ODOT contract 268015 bid tabulation
PRE-IR 70 WB Truck Parking (PARKING AREAS). Let by Ohio DOT on July 30, 2026, PRE. 6 bids received; low bid $11,919,317 by R B Jergens Contractors Inc, -4.5% against the engineer's estimate of $12,479,000.
- Owner
- Ohio DOT
- Letting
- 30 JUL 2026
- Pay items
- 155
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | R B Jergens Contractors Inc | $11,919,317 | Low | -4.0% |
| 2 | Eagle Bridge Co | $12,783,481 | +7.0% | +2.0% |
| 3 | Great Lakes Construction Co | $13,841,717 | +16% | +11% |
| 4 | Brumbaugh Construction Inc | $15,300,000 | +28% | +23% |
| 5 | Complete General Construction Company | $15,619,399 | +31% | +25% |
| 6 | John R Jurgensen Company | $16,946,821 | +42% | +36% |
Engineer's estimate: $12,479,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. R B Jergens Contractors Inc | 2. Eagle Bridge Co | 3. Great Lakes Construction Co | 4. Brumbaugh Construction Inc | 5. Complete General Construction Company | 6. John R Jurgensen Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $112,327 | $100,000 | $158,000 | $350,000 | $80,000 | $83,539 |
| 2 | Headwall removed (202E20010) | EACH | 6 | $353.35 | $650.00 | $370.00 | $350.00 | $770.00 | $1,215.73 |
| 3 | Pavement removed (202E23000) | SY | 37,331 | $11.83 | $7.00 | $11.50 | $12.00 | $14.25 | $16.89 |
| 4 | Curb removed (202E32000) | FT | 4,278 | $4.32 | $3.75 | $2.00 | $10.00 | $8.00 | $6.24 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 1,856 | $31.82 | $12.00 | $18.00 | $10.00 | $35.00 | $38.91 |
| 6 | Pipe removed, over 24" diameter (202E35200) | FT | 250 | $52.23 | $20.00 | $50.00 | $60.00 | $65.00 | $82.52 |
| 7 | Manhole removed (202E58000) | EACH | 15 | $758.52 | $500.00 | $850.00 | $600.00 | $1,000.00 | $1,215.73 |
| 8 | Inlet removed (202E58200) | EACH | 4 | $685.35 | $350.00 | $850.00 | $250.00 | $1,000.00 | $1,463.32 |
| 9 | Fence removed (202E75000) | FT | 9,231 | $5.35 | $4.00 | $4.50 | $5.50 | $2.80 | $5.00 |
| 10 | Removal misc.: removal of wood pole and disposal (202E98100) | EACH | 1 | $620.52 | $250.00 | $350.00 | $700.00 | $1,320.00 | $580.00 |
| 11 | Excavation (203E10000) | CY | 67,190 | $9.91 | $12.00 | $24.30 | $12.00 | $24.00 | $20.34 |
| 12 | Embankment (203E20000) | CY | 24,032 | $6.31 | $3.00 | $7.50 | $10.00 | $4.00 | $13.98 |
| 13 | Geotextile fabric (204E50000) | SY | 1,767 | $4.72 | $2.50 | $2.00 | $3.00 | $4.00 | $3.07 |
| 14 | Cement (206E10500) | TON | 1,395 | $253.26 | $226.00 | $226.00 | $210.00 | $226.00 | $277.50 |
| 15 | Curing coat (206E11000) | SY | 53,673 | $1.40 | $1.40 | $1.25 | $1.50 | $1.39 | $1.41 |
| 16 | Cement stabilized subgrade, 12 inches deep (206E15010) | SY | 53,673 | $2.52 | $4.25 | $3.80 | $4.20 | $2.90 | $6.61 |
| 17 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $20,593 | $21,000 | $19,900 | $25,000 | $19,900 | $24,000 |
| 18 | Ditch cleanout (209E10000) | FT | 2,350 | $7.45 | $7.00 | $10.00 | $6.00 | $14.00 | $18.27 |
| 19 | Fence, type 47RA (607E15100) | FT | 6,357 | $17.65 | $15.50 | $15.50 | $17.00 | $16.50 | $16.50 |
| 20 | Fenceline seeding and mulching (607E70000) | FT | 6,357 | $1.42 | $0.50 | $2.00 | $3.00 | $1.10 | $0.80 |
| 21 | 4" concrete walk (608E10000) | SF | 9,768 | $7.20 | $6.50 | $9.25 | $11.00 | $8.00 | $10.76 |
