ODOT contract 260484 bid tabulation
GAL-US 35 Rest Areas TP (PARKING AREAS). Let by Ohio DOT on October 15, 2026, GAL. 3 bids received; low bid $3,951,942 by Allard Excavation LLC, -0.2% against the engineer's estimate of $3,959,000.
- Owner
- Ohio DOT
- Letting
- 15 OCT 2026
- Pay items
- 118
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Allard Excavation LLC | $3,951,942 | Low | 0.0% |
| 2 | Alan Stone Co Inc | $4,228,003 | +7.0% | +7.0% |
| 3 | D G M Inc | $4,243,649 | +7.0% | +7.0% |
Engineer's estimate: $3,959,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Allard Excavation LLC | 2. Alan Stone Co Inc | 3. D G M Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $20,000 | $50,000 | $50,000 |
| 2 | Headwall removed (202E20010) | EACH | 1 | $96.00 | $1,000.00 | $250.00 |
| 3 | Pavement removed (202E23000) | SY | 3,886 | $11.00 | $15.00 | $10.00 |
| 4 | Walk removed (202E30000) | SF | 22,216 | $2.00 | $1.00 | $1.00 |
| 5 | Curb removed (202E32000) | FT | 2,839 | $12.00 | $2.50 | $2.50 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 1,836 | $6.00 | $15.00 | $11.00 |
| 7 | Manhole removed (202E58000) | EACH | 2 | $600.00 | $460.00 | $500.00 |
| 8 | Catch basin removed (202E58100) | EACH | 11 | $250.00 | $460.00 | $300.00 |
| 9 | Fence removed (202E75000) | FT | 110 | $2.00 | $4.50 | $7.00 |
| 10 | Valve box removed (202E75610) | EACH | 1 | $148.00 | $390.00 | $400.00 |
| 11 | Removal misc.:bench removed for reuse (202E98100) | EACH | 9 | $155.00 | $560.00 | $125.00 |
| 12 | Removal misc.:concrete ashtray removed for reuse (202E98100) | EACH | 2 | $96.00 | $510.00 | $100.00 |
| 13 | Removal misc.:concrete planter box removed for reu (202E98100) | EACH | 4 | $96.00 | $860.00 | $200.00 |
| 14 | Removal misc.:concrete trash can removed for reuse (202E98100) | EACH | 11 | $148.00 | $390.00 | $150.00 |
| 15 | Removal misc.:grill removed for reuse (202E98100) | EACH | 2 | $96.00 | $860.00 | $175.00 |
| 16 | Removal misc.:picnic table removed for resue (202E98100) | EACH | 4 | $203.00 | $510.00 | $275.00 |
| 17 | Removal misc.:pavers removed (202E98200) | FT | 966 | $2.00 | $25.00 | $3.00 |
| 18 | Removal misc.:landscaping removed (202E98300) | SY | 106 | $4.00 | $50.00 | $12.00 |
| 19 | Removal misc.:rock channel protection removed (202E98300) | SY | 19 | $23.00 | $120.00 | $40.00 |
| 20 | Excavation (203E10000) | CY | 6,113 | $17.00 | $20.00 | $15.00 |
| 21 | Embankment (203E20000) | CY | 6,199 | $10.00 | $10.00 | $23.00 |
| 22 | Subgrade compaction (204E10000) | SY | 12,310 | $2.00 | $2.00 | $3.50 |
| 23 | Excavation of subgrade (204E13000) | CY | 593 | $27.00 | $30.00 | $13.00 |
| 24 | Granular material, type C (204E30020) | CY | 593 | $89.00 | $98.00 | $95.00 |
| 25 | Proof rolling (204E45000) | HR | 4 | $280.00 | $1,000.00 | $75.00 |
| 26 | Geotextile fabric (204E50000) | SY | 1,778 | $1.00 | $1.00 | $1.50 |
| 27 | Full depth pavement sawing (252E01500) | FT | 2,087 | $2.00 | $4.00 | $3.50 |
| 28 | Fence, misc.:wooden slat fence (607E98000) | FT | 100 | $207.00 | $250.00 | $235.00 |
| 29 | 6" concrete walk (608E13000) | SF | 10,933 | $10.75 | $14.00 | $19.00 |
| 30 | Curb ramp (608E52000) | SF | 1,164 | $18.00 | $23.00 | $25.00 |
| 31 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $6,700.00 | $4,000.00 | $1,000.00 |
| 32 | Post construction survey monument verification and report (623E51000) | LS | 1 | $6,700.00 | $4,000.00 | $1,000.00 |
| 33 | Special - bollard (690E50600) | EACH | 8 | $1,070.00 | $700.00 | $700.00 |
| 34 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $49,020 | $20,000 | $15,000 |
| 35 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 9 | $91.00 | $120.00 | $200.00 |
