ODOT contract 260440 bid tabulation
AUG-US 33 Rest Areas TP (PARKING AREAS). Let by Ohio DOT on October 1, 2026, AUG. 5 bids received; low bid $6,473,049 by Helms and Sons Excavating, -0.3% against the engineer's estimate of $6,492,000.
- Owner
- Ohio DOT
- Letting
- 01 OCT 2026
- Pay items
- 113
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Helms and Sons Excavating | $6,473,049 | Low | 0.0% |
| 2 | Eagle Bridge Co | $6,610,153 | +2.0% | +2.0% |
| 3 | R D Jones Excavating Inc | $6,831,811 | +6.0% | +5.0% |
| 4 | R B Jergens Contractors Inc | $7,145,700 | +10% | +10% |
| 5 | Integrity Contractors LLC | $7,623,387 | +18% | +17% |
Engineer's estimate: $6,492,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Helms and Sons Excavating | 2. Eagle Bridge Co | 3. R D Jones Excavating Inc | 4. R B Jergens Contractors Inc | 5. Integrity Contractors LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $85,000 | $25,000 | $25,850 | $29,401 | $44,723 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $350.00 | $300.00 | $500.00 | $727.72 | $2,205.42 |
| 3 | Pavement removed (202E23000) | SY | 22,357 | $11.00 | $12.00 | $6.45 | $11.18 | $10.27 |
| 4 | Curb removed (202E32000) | FT | 1,595 | $5.00 | $3.50 | $5.00 | $25.65 | $12.54 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 840 | $10.00 | $12.00 | $16.50 | $21.83 | $29.81 |
| 6 | Removal misc.: slotted drain (202E98200) | FT | 483 | $25.00 | $35.00 | $10.50 | $10.75 | $20.45 |
| 7 | Excavation (203E10000) | CY | 12,512 | $9.00 | $20.00 | $15.25 | $16.73 | $24.11 |
| 8 | Embankment (203E20000) | CY | 8,253 | $9.00 | $10.00 | $3.75 | $11.89 | $22.96 |
| 9 | Subgrade compaction (204E10000) | SY | 261 | $10.00 | $7.00 | $4.50 | $4.78 | $3.28 |
| 10 | Proof rolling (204E45000) | HR | 15 | $120.00 | $300.00 | $175.00 | $315.38 | $261.37 |
| 11 | Lime stabilized subgrade, 12 inches deep (206E10010) | SY | 41,806 | $5.25 | $6.25 | $6.28 | $5.56 | $4.96 |
| 12 | Lime (206E10300) | TON | 1,085 | $215.00 | $215.00 | $225.00 | $227.66 | $250.86 |
| 13 | Curing coat (206E11000) | SY | 41,806 | $1.25 | $1.25 | $1.35 | $1.32 | $1.46 |
| 14 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $16,500 | $20,000 | $16,500 | $17,471 | $19,252 |
| 15 | Fence, misc.: wooden slat fence (607E98000) | FT | 116 | $210.00 | $210.00 | $130.00 | $105.50 | $159.35 |
| 16 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $3,500.00 | $4,000.00 | $3,780.00 | $1,994.00 | $37,054 |
| 17 | Post construction survey monument verification and report (623E51000) | LS | 1 | $3,500.00 | $4,000.00 | $3,780.00 | $1,994.00 | $3,970.05 |
| 18 | Special - bollard (690E50600) | EACH | 10 | $1,250.00 | $1,025.00 | $950.00 | $501.14 | $596.13 |
| 19 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 547 | $95.00 | $80.00 | $69.15 | $91.25 | $104.15 |
| 20 | Topsoil (659E00300) | CY | 5,322 | $15.00 | $7.00 | $18.50 | $44.05 | $72.52 |
| 21 | Seeding and mulching (659E10000) | SY | 43,134 | $1.00 | $1.25 | $1.50 | $0.97 | $1.18 |
| 22 | Repair seeding and mulching (659E14000) | SY | 2,160 | $1.00 | $1.50 | $1.50 | $0.79 | $0.86 |
| 23 | Inter-seeding (659E15000) | SY | 2,160 | $0.60 | $0.50 | $1.50 | $0.01 | $0.86 |
| 24 | Commercial fertilizer (659E20000) | TON | 6.10 | $850.00 | $1,500.00 | $1,200.00 | $1,582.54 | $787.71 |