| 22 | Curb ramp (608E52000) | SF | 1,001 | $34.96 | $14.00 | $10.00 | $28.00 | $24.00 | $28.14 |
| 23 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $116,340 | $80,000 | $90,200 | $150,000 | $125,000 | $94,306 |
| 24 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 14 | $142.45 | $100.00 | $195.00 | $240.00 | $160.00 | $438.99 |
| 25 | Dumped rock fill, type D (601E28000) | CY | 978 | $119.56 | $100.00 | $70.00 | $90.00 | $95.00 | $134.68 |
| 26 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 2 | $353.57 | $150.00 | $270.00 | $100.00 | $465.00 | $745.43 |
| 27 | Water (616E10000) | MGAL | 550 | $140.05 | $15.00 | $55.00 | $3.00 | $100.00 | $55.83 |
| 28 | Soil analysis test (659E00100) | EACH | 2 | $206.97 | $400.00 | $200.00 | $100.00 | $100.00 | $50.00 |
| 29 | Topsoil (659E00300) | CY | 5,395 | $41.96 | $5.00 | $24.00 | $30.00 | $36.00 | $40.11 |
| 30 | Seeding and mulching (659E10000) | SY | 48,596 | $0.70 | $1.25 | $0.68 | $1.00 | $0.98 | $0.61 |
| 31 | Repair seeding and mulching (659E14000) | SY | 2,431 | $0.52 | $1.00 | $0.50 | $2.00 | $0.90 | $0.61 |
| 32 | Inter-seeding (659E15000) | SY | 2,431 | $0.01 | $0.25 | $0.01 | $2.00 | $0.90 | $0.61 |
| 33 | Commercial fertilizer (659E20000) | TON | 6.78 | $1,552.25 | $1,500.00 | $1,500.00 | $900.00 | $700.00 | $700.00 |
| 34 | Lime (659E31000) | ACRE | 10.05 | $206.97 | $1.00 | $200.00 | $100.00 | $10.00 | $0.15 |
| 35 | Water (659E35000) | MGAL | 270 | $1.03 | $1.00 | $1.00 | $3.00 | $1.00 | $0.15 |
| 36 | Slope erosion protection (670E00500) | SY | 7,348 | $2.02 | $2.50 | $1.95 | $2.00 | $1.85 | $1.63 |
| 37 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,156.24 | $5,000.00 | $4,500.00 | $4,000.00 | $5,000.00 | $3,200.00 |
| 38 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $20,179 | $22,500 | $17,000 | $22,000 | $30,000 | $10,670 |
| 39 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $16,557 | $17,500 | $15,000 | $16,000 | $13,853 | $13,852 |
| 40 | Erosion control (832E30000) | EACH | 100,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 41 | Concrete masonry (602E20000) | CY | 2.80 | $2,001.03 | $2,000.00 | $3,500.00 | $1,200.00 | $4,150.00 | $2,290.85 |
| 42 | 6" base pipe underdrains with geotextile fabric (605E14020) | FT | 18,272 | $10.64 | $11.00 | $14.50 | $8.00 | $18.00 | $18.19 |
| 43 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 425 | $22.35 | $25.00 | $35.00 | $12.00 | $25.00 | $67.23 |
| 44 | 12" conduit, type B (611E04400) | FT | 764 | $71.20 | $100.00 | $105.00 | $70.00 | $170.00 | $88.25 |
| 45 | 15" conduit, type B (611E05900) | FT | 640 | $65.83 | $90.00 | $95.00 | $80.00 | $130.00 | $91.48 |
| 46 | 15" conduit, type C (611E06100) | FT | 32 | $60.45 | $85.00 | $125.00 | $100.00 | $118.00 | $133.58 |
| 47 | 18" conduit, type B (611E07400) | FT | 588 | $95.87 | $175.00 | $145.00 | $120.00 | $268.00 | $124.56 |
| 48 | 24" conduit, type B (611E10400) | FT | 495 | $140.27 | $225.00 | $220.00 | $175.00 | $419.00 | $197.72 |
| 49 | 24" conduit, type C (611E10600) | FT | 178 | $120.25 | $200.00 | $145.00 | $175.00 | $209.00 | $221.55 |
| 50 | 30" conduit, type B (611E13400) | FT | 380 | $176.01 | $250.00 | $255.00 | $160.00 | $495.00 | $247.48 |
