ODOT contract 260268 bid tabulation
JAC-US 35-18.16 (Safety) (PART 1 AND PART 2) (INTERSECTION). Let by Ohio DOT on May 21, 2026, JAC. 4 bids received; low bid $2,276,498 by Shelly & Sands Inc, -2.9% against the engineer's estimate of $2,344,000.
- Owner
- Ohio DOT
- Letting
- 21 MAY 2026
- Pay items
- 161
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $2,276,498 | Low | -3.0% |
| 2 | Axis Civil Construction LLC | $2,481,157 | +9.0% | +6.0% |
| 3 | Complete General Construction Company | $2,762,348 | +21% | +18% |
| 4 | D G M Inc | $2,780,530 | +22% | +19% |
Engineer's estimate: $2,344,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Axis Civil Construction LLC | 3. Complete General Construction Company | 4. D G M Inc |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $14,000 | $5,000.00 | $4,000.00 | $45,000 |
| 2 | Pavement removed (202E23000) | SY | 4,632 | $17.00 | $19.00 | $32.00 | $20.00 |
| 3 | Pipe removed, 24" and under (202E35100) | FT | 153 | $29.00 | $35.00 | $26.00 | $20.00 |
| 4 | Guardrail removed (202E38000) | FT | 323 | $3.50 | $6.50 | $2.50 | $1.00 |
| 5 | Catch basin removed (202E58100) | EACH | 4 | $1,200.00 | $1,200.00 | $810.00 | $300.00 |
| 6 | Excavation (203E10000) | CY | 2,330 | $39.00 | $36.00 | $60.00 | $35.00 |
| 7 | Embankment (203E20000) | CY | 411 | $18.00 | $36.00 | $15.00 | $35.00 |
| 8 | Granular material, type B (203E35110) | CY | 100 | $97.00 | $125.00 | $135.00 | $110.00 |
| 9 | Excavation of subgrade (204E13000) | CY | 100 | $47.00 | $33.00 | $95.00 | $25.00 |
| 10 | Proof rolling (204E45000) | HR | 4 | $300.00 | $250.00 | $250.00 | $100.00 |
| 11 | Geotextile fabric (204E50000) | SY | 1,000 | $0.60 | $2.12 | $6.00 | $2.00 |
| 12 | Guardrail, type MGS with long posts (606E15100) | FT | 300 | $38.00 | $38.00 | $29.80 | $40.00 |
| 13 | Anchor assembly, type T (606E26500) | EACH | 1 | $1,400.00 | $1,400.00 | $1,620.00 | $1,500.00 |
| 14 | 4" concrete median (609E70000) | SY | 274 | $83.00 | $115.00 | $125.00 | $100.00 |
| 15 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $600.00 | $150.00 | $75.00 |
| 16 | Topsoil (659E00300) | CY | 127 | $55.00 | $65.00 | $75.00 | $25.00 |
| 17 | Seeding and mulching (659E10000) | SY | 4,570 | $0.86 | $0.86 | $3.00 | $2.50 |
| 18 | Repair seeding and mulching (659E14000) | SY | 229 | $0.86 | $0.86 | $1.80 | $0.05 |
| 19 | Inter-seeding (659E15000) | SY | 229 | $0.86 | $0.86 | $0.10 | $0.05 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.82 | $1,250.00 | $1,250.00 | $750.00 | $1,500.00 |
| 21 | Lime (659E31000) | ACRE | 0.94 | $150.00 | $150.00 | $50.00 | $300.00 |
| 22 | Water (659E35000) | MGAL | 25 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Slope erosion protection (670E00500) | SY | 95 | $2.00 | $2.00 | $3.20 | $3.00 |
| 24 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $2,500.00 | $2,500.00 | $3,000.00 |
| 25 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $14,700 | $14,700 | $14,700 | $16,000 |
| 26 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $14,500 | $15,000 | $14,412 | $15,000 |
| 27 | Erosion control (832E30000) | EACH | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 28 | 6" shallow pipe underdrains (605E11100) | FT | 2,580 | $21.00 | $23.00 | $25.00 | $22.00 |
| 29 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 130 | $29.00 | $23.00 | $35.00 | $30.00 |
| 30 | 12" conduit, type C (611E04600) | FT | 199 | $102.00 | $65.00 | $140.00 | $210.00 |
| 31 | 15" conduit, type B (611E05900) | FT | 24 | $219.00 | $125.00 | $200.00 | $300.00 |
| 32 | 15" conduit, type C (611E06100) | FT | 135 | $115.00 | $125.00 | $135.00 | $250.00 |
| 33 | Catch basin, no. 2-3 (611E98510) | EACH | 5 | $4,100.00 | $3,250.00 | $4,500.00 | $3,000.00 |
| 34 | Manhole, no. 3 (611E99574) | EACH | 2 | $4,600.00 | $3,750.00 | $4,800.00 | $4,000.00 |
| 35 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $587.00 | $1,100.00 | $2,200.00 | $300.00 |
| 36 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 88 | $5.00 | $6.00 | $8.80 | $15.00 |
| 37 | Subgrade compaction (204E10000) | SY | 6,307 | $4.00 | $2.00 | $5.00 | $5.00 |
| 38 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 12,229 | $3.75 | $3.95 | $3.95 | $3.75 |
| 39 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 1,489 | $185.00 | $250.00 | $231.00 | $195.00 |
| 40 | Aggregate base (304E20000) | CY | 1,052 | $100.00 | $110.00 | $135.00 | $150.00 |
| 41 | Non-tracking tack coat (407E20000) | GAL | 2,927 | $3.50 | $4.30 | $4.30 | $3.50 |
| 42 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 735 | $265.00 | $272.75 | $272.75 | $275.00 |
| 43 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 526 | $255.00 | $266.00 | $266.00 | $265.00 |
| 44 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 2,550 | $1.75 | $4.00 | $2.75 | $3.50 |
| 45 | Connection, fused pull apart (625E00450) | EACH | 24 | $160.00 | $160.00 | $160.00 | $185.00 |
| 46 | Light pole, conventional, AT15B40 (625E10490) | EACH | 12 | $3,250.00 | $3,250.00 | $3,250.00 | $5,500.00 |
| 47 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 12 | $2,500.00 | $2,500.00 | $2,500.00 | $2,200.00 |
| 48 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 8,271 | $4.00 | $4.00 | $4.00 | $5.75 |
| 49 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,560 | $2.00 | $2.00 | $2.00 | $2.00 |
| 50 | Conduit, 2", 725.051 (625E25408) | FT | 2,032 | $9.00 | $9.00 | $9.00 | $6.50 |
| 51 | Conduit, 3", 725.051 (625E25504) | FT | 487 | $14.00 | $14.00 | $14.00 | $24.00 |
| 52 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 12 | $450.00 | $450.00 | $450.00 | $650.00 |
| 53 | Trench (625E29000) | FT | 2,032 | $6.00 | $6.00 | $6.00 | $7.50 |
| 54 | Trench in paved area (625E29400) | FT | 487 | $20.00 | $20.00 | $20.00 | $40.00 |
| 55 | Pull box, 725.08, 18" (625E30700) | EACH | 5 | $1,350.00 | $1,350.00 | $1,350.00 | $1,600.00 |
| 56 | Ground rod (625E32000) | EACH | 12 | $250.00 | $250.00 | $250.00 | $400.00 |
| 57 | Power service, as per plan (625E34001) | EACH | 1 | $10,000 | $10,000 | $10,000 | $15,000 |
| 58 | Underground warning marking tape (625E36010) | FT | 2,519 | $1.75 | $1.75 | $1.75 | $0.09 |
| 59 | Service cable, 2 conductor, no. 4 AWG (632E69600) | FT | 51 | $9.00 | $9.00 | $9.00 | $20.00 |
| 60 | Delineator, post surface mounted, as per plan (620E60001) | EACH | 33 | $75.00 | $75.00 | $135.00 | $80.00 |
| 61 | Delineator, post surface mounted, as per plan (620E60001) | EACH | 32 | $75.00 | $75.00 | $135.00 | $80.00 |