| 25 | Lime (659E31000) | ACRE | 9 | $35.00 | $1.00 | $925.00 | $211.01 | $10.50 |
| 26 | Water (659E35000) | MGAL | 245 | $1.00 | $8.00 | $10.00 | $1.06 | $1.05 |
| 27 | Slope erosion protection (670E00500) | SY | 4,773 | $2.00 | $2.50 | $4.00 | $2.48 | $1.94 |
| 28 | Storm water pollution prevention plan (832E15000) | LS | 1 | $1,500.00 | $4,000.00 | $3,250.00 | $3,270.59 | $3,255.86 |
| 29 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $15,000 | $15,000 | $14,980 | $10,550 | $10,503 |
| 30 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $15,000 | $15,000 | $1,500.00 | $14,770 | $14,704 |
| 31 | Erosion control (832E30000) | EACH | 50,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Concrete masonry (602E20000) | CY | 4 | $3,000.00 | $2,750.00 | $2,000.00 | $2,021.30 | $1,913.32 |
| 33 | 6" shallow pipe underdrains (605E11100) | FT | 18,856 | $14.00 | $10.50 | $20.00 | $11.53 | $11.38 |
| 34 | 6" unclassified pipe underdrains (605E13300) | FT | 124 | $14.00 | $15.00 | $21.10 | $33.29 | $16.21 |
| 35 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 1,051 | $18.00 | $25.00 | $23.45 | $27.28 | $17.38 |
| 36 | 6" conduit, type B (611E00900) | FT | 8 | $75.00 | $120.00 | $35.00 | $102.96 | $17.72 |
| 37 | 6" conduit, type C (611E01100) | FT | 500 | $14.00 | $6.00 | $21.10 | $22.76 | $15.62 |
| 38 | 12" conduit, type B (611E04400) | FT | 400 | $95.00 | $75.00 | $75.45 | $70.82 | $99.41 |
| 39 | 15" conduit, type B (611E05900) | FT | 75 | $120.00 | $85.00 | $82.65 | $95.51 | $105.79 |
| 40 | 18" conduit, type B (611E07400) | FT | 100 | $145.00 | $100.00 | $90.65 | $111.86 | $116.62 |
| 41 | 21" conduit, type B (611E08900) | FT | 200 | $150.00 | $120.00 | $109.85 | $132.02 | $120.29 |
| 42 | 19" X 30" conduit, type B, 706.04 (611E52302) | FT | 851 | $188.00 | $175.00 | $185.85 | $199.04 | $208.32 |
| 43 | 22" X 34" conduit, type A, 706.04 (611E52400) | FT | 132 | $205.00 | $220.00 | $218.65 | $177.82 | $223.99 |
| 44 | 22" X 34" conduit, type B, 706.04 (611E52402) | FT | 909 | $205.00 | $215.00 | $214.75 | $185.56 | $200.46 |
| 45 | Catch basin, no. 6, as per plan (611E98371) | EACH | 26 | $2,750.00 | $3,100.00 | $2,850.00 | $2,072.27 | $3,372.06 |
| 46 | Catch basin reconstructed to grade (611E98634) | EACH | 1 | $1,500.00 | $1,000.00 | $2,550.00 | $1,317.97 | $2,830.10 |
| 47 | Manhole, no. 3 (611E99574) | EACH | 2 | $10,000 | $10,000 | $10,250 | $13,442 | $9,176.05 |
| 48 | Precast reinforced concrete outlet (611E99710) | EACH | 5 | $350.00 | $400.00 | $650.00 | $501.32 | $958.80 |
| 49 | Drainage structure, misc.: curb cut (611E99900) | EACH | 71 | $700.00 | $375.00 | $500.00 | $723.97 | $949.23 |
| 50 | Full depth pavement sawing (255E20000) | FT | 878 | $3.00 | $3.00 | $3.15 | $4.92 | $2.31 |
| 51 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 6,293 | $208.00 | $197.00 | $213.00 | $208.74 | $207.80 |
| 52 | Aggregate base (304E20000) | CY | 6,547 | $56.00 | $48.00 | $38.00 | $65.31 | $65.36 |
| 53 | Non-tracking tack coat (407E20000) | GAL | 4,519 | $3.00 | $3.00 | $3.25 | $3.18 | $3.16 |
| 54 | Stabilized crushed aggregate (411E10000) | CY | 134 | $90.00 | $150.00 | $56.75 | $78.67 | $75.35 |