| 51 | 36" conduit, type A (611E16200) | FT | 14 | $256.29 | $480.00 | $440.00 | $320.00 | $590.00 | $581.48 |
| 52 | 36" conduit, type B (611E16400) | FT | 58 | $227.56 | $270.00 | $325.00 | $270.00 | $420.00 | $389.02 |
| 53 | Catch basin, no. 3, as per plan (611E98151) | EACH | 2 | $9,315.45 | $10,500 | $13,500 | $14,000 | $6,700.00 | $13,148 |
| 54 | Catch basin, no. 3A (611E98180) | EACH | 2 | $4,647.62 | $3,500.00 | $7,700.00 | $9,000.00 | $4,450.00 | $6,727.07 |
| 55 | Catch basin, no. 3A, as per plan (611E98181) | EACH | 4 | $4,647.62 | $6,500.00 | $7,900.00 | $10,500 | $5,000.00 | $8,291.61 |
| 56 | Catch basin, no. 6 (611E98370) | EACH | 4 | $3,089.43 | $3,500.00 | $6,000.00 | $9,000.00 | $4,700.00 | $3,946.29 |
| 57 | Catch basin, no. 2-3 (611E98510) | EACH | 2 | $2,621.39 | $3,000.00 | $3,500.00 | $6,000.00 | $2,900.00 | $2,911.01 |
| 58 | Catch basin, no. 2-4 (611E98540) | EACH | 3 | $4,454.39 | $5,500.00 | $7,200.00 | $8,000.00 | $3,600.00 | $5,569.58 |
| 59 | Manhole, no. 3 (611E99574) | EACH | 1 | $5,625.79 | $6,000.00 | $5,200.00 | $11,000 | $7,000.00 | $4,036.23 |
| 60 | Precast reinforced concrete outlet (611E99710) | EACH | 7 | $825.41 | $450.00 | $500.00 | $800.00 | $450.00 | $772.35 |
| 61 | Pavement planing, asphalt concrete, T = 1.5" min. (254E01000) | SY | 2,852 | $2.49 | $2.35 | $2.35 | $5.00 | $2.35 | $7.50 |
| 62 | Full depth pavement sawing, as per plan (255E20001) | FT | 500 | $6.21 | $3.00 | $3.00 | $3.00 | $4.00 | $3.65 |
| 63 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 351 | $251.69 | $238.00 | $238.00 | $245.00 | $238.00 | $290.00 |
| 64 | Aggregate base (304E20000) | CY | 9,057 | $58.78 | $68.00 | $63.50 | $75.00 | $72.00 | $78.52 |
| 65 | Tack coat (407E10000) | GAL | 920 | $1.06 | $1.00 | $1.00 | $1.00 | $1.00 | $5.00 |
| 66 | Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000) | CY | 88 | $338.41 | $320.00 | $320.00 | $330.00 | $320.00 | $425.00 |
| 67 | Asphalt concrete intermediate course, type 2, (446) (441E10200) | CY | 123 | $290.82 | $275.00 | $275.00 | $280.00 | $275.00 | $355.00 |
| 68 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 407 | $322.55 | $305.00 | $305.00 | $315.00 | $305.00 | $405.00 |
| 69 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 529 | $301.40 | $285.00 | $285.00 | $290.00 | $285.00 | $325.00 |
| 70 | Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400) | CY | 105 | $311.97 | $295.00 | $295.00 | $300.00 | $295.00 | $460.00 |
| 71 | 10" non-reinforced concrete pavement, class QC 1P with QC/QA, as per plan (452E14021) | SY | 45,688 | $94.04 | $114.50 | $110.25 | $150.00 | $125.00 | $150.09 |
| 72 | Curb, type 6 (609E26000) | FT | 2,785 | $16.31 | $30.00 | $23.00 | $30.00 | $25.00 | $31.28 |
| 73 | Curb, type 7 (609E28000) | FT | 5,842 | $23.03 | $30.00 | $23.00 | $32.00 | $28.00 | $32.79 |
| 74 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 0.35 | $19,144 | $25,000 | $18,150 | $46,000 | $24,000 | $18,150 |
| 75 | Connection, fused pull apart (625E00450) | EACH | 52 | $210.39 | $97.92 | $97.92 | $200.00 | $155.00 | $202.50 |
| 76 | Connection, unfused pull apart (625E00460) | EACH | 26 | $198.96 | $93.87 | $93.87 | $195.00 | $150.00 | $191.50 |