| 36 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 28 | $122.00 | $80.00 | $160.00 |
| 37 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 3 | $165.00 | $500.00 | $400.00 |
| 38 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $225.00 | $70.00 |
| 39 | Topsoil (659E00300) | CY | 739 | $33.00 | $25.00 | $25.00 |
| 40 | Seeding and mulching (659E10000) | SY | 6,655 | $1.00 | $1.50 | $2.00 |
| 41 | Repair seeding and mulching (659E14000) | SY | 333 | $1.00 | $1.00 | $0.05 |
| 42 | Inter-seeding (659E15000) | SY | 333 | $1.00 | $0.60 | $0.05 |
| 43 | Commercial fertilizer (659E20000) | TON | 1.50 | $1,250.00 | $660.00 | $1,500.00 |
| 44 | Lime (659E31000) | ACRE | 1.38 | $150.00 | $0.30 | $300.00 |
| 45 | Water (659E35000) | MGAL | 37 | $1.00 | $1.00 | $1.00 |
| 46 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,500.00 | $3,500.00 | $4,000.00 |
| 47 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,700.00 | $13,000 | $13,000 |
| 48 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,000 | $13,000 | $12,000 |
| 49 | Erosion control (832E30000) | EACH | 68,000 | $1.00 | $1.00 | $1.00 |
| 50 | Concrete masonry (602E20000) | CY | 2 | $2,377.00 | $2,300.00 | $1,600.00 |
| 51 | 4" base pipe underdrains (605E06000) | FT | 6,988 | $12.00 | $15.00 | $10.00 |
| 52 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 397 | $20.00 | $20.00 | $27.50 |
| 53 | 8" conduit, type C (611E02000) | FT | 5 | $178.00 | $500.00 | $300.00 |
| 54 | 12" conduit, type B (611E04400) | FT | 668 | $101.00 | $75.00 | $102.50 |
| 55 | 15" conduit, type B (611E05900) | FT | 207 | $102.00 | $110.00 | $113.00 |
| 56 | 15" conduit, type C (611E06100) | FT | 102 | $103.00 | $80.00 | $85.00 |
| 57 | 18" conduit, type B (611E07400) | FT | 95 | $160.00 | $85.00 | $215.00 |
| 58 | Catch basin, no. 3 (611E98150) | EACH | 12 | $5,985.00 | $5,100.00 | $6,650.00 |
| 59 | Catch basin, no. 3A (611E98180) | EACH | 2 | $6,767.00 | $4,900.00 | $4,250.00 |
| 60 | Manhole, no. 3 (611E99574) | EACH | 3 | $5,665.00 | $3,700.00 | $7,000.00 |
| 61 | Manhole adjusted to grade (611E99654) | EACH | 1 | $808.00 | $1,700.00 | $600.00 |
| 62 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $317.00 | $450.00 | $400.00 |
| 63 | Pavement planing, asphalt concrete, 4" (254E01000) | SY | 12,788 | $4.35 | $3.00 | $4.35 |
| 64 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 2,134 | $204.25 | $220.00 | $222.00 |
| 65 | Aggregate base (304E20000) | CY | 2,058 | $96.00 | $90.00 | $100.00 |
| 66 | Tack coat (407E10000) | GAL | 2,726 | $2.50 | $3.00 | $2.50 |
| 67 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,030 | $266.00 | $280.00 | $280.00 |
| 68 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 1,713 | $226.25 | $235.00 | $226.25 |
| 69 | 10" non-reinforced concrete pavement, class QC 1P (452E14010) | SY | 102 | $170.00 | $180.00 | $200.00 |
| 70 | Curb, type 6 (609E26000) | FT | 914 | $26.00 | $51.00 | $26.50 |
| 71 | Curb, type 7 (609E28000) | FT | 2,800 | $29.00 | $60.00 | $27.85 |
| 72 | 4" concrete traffic island (609E50000) | SY | 1,268 | $74.00 | $65.00 | $50.00 |
| 73 | 4" water main ductile iron pipe ansi class 52, push-on joints and fittings (638E00100) | FT | 235 | $139.00 | $200.00 | $180.00 |
| 74 | 8" steel pipe encasement, open cut (638E06300) | FT | 42 | $232.00 | $200.00 | $110.00 |
| 75 | 4" gate valve and valve box (638E07700) | EACH | 4 | $3,553.00 | $1,600.00 | $2,750.00 |
| 76 | 4" cutting-in sleeve (638E08702) | EACH | 2 | $1,089.00 | $4,500.00 | $1,500.00 |
| 77 | Fire hydrant removed and reset (638E10500) | EACH | 3 | $5,034.00 | $4,500.00 | $7,000.00 |
| 78 | Valve box adjusted to grade (638E10800) | EACH | 1 | $808.00 | $250.00 | $400.00 |