| 55 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,568 | $275.00 | $289.00 | $300.00 | $306.22 | $304.84 |
| 56 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 2,610 | $230.00 | $232.00 | $244.00 | $245.83 | $244.72 |
| 57 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 209 | $95.00 | $90.00 | $146.75 | $95.23 | $155.34 |
| 58 | Curb, type 7 (609E28000) | FT | 6,156 | $25.00 | $22.00 | $34.50 | $20.91 | $24.16 |
| 59 | 4" concrete median (609E70000) | SY | 762 | $85.00 | $50.00 | $111.75 | $10.30 | $99.93 |
| 60 | Connection, fused pull apart (625E00450) | EACH | 46 | $142.00 | $200.00 | $137.00 | $236.59 | $236.80 |
| 61 | Connection, unfused permanent (625E00480) | EACH | 39 | $135.00 | $200.00 | $137.00 | $224.46 | $224.65 |
| 62 | Light pole, conventional, AT20B40 (625E10490) | EACH | 23 | $5,225.00 | $5,000.00 | $5,380.00 | $5,665.51 | $5,670.44 |
| 63 | Light tower, misc.: light tower, BB45 (625E13500) | EACH | 10 | $24,000 | $20,000 | $25,025 | $22,926 | $22,946 |
| 64 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 23 | $1,700.00 | $2,500.00 | $2,945.00 | $2,537.34 | $2,539.55 |
| 65 | Light tower foundation, misc.: 36" X 10' deep (625E15700) | EACH | 10 | $6,200.00 | $7,700.00 | $6,515.00 | $11,410 | $11,420 |
| 66 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 3,324 | $4.25 | $5.00 | $6.30 | $5.64 | $5.65 |
| 67 | No. 10 AWG pole and bracket cable (625E23400) | FT | 4,830 | $2.00 | $2.00 | $3.15 | $2.48 | $2.48 |
| 68 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 9,773 | $14.50 | $17.00 | $16.25 | $16.51 | $16.53 |
| 69 | Conduit, 3", 725.04 (625E25500) | FT | 600 | $47.00 | $28.00 | $40.00 | $37.19 | $37.22 |
| 70 | Conduit, 3", 725.051 (625E25504) | FT | 294 | $10.00 | $7.00 | $19.00 | $10.29 | $10.30 |
| 71 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 124 | $82.00 | $65.00 | $71.50 | $131.88 | $131.99 |
| 72 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 7 | $525.00 | $425.00 | $550.00 | $570.77 | $571.27 |
| 73 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 6 | $525.00 | $425.00 | $550.00 | $570.77 | $571.27 |
| 74 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $580.00 | $470.00 | $600.00 | $630.91 | $631.46 |
| 75 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 20 | $1,400.00 | $1,250.00 | $1,500.00 | $1,358.88 | $1,360.06 |
| 76 | Trench (625E29000) | FT | 9,959 | $8.00 | $6.00 | $16.25 | $16.35 | $16.37 |
| 77 | Pull box, 725.08, 18" (625E30700) | EACH | 21 | $1,115.00 | $1,500.00 | $1,400.00 | $1,139.43 | $1,140.42 |
| 78 | Ground rod (625E32000) | EACH | 43 | $390.00 | $300.00 | $400.00 | $313.87 | $314.14 |
| 79 | Power service, as per plan (625E34001) | EACH | 2 | $13,500 | $15,500 | $17,500 | $26,376 | $26,399 |
| 80 | Underground warning marking tape (625E36010) | FT | 9,964 | $0.25 | $1.50 | $4.15 | $4.33 | $4.33 |
| 81 | Light pole removed (625E75400) | EACH | 27 | $500.00 | $500.00 | $500.00 | $290.13 | $290.39 |
| 82 | Light pole foundation removed (625E75500) | EACH | 27 | $455.00 | $500.00 | $325.00 | $611.92 | $612.45 |
| 83 | Luminaire removed (625E75506) | EACH | 27 | $110.00 | $75.00 | $85.00 | $145.59 | $145.72 |
| 84 | Arc flash calculations and label, at control cente (625E76000) | EACH | 2 | $3,675.00 | $4,000.00 | $3,700.00 | $2,954.08 | $2,956.65 |