| 62 | Delineator, misc.:plastic curb and delineators (620E70010) | FT | 62 | $85.00 | $85.00 | $165.00 | $95.00 |
| 63 | RPM (621E00100) | EACH | 147 | $60.00 | $60.00 | $60.00 | $90.00 |
| 64 | Ground mounted support, no. 3 post (630E03100) | FT | 415 | $15.50 | $15.50 | $17.00 | $16.00 |
| 65 | Sign post reflector (630E08600) | EACH | 16 | $55.00 | $55.00 | $45.00 | $60.00 |
| 66 | Sign, flat sheet (630E80100) | SF | 192 | $16.00 | $16.00 | $20.00 | $20.00 |
| 67 | Removal of ground mounted sign and disposal (630E84900) | EACH | 29 | $15.00 | $15.00 | $10.00 | $15.00 |
| 68 | Removal of ground mounted post support and disposal (630E86002) | EACH | 28 | $20.00 | $20.00 | $15.00 | $20.00 |
| 69 | Edge line, 6" (644E00104) | MI | 1.42 | $7,000.00 | $7,000.00 | $7,000.00 | $5,000.00 |
| 70 | Lane line, 6" (644E00204) | MI | 0.57 | $2,650.00 | $2,650.00 | $2,650.00 | $2,250.00 |
| 71 | Center line (644E00300) | MI | 0.14 | $9,650.00 | $9,650.00 | $9,650.00 | $10,000 |
| 72 | Channelizing line, 12" (644E00404) | FT | 3,340 | $3.10 | $3.10 | $3.10 | $2.00 |
| 73 | Stop line (644E00500) | FT | 37 | $8.80 | $8.80 | $8.80 | $9.00 |
| 74 | Transverse/diagonal line (644E00700) | FT | 309 | $8.80 | $8.80 | $8.80 | $9.00 |
| 75 | Chevron marking (644E00720) | FT | 257 | $8.80 | $8.80 | $8.80 | $9.00 |
| 76 | Lane arrow (644E01300) | EACH | 20 | $100.00 | $100.00 | $100.00 | $125.00 |
| 77 | Lane reduction arrow (644E01350) | EACH | 2 | $280.00 | $280.00 | $280.00 | $300.00 |
| 78 | Dotted line, 6" (644E01510) | FT | 873 | $2.50 | $2.50 | $2.50 | $2.00 |
| 79 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 60 | $285.00 | $260.00 | $330.00 | $185.00 |
| 80 | Aggregate base (304E20000) | CY | 60 | $209.00 | $120.00 | $135.00 | $80.00 |
| 81 | Tack coat (407E10000) | GAL | 60 | $3.50 | $4.00 | $4.30 | $3.50 |
| 82 | Prime coat (408E10000) | GAL | 60 | $5.50 | $10.00 | $20.00 | $5.50 |
| 83 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 30 | $320.00 | $320.00 | $495.00 | $220.00 |
| 84 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $120.00 | $75.00 | $85.00 | $100.00 |
| 85 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 4 | $2,200.00 | $2,550.00 | $3,450.00 | $2,500.00 |
| 87 | Work zone marking sign (614E12460) | EACH | 2 | $75.00 | $75.00 | $75.00 | $135.00 |
| 89 | Asphalt concrete for maintaining traffic (614E13000) | CY | 35 | $300.00 | $280.00 | $365.00 | $200.00 |
| 90 | Barrier reflector, type 1, 1-way (614E13310) | EACH | 129 | $13.00 | $16.00 | $29.00 | $12.00 |
| 91 | Object marker, one way (614E13350) | EACH | 129 | $16.00 | $25.00 | $57.41 | $20.00 |
| 92 | Work zone lane line, class I, 6", 642 paint (614E20110) | MI | 0.42 | $3,695.00 | $3,695.00 | $3,695.00 | $4,000.00 |
| 93 | Work zone center line, class I, 642 paint (614E21100) | MI | 1.02 | $2,195.00 | $2,195.00 | $2,195.00 | $2,000.00 |
| 94 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 3.05 | $1,750.00 | $1,750.00 | $1,750.00 | $2,000.00 |
| 95 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 3,041 | $0.75 | $0.75 | $0.75 | $0.85 |
| 96 | Work zone transverse/diagonal line, class I, 642 paint (614E25200) | FT | 31 | $14.00 | $14.00 | $14.00 | $15.00 |
| 97 | Work zone stop line, class I, 642 paint (614E26200) | FT | 23 | $14.00 | $14.00 | $14.00 | $20.00 |
| 98 | Water (616E10000) | MGAL | 85 | $50.00 | $1.00 | $250.00 | $1.00 |
| 99 | Compacted aggregate (617E10100) | CY | 120 | $145.00 | $105.00 | $85.00 | $90.00 |
| 100 | Portable barrier, unanchored (622E41100) | FT | 6,440 | $30.00 | $33.00 | $30.00 | $35.00 |
| 101 | Center line, type 1 (642E00300) | MI | 1 | $2,470.00 | $2,470.00 | $2,470.00 | $3,000.00 |
| 102 | Removal of pavement marking (642E30000) | FT | 2,880 | $1.00 | $0.90 | $0.90 | $1.25 |
| 103 | Lane line, 6" (644E00204) | MI | 0.65 | $2,650.00 | $2,650.00 | $2,650.00 | $2,750.00 |
| 104 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 6 | $1,000.00 | $1,900.00 | $1,000.00 | $1,000.00 |
| 105 | Clearing and grubbing (201E11000) | LS | 1 | $5,000.00 | $3,000.00 | $3,500.00 | $11,000 |
| 106 | Pavement removed (202E23000) | SY | 357 | $20.00 | $18.50 | $48.00 | $12.00 |
| 107 | Excavation (203E10000) | CY | 107 | $13.00 | $60.00 | $125.00 | $50.00 |
| 108 | Embankment (203E20000) | CY | 127 | $16.00 | $40.00 | $18.00 | $50.00 |
| 109 | Subgrade compaction (204E10000) | SY | 686 | $8.00 | $3.00 | $5.00 | $6.00 |
| 110 | Proof rolling (204E45000) | HR | 1 | $260.00 | $250.00 | $255.00 | $100.00 |
| 111 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 2 | $265.00 | $450.00 | $685.00 | $150.00 |
| 112 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $150.00 | $150.00 | $75.00 |
| 113 | Topsoil (659E00300) | CY | 88 | $41.00 | $62.00 | $78.00 | $25.00 |
| 114 | Seeding and mulching (659E10000) | SY | 788 | $4.00 | $4.00 | $3.75 | $5.00 |
| 115 | Repair seeding and mulching (659E14000) | SY | 40 | $4.00 | $4.00 | $2.20 | $0.05 |
| 116 | Inter-seeding (659E15000) | SY | 40 | $4.00 | $4.00 | $0.10 | $0.05 |
| 117 | Commercial fertilizer (659E20000) | TON | 0.11 | $1,250.00 | $1,250.00 | $950.00 | $1,500.00 |
| 118 | Lime (659E31000) | ACRE | 0.16 | $150.00 | $150.00 | $50.00 | $300.00 |
| 119 | Water (659E35000) | MGAL | 5 | $1.00 | $1.00 | $1.00 | $1.00 |
| 120 | Erosion control (832E30000) | EACH | 4,570 | $1.00 | $1.00 | $1.00 | $1.00 |
| 121 | 6" unclassified pipe underdrains (605E13300) | FT | 50 | $23.17 | $32.00 | $34.00 | $15.00 |
| 122 | 6" base pipe underdrains (605E14000) | FT | 355 | $22.00 | $24.00 | $28.00 | $30.00 |
| 123 | 6" conduit, type F (611E01500) | FT | 50 | $25.00 | $35.00 | $42.00 | $15.00 |
| 124 | Precast reinforced concrete outlet (611E99710) | EACH | 1 | $590.00 | $990.00 | $1,500.00 | $150.00 |
| 125 | Partial depth pavement repair (442), as per plan (251E01021) | SY | 390 | $70.00 | $65.00 | $141.92 | $75.00 |
| 126 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 162 | $255.00 | $300.00 | $239.00 | $265.00 |
| 127 | Aggregate base (304E20000) | CY | 112 | $115.00 | $135.00 | $135.00 | $180.00 |
| 128 | Non-tracking tack coat (407E20000) | GAL | 71 | $3.50 | $7.00 | $4.10 | $3.50 |
| 129 | Asphalt concrete surface course, 12.5 MM, type A (449) (442E22100) | CY | 35 | $375.00 | $445.00 | $330.00 | $385.00 |
| 130 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 53 | $275.00 | $355.00 | $298.00 | $285.00 |
| 131 | Rumble strips, shoulder (asphalt concrete) (618E40100) | FT | 1,406 | $2.75 | $4.90 | $2.75 | $3.50 |