| 79 | Connection, fused pull apart (625E00450) | EACH | 64 | $169.00 | $200.00 | $180.00 |
| 80 | Connection, unfused permanent (625E00480) | EACH | 21 | $160.00 | $190.00 | $170.00 |
| 81 | Light pole, conventional AT18B40 (625E10490) | EACH | 15 | $4,881.00 | $5,000.00 | $5,500.00 |
| 82 | Light tower, misc.: light tower B45 (625E13500) | EACH | 15 | $24,545 | $25,000 | $25,750 |
| 83 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 15 | $1,845.00 | $2,000.00 | $1,900.00 |
| 84 | Light tower foundation, misc.: 36" X 10' deep (625E15700) | EACH | 15 | $6,012.00 | $6,500.00 | $6,300.00 |
| 85 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 3,648 | $4.74 | $5.00 | $5.00 |
| 86 | No. 10 AWG pole and bracket cable (625E23400) | FT | 5,085 | $1.58 | $2.00 | $1.65 |
| 87 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 5,140 | $13.95 | $15.00 | $15.00 |
| 88 | Conduit, 2", 725.04 (625E25400) | FT | 1,106 | $28.27 | $30.00 | $32.00 |
| 89 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 15 | $501.00 | $515.00 | $525.00 |
| 90 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 15 | $1,890.00 | $2,000.00 | $2,000.00 |
| 91 | Trench, 24" deep (625E29002) | FT | 4,898 | $7.70 | $8.00 | $8.00 |
| 92 | Trench in paved area (625E29400) | FT | 962 | $10.98 | $15.00 | $12.00 |
| 93 | Pull box, 725.08, 18" (625E30700) | EACH | 11 | $1,366.00 | $1,600.00 | $1,440.00 |
| 94 | Pull box removed (625E31510) | EACH | 8 | $232.00 | $280.00 | $245.00 |
| 95 | Ground rod (625E32000) | EACH | 30 | $411.00 | $490.00 | $425.00 |
| 96 | Power service, as per plan (625E34001) | EACH | 2 | $13,620 | $16,000 | $14,300 |
| 97 | Underground warning marking tape (625E36010) | FT | 6,175 | $0.11 | $0.10 | $0.12 |
| 98 | Light pole removed (625E75400) | EACH | 19 | $220.00 | $260.00 | $230.00 |
| 99 | Light pole foundation removed (625E75500) | EACH | 19 | $256.00 | $310.00 | $265.00 |
| 100 | Luminaire removed (625E75506) | EACH | 19 | $110.00 | $130.00 | $115.00 |
| 101 | Arc flash calculations and label, power service (625E76000) | EACH | 2 | $3,655.00 | $4,400.00 | $3,750.00 |
| 102 | Ground mounted support, no. 3 post (630E03100) | FT | 541.50 | $19.06 | $15.00 | $16.00 |
| 103 | Sign post reflector (630E08600) | EACH | 2 | $59.23 | $65.00 | $60.00 |
| 104 | Removal of ground mounted sign and storage (630E85000) | EACH | 14 | $17.02 | $40.00 | $35.00 |
| 105 | Removal of ground mounted sign and reerection (630E85100) | EACH | 23 | $63.51 | $230.00 | $210.00 |
| 106 | Removal of ground mounted post support and disposal (630E86002) | EACH | 41 | $22.70 | $40.00 | $35.00 |
| 107 | Edge line, 6" (644E00104) | MI | 0.28 | $6,240.00 | $9,500.00 | $8,500.00 |
| 108 | Channelizing line, 8" (644E00400) | FT | 40 | $2.00 | $3.50 | $3.00 |
| 109 | Transverse/diagonal line, as per plan (644E00701) | FT | 1,725 | $1.85 | $2.50 | $2.20 |
| 110 | Chevron marking (644E00720) | FT | 16 | $5.75 | $10.00 | $10.00 |
| 111 | Parking lot stall marking (644E01200) | FT | 7,526 | $1.85 | $2.50 | $2.25 |
| 112 | Handicap symbol marking (644E01600) | EACH | 6 | $250.00 | $150.00 | $130.00 |
| 113 | Water (616E10000) | MGAL | 30 | $1.00 | $1.00 | $1.00 |
| 114 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $26,000 | $30,000 | $125,000 |
| 115 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $15,000 | $75,000 |
| 116 | Construction layout stakes and surveying (623E10000) | LS | 1 | $73,000 | $50,000 | $35,000 |
| 117 | Mobilization (624E10000) | LS | 1 | $140,000 | $175,000 | $100,000 |
| 200 | Special - bollard (690E50600) | EACH | 26 | $1,402.00 | $850.00 | $875.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 15, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.