| 85 | Ground mounted support, no. 3 post (630E03100) | FT | 690 | $17.00 | $17.00 | $19.00 | $16.88 | $16.90 |
| 86 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 35 | $45.00 | $45.00 | $49.00 | $42.20 | $42.24 |
| 87 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 44 | $75.00 | $73.00 | $76.00 | $65.41 | $65.47 |
| 88 | Sign post reflector (630E08600) | EACH | 20 | $45.00 | $45.00 | $50.00 | $48.80 | $59.12 |
| 89 | Breakaway structural beam connection (630E09000) | EACH | 4 | $790.00 | $785.00 | $800.00 | $685.77 | $830.90 |
| 90 | Sign, flat sheet (630E80100) | SF | 268 | $20.00 | $19.50 | $23.00 | $26.51 | $32.12 |
| 91 | Sign, ground mounted extrusheet (630E80200) | SF | 141 | $28.00 | $27.00 | $30.00 | $40.19 | $48.69 |
| 92 | Sign backing assembly (630E82000) | EACH | 4 | $330.00 | $330.00 | $350.00 | $290.13 | $351.53 |
| 93 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $1,500.00 | $1,475.00 | $1,600.00 | $1,846.30 | $2,237.04 |
| 94 | Removal of ground mounted sign and disposal (630E84900) | EACH | 16 | $15.00 | $15.00 | $20.00 | $26.38 | $31.96 |
| 95 | Removal of ground mounted sign and reerection (630E85100) | EACH | 4 | $75.00 | $75.00 | $80.00 | $131.88 | $159.79 |
| 96 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 2 | $250.00 | $240.00 | $265.00 | $158.25 | $191.75 |
| 97 | Removal of ground mounted post support and disposal (630E86002) | EACH | 31 | $20.00 | $20.00 | $25.00 | $31.65 | $38.35 |
| 98 | Removal of ground mounted structural beam support (630E86102) | EACH | 4 | $300.00 | $285.00 | $300.00 | $369.26 | $447.41 |
| 99 | Removal of pole mounted sign and reerection (630E87520) | EACH | 3 | $200.00 | $195.00 | $215.00 | $131.88 | $159.79 |
| 100 | Edge line, 6" (644E00104) | MI | 2 | $4,050.00 | $4,010.00 | $4,400.00 | $4,230.67 | $8,502.64 |
| 101 | Channelizing line, 12" (644E00404) | FT | 506 | $1.75 | $1.70 | $2.00 | $1.79 | $3.19 |
| 102 | Stop line (644E00500) | FT | 71 | $9.00 | $9.00 | $9.50 | $9.50 | $10.63 |
| 103 | Transverse/diagonal line (644E00700) | FT | 332 | $9.25 | $9.00 | $9.50 | $9.50 | $10.63 |
| 104 | Parking lot stall marking (644E01200) | FT | 7,846 | $2.00 | $1.85 | $2.00 | $1.95 | $2.13 |
| 105 | Lane arrow (644E01300) | EACH | 24 | $110.00 | $100.00 | $125.00 | $105.50 | $159.42 |
| 106 | Handicap symbol marking (644E01600) | EACH | 4 | $300.00 | $300.00 | $325.00 | $316.51 | $265.71 |
| 107 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $100.00 | $75.00 | $250.00 | $158.25 | $180.25 |
| 108 | Water (616E10000) | MGAL | 76 | $10.00 | $20.00 | $15.00 | $148.81 | $3.83 |
| 109 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $40,000 | $90,000 | $35,250 | $25,321 | $69,318 |
| 110 | Maintaining traffic (614E11000) | LS | 1 | $30,000 | $10,000 | $30,000 | $85,223 | $16,279 |
| 111 | Field office, type C (619E16020) | MNTH | 6 | $1,000.00 | $3,500.00 | $7,000.00 | $2,637.57 | $4,936.30 |
| 112 | Construction layout stakes and surveying (623E10000) | LS | 1 | $40,000 | $25,000 | $50,000 | $37,221 | $3,970.05 |
| 113 | Mobilization (624E10000) | LS | 1 | $90,000 | $300,000 | $55,500 | $172,065 | $150,525 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 1, 2026. Compiled by Mirage Metrics.