| 132 | RPM (621E00100) | EACH | 20 | $75.23 | $75.00 | $75.00 | $100.00 |
| 133 | Raised pavement marker removed (621E54000) | EACH | 20 | $15.00 | $32.00 | $37.05 | $1.00 |
| 134 | Ground mounted support, no. 3 post (630E03100) | FT | 28 | $15.50 | $15.50 | $25.00 | $17.50 |
| 135 | Sign post reflector (630E08600) | EACH | 1 | $55.00 | $55.00 | $45.00 | $65.00 |
| 136 | Removal of ground mounted sign and reerection (630E85100) | EACH | 2 | $250.00 | $15.00 | $70.00 | $20.00 |
| 137 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $20.00 | $20.00 | $15.00 | $25.00 |
| 138 | Edge line, 6" (644E00104) | MI | 0.36 | $11,500 | $11,500 | $11,500 | $7,500.00 |
| 139 | Lane line, 6" (644E00204) | MI | 0.30 | $3,350.00 | $3,350.00 | $3,350.00 | $3,000.00 |
| 140 | Channelizing line, 12" (644E00404) | FT | 295 | $4.00 | $4.00 | $4.00 | $3.50 |
| 141 | Lane arrow (644E01300) | EACH | 4 | $125.00 | $125.00 | $125.00 | $150.00 |
| 142 | Dotted line, 6" (644E01510) | FT | 308 | $3.00 | $3.00 | $3.00 | $2.00 |
| 143 | Dotted line, 8" (644E01514) | FT | 229 | $3.00 | $3.00 | $3.00 | $2.00 |
| 144 | Removal of pavement marking (644E30000) | FT | 3,360 | $0.60 | $0.60 | $0.60 | $0.75 |
| 145 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $108.00 | $75.00 | $85.00 | $100.00 |
| 146 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $2,200.00 | $2,600.00 | $3,450.00 | $2,500.00 |
| 147 | Barrier reflector, type 1 (unidirectional) (614E13310) | EACH | 10 | $16.00 | $35.00 | $29.00 | $12.00 |
| 148 | Object marker, one way (614E13350) | EACH | 10 | $20.00 | $45.00 | $65.36 | $20.00 |
| 149 | Work zone edge line, class I, 6", 642 paint (614E22110) | MI | 0.53 | $2,553.00 | $2,600.00 | $2,552.96 | $3,000.00 |
| 150 | Work zone channelizing line, class I, 12", 642 paint (614E23210) | FT | 1,562 | $0.90 | $0.90 | $0.89 | $1.00 |
| 151 | Work zone dotted line, class I, 6", 642 paint (614E24202) | FT | 358 | $1.55 | $1.60 | $1.55 | $1.75 |
| 152 | Pavement for maintaining traffic, class B (615E25000) | SY | 156 | $70.00 | $120.00 | $169.66 | $125.00 |
| 153 | Water (616E10000) | MGAL | 1 | $120.00 | $1.00 | $800.00 | $1.00 |
| 154 | Portable barrier, unanchored (622E41100) | FT | 460 | $42.00 | $29.00 | $32.00 | $50.00 |
| 155 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $5,000.00 | $12,500 | $17,000 | $100,000 |
| 156 | Maintaining traffic (614E11000) | LS | 1 | $31,300 | $65,000 | $58,000 | $200,000 |
| 157 | Field office, type A (619E16000) | MNTH | 15 | $3,300.00 | $2,320.00 | $1,800.00 | $750.00 |
| 158 | Construction layout stakes and surveying (623E10000) | LS | 1 | $30,000 | $56,000 | $34,000 | $20,000 |
| 159 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $5,500.00 | $1,600.00 | $1,200.00 | $1,000.00 |
| 160 | Post construction survey monument verification and report (623E51000) | LS | 1 | $5,500.00 | $1,600.00 | $1,200.00 | $1,000.00 |
| 161 | Mobilization (624E10000) | LS | 1 | $70,000 | $75,000 | $145,000 | $100,000 |
| 162 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $20,000 | $18,500 | $3,738.00 | $15,000 |
| 200 | Detour signing (614E12420) | LS | 1 | $12,550 | $12,215 | $30,000 | $13,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of May 21, 2026. Compiled by Mirage Metrics.