.00
44Lime (659E31000)ACRE1.38$150.00$0.30$300.00
45Water (659E35000)MGAL37$1.00$1.00$1.00
46Storm water pollution prevention plan (832E15000)LS1$3,500.00$3,500.00$4,000.00
47Storm water pollution prevention inspections (832E15002)LS1$8,700.00$13,000$13,000
48Storm water pollution prevention inspection software (832E15010)LS1$12,000$13,000$12,000
49Erosion control (832E30000)EACH68,000$1.00$1.00$1.00
50Concrete masonry (602E20000)CY2$2,377.00$2,300.00$1,600.00
514" base pipe underdrains (605E06000)FT6,988$12.00$15.00$10.00
524" conduit, type F for underdrain outlet (611E00410)FT397$20.00$20.00$27.50
538" conduit, type C (611E02000)FT5$178.00$500.00$300.00
5412" conduit, type B (611E04400)FT668$101.00$75.00$102.50
5515" conduit, type B (611E05900)FT207$102.00$110.00$113.00
5615" conduit, type C (611E06100)FT102$103.00$80.00$85.00
5718" conduit, type B (611E07400)FT95$160.00$85.00$215.00
58Catch basin, no. 3 (611E98150)EACH12$5,985.00$5,100.00$6,650.00
59Catch basin, no. 3A (611E98180)EACH2$6,767.00$4,900.00$4,250.00
60Manhole, no. 3 (611E99574)EACH3$5,665.00$3,700.00$7,000.00
61Manhole adjusted to grade (611E99654)EACH1$808.00$1,700.00$600.00
62Precast reinforced concrete outlet (611E99710)EACH5$317.00$450.00$400.00
63Pavement planing, asphalt concrete, 4" (254E01000)SY12,788$4.35$3.00$4.35
64Asphalt concrete base, PG64-22, (449) (301E56000)CY2,134$204.25$220.00$222.00
65Aggregate base (304E20000)CY2,058$96.00$90.00$100.00
66Tack coat (407E10000)GAL2,726$2.50$3.00$2.50
67Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000)CY1,030$266.00$280.00$280.00
68Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100)CY1,713$226.25$235.00$226.25
6910" non-reinforced concrete pavement, class QC 1P (452E14010)SY102$170.00$180.00$200.00
70Curb, type 6 (609E26000)FT914$26.00$51.00$26.50
71Curb, type 7 (609E28000)FT2,800$29.00$60.00$27.85
724" concrete traffic island (609E50000)SY1,268$74.00$65.00$50.00
734" water main ductile iron pipe ansi class 52, push-on joints and fittings (638E00100)FT235$139.00$200.00$180.00
748" steel pipe encasement, open cut (638E06300)FT42$232.00$200.00$110.00
754" gate valve and valve box (638E07700)EACH4$3,553.00$1,600.00$2,750.00
764" cutting-in sleeve (638E08702)EACH2$1,089.00$4,500.00$1,500.00
77Fire hydrant removed and reset (638E10500)EACH3$5,034.00$4,500.00$7,000.00
78Valve box adjusted to grade (638E10800)EACH1$808.00$250.00$400.00
79Connection, fused pull apart (625E00450)EACH64$169.00$200.00$180.00
80Connection, unfused permanent (625E00480)EACH21$160.00$190.00$170.00
81Light pole, conventional AT18B40 (625E10490)EACH15$4,881.00$5,000.00$5,500.00
82Light tower, misc.: light tower B45 (625E13500)EACH15$24,545$25,000$25,750
83Light pole foundation, 24" X 8' deep (625E14100)EACH15$1,845.00$2,000.00$1,900.00
84Light tower foundation, misc.: 36" X 10' deep (625E15700)EACH15$6,012.00$6,500.00$6,300.00
85No. 4 AWG 2400 volt distribution cable (625E23200)FT3,648$4.74$5.00$5.00
86No. 10 AWG pole and bracket cable (625E23400)FT5,085$1.58$2.00$1.65
871-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT5,140$13.95$15.00$15.00
88Conduit, 2", 725.04 (625E25400)FT1,106$28.27$30.00$32.00
89Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH15$501.00$515.00$525.00
90Luminaire, high mast, solid state (LED), as per plan (625E26263)EACH15$1,890.00$2,000.00$2,000.00
91Trench, 24" deep (625E29002)FT4,898$7.70$8.00$8.00
92Trench in paved area (625E29400)FT962$10.98$15.00$12.00
93Pull box, 725.08, 18" (625E30700)EACH11$1,366.00$1,600.00$1,440.00
94Pull box removed (625E31510)EACH8$232.00$280.00$245.00
95Ground rod (625E32000)EACH30$411.00$490.00$425.00
96Power service, as per plan (625E34001)EACH2$13,620$16,000$14,300
97Underground warning marking tape (625E36010)FT6,175$0.11$0.10$0.12
98Light pole removed (625E75400)EACH19$220.00$260.00$230.00
99Light pole foundation removed (625E75500)EACH19$256.00$310.00$265.00
100Luminaire removed (625E75506)EACH19$110.00$130.00$115.00
101Arc flash calculations and label, power service (625E76000)EACH2$3,655.00$4,400.00$3,750.00
102Ground mounted support, no. 3 post (630E03100)FT541.50$19.06$15.00$16.00
103Sign post reflector (630E08600)EACH2$59.23$65.00$60.00
104Removal of ground mounted sign and storage (630E85000)EACH14$17.02$40.00$35.00
105Removal of ground mounted sign and reerection (630E85100)EACH23$63.51$230.00$210.00
106Removal of ground mounted post support and disposal (630E86002)EACH41$22.70$40.00$35.00
107Edge line, 6" (644E00104)MI0.28$6,240.00$9,500.00$8,500.00
108Channelizing line, 8" (644E00400)FT40$2.00$3.50$3.00
109Transverse/diagonal line, as per plan (644E00701)FT1,725$1.85$2.50$2.20
110Chevron marking (644E00720)FT16$5.75$10.00$10.00
111Parking lot stall marking (644E01200)FT7,526$1.85$2.50$2.25
112Handicap symbol marking (644E01600)EACH6$250.00$150.00$130.00
113Water (616E10000)MGAL30$1.00$1.00$1.00
114Premium for contract performance bond and for payment bond (103E05000)LS1$26,000$30,000$125,000
115Maintaining traffic (614E11000)LS1$25,000$15,000$75,000
116Construction layout stakes and surveying (623E10000)LS1$73,000$50,000$35,000
117Mobilization (624E10000)LS1$140,000$175,000$100,000
200Special - bollard (690E50600)EACH26$1,402.00$850.00$875.00
ODOT contract 260484: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 15, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy