ODOT contract 268005 bid tabulation
MED-IR 71 Rest Areas TP (PARKING AREAS). Let by Ohio DOT on April 9, 2026, MED. 3 bids received; low bid $5,035,276 by Great Lakes Construction Co, -8.1% against the engineer's estimate of $5,482,000.
- Owner
- Ohio DOT
- Letting
- 09 APR 2026
- Pay items
- 123
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Great Lakes Construction Co | $5,035,276 | Low | -8.0% |
| 2 | Kokosing Construction Company Inc | $5,434,867 | +8.0% | -1.0% |
| 3 | Karvo Companies Inc | $5,528,408 | +10% | +1.0% |
Engineer's estimate: $5,482,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Great Lakes Construction Co | 2. Kokosing Construction Company Inc | 3. Karvo Companies Inc |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $46,750 | $31,570 | $50,000 |
| 2 | Pavement removed (202E23000) | SY | 20,688 | $9.00 | $9.00 | $20.50 |
| 3 | Walk removed (202E30000) | SF | 13,676 | $1.20 | $2.25 | $1.75 |
| 4 | Curb removed (202E32000) | FT | 5,486 | $1.65 | $3.15 | $8.50 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 404 | $16.50 | $14.00 | $22.00 |
| 6 | Guardrail removed (202E38000) | FT | 1,509 | $2.00 | $2.00 | $2.00 |
| 7 | Manhole removed (202E58000) | EACH | 4 | $700.00 | $1,100.00 | $500.00 |
| 8 | Catch basin removed (202E58100) | EACH | 5 | $700.00 | $750.00 | $500.00 |
| 9 | Special - drilled water well abandoned (202E66000) | EACH | 2 | $4,795.00 | $1,750.00 | $750.00 |
| 10 | Fence removed (202E75000) | FT | 63 | $5.00 | $5.00 | $7.00 |
| 11 | Removal misc.: ground mounted signs and post suppo (202E98000) | LS | 1 | $1,300.00 | $1,500.00 | $1,575.00 |
| 12 | Removal misc.: sanitary pump station (202E98000) | LS | 1 | $13,000 | $9,500.00 | $6,500.00 |
| 13 | Removal misc.: boulder (202E98100) | EACH | 1 | $200.00 | $150.00 | $500.00 |
| 14 | Removal misc.: concrete picnic table (202E98100) | EACH | 27 | $100.00 | $150.00 | $100.00 |
| 15 | Removal misc.: drinking fountain (202E98100) | EACH | 1 | $250.00 | $350.00 | $250.00 |
| 16 | Removal misc.: flag pole (202E98100) | EACH | 2 | $500.00 | $1,000.00 | $250.00 |
| 17 | Removal misc.: grill (202E98100) | EACH | 9 | $400.00 | $125.00 | $100.00 |
| 18 | Removal misc.: newspaper boxes (202E98100) | EACH | 1 | $250.00 | $650.00 | $225.00 |
| 19 | Removal misc.: vending machine (202E98100) | EACH | 3 | $500.00 | $725.00 | $150.00 |
| 20 | Removal misc.: wood post (202E98100) | EACH | 1 | $100.00 | $32.00 | $250.00 |
| 21 | Removal misc.: concrete pad (202E98400) | SF | 4,972 | $2.00 | $2.00 | $2.50 |
| 22 | Excavation (203E10000) | CY | 13,458 | $20.30 | $21.00 | $20.00 |
| 23 | Embankment (203E20000) | CY | 6,291 | $10.50 | $2.40 | $12.00 |
| 24 | Subgrade compaction (204E10000) | SY | 102 | $5.00 | $12.50 | $3.00 |
| 25 | Proof rolling (204E45000) | HR | 17 | $400.00 | $160.00 | $250.00 |
| 26 | Cement (206E10500) | TON | 927 | $190.00 | $185.00 | $199.00 |
| 27 | Curing coat (206E11000) | SY | 35,817 | $1.20 | $1.20 | $1.10 |
| 28 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 35,817 | $3.31 | $4.80 | $2.50 |
| 29 | Guardrail, type MGS (606E15050) | FT | 837.50 | $21.60 | $21.60 | $21.60 |
| 30 | Anchor assembly, type E (606E26100) | EACH | 2 | $2,075.00 | $2,075.00 | $2,075.00 |
| 31 | Anchor assembly, type T (606E26500) | EACH | 2 | $850.00 | $850.00 | $850.00 |
| 32 | Fence, misc.: dumpster screen wall (607E98000) | FT | 100 | $192.00 | $192.00 | $192.00 |
| 33 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,300.00 | $4,000.00 | $5,000.00 |
| 34 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,300.00 | $4,000.00 | $5,000.00 |
| 35 | Special - bollard (690E50600) | EACH | 9 | $720.00 | $720.00 | $500.00 |
| 36 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 8 | $120.00 | $180.00 | $200.00 |
| 37 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 403 | $115.00 | $85.00 | $50.00 |
| 38 | Rock channel protection, type C with filter (601E32200) | CY | 2 | $515.00 | $450.00 | $800.00 |
| 39 | Soil analysis test (659E00100) | EACH | 2 | $70.00 | $135.00 | $70.00 |
| 40 | Topsoil (659E00300) | CY | 2,891 | $40.00 | $17.50 | $10.00 |
| 41 | Seeding and mulching, class 1 (659E00500) | SY | 19,299 | $1.10 | $0.79 | $1.10 |
| 42 | Repair seeding and mulching (659E14000) | SY | 922 | $1.10 | $0.80 | $1.10 |
| 43 | Inter-seeding (659E15000) | SY | 922 | $0.80 | $0.80 | $0.80 |
| 44 | Commercial fertilizer (659E20000) | TON | 2.57 | $850.00 | $939.01 | $850.00 |
| 45 | Lime (659E31000) | ACRE | 3.81 | $35.00 | $157.87 | $35.00 |
| 46 | Water (659E35000) | MGAL | 102 | $1.00 | $1.00 | $1.00 |
| 47 | Slope erosion protection (670E00500) | SY | 7,595 | $1.80 | $1.32 | $1.80 |
| 48 | Ditch erosion protection mat, type B (670E00720) | SY | 324 | $1.80 | $1.49 | $1.80 |
| 49 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,400.00 | $3,200.00 | $5,000.00 |
| 50 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $8,000.00 | $6,420.00 | $15,000 |
| 51 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 | $500.00 | $15,000 |
| 52 | Erosion control (832E30000) | EACH | 94,398 | $1.00 | $1.00 | $1.00 |
| 53 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 48 | $5.00 | $5.49 | $5.00 |
| 54 | Concrete masonry (602E20000) | CY | 0.60 | $3,400.00 | $2,500.00 | $2,000.00 |
| 55 | 4" base pipe underdrains (605E06000) | FT | 16,950 | $12.25 | $11.00 | $12.00 |
| 56 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 306 | $48.00 | $35.00 | $15.00 |
| 57 | 15" conduit, type B (611E05900) | FT | 743 | $110.00 | $125.00 | $75.00 |
| 60 | Catch basin, no. 3A (611E98180) | EACH | 11 | $5,100.00 | $4,425.00 | $5,000.00 |
| 61 | Precast reinforced concrete outlet (611E99710) | EACH | 4 | $500.00 | $550.00 | $450.00 |
| 62 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 5,619 | $160.00 | $190.00 | $180.00 |
| 63 | Aggregate base (304E20000) | CY | 6,256 | $70.00 | $75.00 | $80.00 |
| 64 | Tack coat (407E10000) | GAL | 4,030 | $2.50 | $1.50 | $2.40 |
| 65 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,399 | $225.00 | $305.00 | $285.00 |
| 66 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 2,333 | $206.00 | $263.00 | $235.00 |
| 67 | 6" non-reinforced concrete pavement, class QC 1P (452E10010) | SY | 268 | $75.00 | $60.00 | $75.00 |
| 68 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 102 | $135.00 | $110.00 | $100.00 |
| 69 | Curb, type 7 (609E28000) | FT | 4,947 | $27.00 | $25.00 | $18.00 |
| 70 | Curb, misc.: curb, type 7 snow turnout (609E98100) | EACH | 4 | $3,000.00 | $2,500.00 | $2,750.00 |
| 71 | Curb, misc.: curb, type 7 turnout (609E98100) | EACH | 28 | $1,350.00 | $850.00 | $400.00 |
| 72 | Special - fill and plug existing conduit (202E70000) | FT | 346 | $30.00 | $8.50 | $30.00 |
| 73 | Manhole adjusted to grade (611E99654) | EACH | 5 | $650.00 | $850.00 | $1,000.00 |
| 74 | 4" conduit, type E (611E00400) | FT | 240 | $6.82 | $18.00 | $6.79 |
| 75 | Connection, fused pull apart (625E00450) | EACH | 32 | $149.09 | $220.00 | $148.53 |
| 76 | Connection, unfused permanent (625E00480) | EACH | 36 | $84.61 | $175.00 | $84.29 |
| 77 | Light pole (installation only), as per plan (625E10503) | EACH | 7 | $836.83 | $1,920.00 | $833.71 |
| 78 | Light pole (installation only), as per plan (625E10503) | EACH | 9 | $1,047.91 | $3,750.00 | $1,044.00 |
| 79 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 7 | $2,036.16 | $2,650.00 | $2,028.57 |
| 80 | Light tower foundation, 36" X 15' deep (625E15000) | EACH | 9 | $4,599.37 | $5,150.00 | $4,582.22 |
| 81 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 9,585 | $4.43 | $4.50 | $4.41 |
| 82 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,302 | $1.22 | $2.20 | $1.22 |
| 83 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 1,525 | $17.30 | $25.00 | $17.24 |
| 84 | Conduit, 3", 725.051 (625E25504) | FT | 2,845 | $11.60 | $10.00 | $11.56 |
| 85 | Luminaire, conventional, solid state (LED), NVN-AF (625E26252) | EACH | 7 | $495.85 | $385.00 | $494.00 |
| 86 | Luminaire, high mast, solid state (LED), HMLED4_P3 (625E26262) | EACH | 36 | $1,378.54 | $1,200.00 | $1,373.40 |
| 87 | Trench, 24" deep (625E29002) | FT | 4,370 | $9.32 | $9.00 | $9.29 |
| 88 | Pull box, 725.08, 24" (625E30706) | EACH | 12 | $1,432.54 | $2,015.00 | $1,427.20 |
| 89 | Ground rod (625E32000) | EACH | 25 | $168.79 | $390.00 | $168.16 |
| 90 | Power service (625E34000) | EACH | 1 | $3,713.85 | $7,000.00 | $3,700.00 |
| 91 | Control center cabinet, complete (625E34450) | EACH | 1 | $8,521.78 | $6,000.00 | $8,490.00 |
| 92 | Underground warning marking tape (625E36010) | FT | 4,370 | $0.79 | $0.35 | $0.79 |
| 93 | Temporary lighting (625E39000) | LS | 1 | $31,156 | $10,000 | $31,040 |
| 94 | Light tower removed, as per plan (625E75351) | EACH | 8 | $954.56 | $1,500.00 | $951.00 |
| 95 | Light pole removed (625E75400) | EACH | 14 | $426.88 | $1,450.00 | $425.29 |
| 96 | Luminaire removed, as per plan (625E75507) | EACH | 25 | $93.71 | $130.00 | $93.36 |
| 97 | Light tower foundation removed (625E75540) | EACH | 8 | $523.95 | $2,100.00 | $522.00 |
| 98 | Arc flash calculations and label (med-122872) (625E76000) | EACH | 2 | $2,083.77 | $1,500.00 | $2,076.00 |
| 99 | Lighting, misc.: test existing circuit (625E98000) | EACH | 2 | $406.72 | $2,450.00 | $405.20 |
| 100 | Ground mounted support, no. 3 post, as per plan (630E03101) | FT | 246 | $12.25 | $15.00 | $15.00 |
| 101 | Ground mounted support, no. 4 post (630E04100) | FT | 73 | $27.25 | $17.00 | $17.00 |
| 102 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 95 | $46.00 | $70.00 | $70.00 |
| 103 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 98 | $33.00 | $56.50 | $56.50 |
| 104 | Breakaway structural beam connection (630E09000) | EACH | 8 | $765.00 | $725.00 | $725.00 |
| 105 | Sign, flat sheet (630E80100) | SF | 114 | $18.80 | $19.00 | $19.00 |
| 106 | Sign erected, extrusheet (630E81200) | SF | 456 | $25.10 | $26.00 | $26.00 |
| 107 | Ground mounted structural beam support foundation (630E84500) | EACH | 8 | $1,400.00 | $1,275.00 | $1,275.00 |
| 108 | Removal of ground mounted sign and disposal (630E84900) | EACH | 10 | $29.20 | $10.00 | $10.00 |
| 109 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 4 | $185.00 | $265.00 | $265.00 |
| 110 | Removal of ground mounted post support and disposal (630E86002) | EACH | 12 | $26.00 | $20.00 | $20.00 |
| 111 | Removal of ground mounted structural beam support (630E86102) | EACH | 4 | $350.00 | $220.00 | $220.00 |
| 112 | Edge line, 4" (644E00100) | MI | 0.97 | $4,000.00 | $4,000.00 | $4,000.00 |
| 113 | Wrong way arrow (644E01360) | EACH | 14 | $325.00 | $325.00 | $2,275.00 |
| 114 | Building demolished (NB 1 story brick) (202E56000) | LS | 1 | $24,125 | $30,624 | $50,000 |
| 115 | Building demolished (NB wood shed) (202E56000) | LS | 1 | $3,000.00 | $5,000.00 | $7,500.00 |
| 116 | Building demolished (SB 1 story brick) (202E56000) | LS | 1 | $20,750 | $30,624 | $25,000 |
| 117 | Building demolished (SB wood shed) (202E56000) | LS | 1 | $3,000.00 | $5,000.00 | $5,000.00 |
| 118 | Water (616E10000) | MGAL | 39 | $60.00 | $100.00 | $1.00 |
| 124 | Parking lot stall marking (644E01200) | FT | 9,454 | $1.15 | $1.15 | $1.15 |
| 130 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $40,000 | $20,000 | $25,000 |
| 131 | Maintaining traffic (614E11000) | LS | 1 | $86,000 | $68,554 | $25,000 |
| 132 | Field office, type C (619E16020) | MNTH | 6 | $4,200.00 | $2,800.00 | $3,000.00 |
| 133 | Construction layout stakes and surveying (623E10000) | LS | 1 | $22,500 | $55,000 | $200,000 |
| 134 | Mobilization (624E10000) | LS | 1 | $251,000 | $270,000 | $200,000 |
| 200 | Light pole foundation removed (625E75500) | EACH | 14 | $350.00 | $760.00 | $2,053.08 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 9, 2026. Compiled by Mirage Metrics.