| 77 | Connection, unfused permanent (625E00480) | EACH | 24 | $187.53 | $37.81 | $37.81 | $185.00 | $130.00 | $180.50 |
| 78 | Light pole, conventional, (AT12B40) (625E10490) | EACH | 4 | $3,642.59 | $3,368.89 | $3,368.89 | $3,600.00 | $2,850.00 | $3,506.00 |
| 79 | Light pole, conventional, (AT8B40) (625E10490) | EACH | 22 | $3,605.18 | $3,309.04 | $3,309.04 | $3,600.00 | $2,750.00 | $3,470.00 |
| 80 | Light tower, misc.:BBBB45 (625E13500) | EACH | 10 | $21,475 | $25,136 | $25,136 | $21,000 | $21,500 | $20,670 |
| 81 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 26 | $2,244.15 | $2,750.00 | $2,750.00 | $2,200.00 | $2,800.00 | $2,160.00 |
| 82 | Light tower foundation, 36" X 15' deep (625E15000) | EACH | 12 | $10,266 | $6,500.00 | $6,500.00 | $10,000 | $18,000 | $9,881.00 |
| 83 | No. 10 AWG pole and bracket cable (625E23400) | FT | 3,016 | $2.18 | $0.71 | $0.71 | $2.15 | $2.40 | $2.10 |
| 84 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 9,553 | $15.79 | $14.28 | $14.28 | $15.50 | $17.00 | $15.20 |
| 85 | Conduit, 3", 725.04 (625E25500) | FT | 287 | $35.64 | $28.09 | $28.09 | $35.00 | $40.00 | $34.30 |
| 86 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 26 | $524.67 | $463.54 | $463.54 | $515.00 | $640.00 | $505.00 |
| 87 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 52 | $1,278.96 | $1,132.75 | $1,132.75 | $1,260.00 | $1,025.00 | $1,231.00 |
| 88 | Trench, 24" deep (625E29002) | FT | 8,815 | $11.69 | $16.50 | $16.50 | $11.50 | $8.50 | $11.25 |
| 89 | Pull box, 725.08, 18" (625E30700) | EACH | 17 | $988.05 | $734.99 | $734.99 | $970.00 | $1,350.00 | $951.00 |
| 90 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,379.74 | $910.00 | $910.00 | $1,350.00 | $1,650.00 | $1,328.00 |
| 91 | Pull box removed (625E31510) | EACH | 7 | $555.84 | $500.00 | $500.00 | $550.00 | $225.00 | $535.00 |
| 92 | Ground rod (625E32000) | EACH | 50 | $283.64 | $135.00 | $135.00 | $280.00 | $325.00 | $273.00 |
| 93 | Power service, as per plan (625E34001) | EACH | 1 | $18,497 | $2,233.96 | $2,233.96 | $18,000 | $13,000 | $17,803 |
| 94 | Underground warning marking tape (625E36010) | FT | 8,815 | $4.21 | $1.62 | $1.62 | $4.00 | $1.75 | $4.05 |
| 95 | Light pole removed (625E75400) | EACH | 7 | $249.35 | $1,250.00 | $1,250.00 | $245.00 | $325.00 | $240.00 |
| 96 | Delineator, post ground mounted (620E00500) | EACH | 18 | $126.53 | $55.00 | $55.00 | $100.00 | $65.00 | $86.24 |
| 97 | RPM (621E00100) | EACH | 141 | $52.78 | $51.00 | $51.00 | $62.00 | $51.00 | $51.00 |
| 98 | Ground mounted support, no. 3 post (630E03100) | FT | 611.60 | $19.12 | $15.00 | $15.00 | $17.00 | $15.00 | $16.75 |
| 99 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 100.60 | $52.52 | $44.00 | $44.00 | $47.00 | $60.00 | $46.00 |
| 100 | Ground mounted structural beam support, W10X12 (630E07600) | FT | 39.40 | $41.10 | $32.00 | $32.00 | $37.00 | $50.00 | $36.00 |
| 101 | Sign post reflector (630E08600) | EACH | 52 | $51.38 | $50.00 | $50.00 | $46.00 | $45.00 | $45.00 |
| 102 | Breakaway structural beam connection (630E09000) | EACH | 6 | $913.39 | $750.00 | $750.00 | $815.00 | $870.00 | $800.00 |
| 103 | Sign, flat sheet (630E80100) | SF | 328 | $25.57 | $22.50 | $22.50 | $23.00 | $21.00 | $22.40 |
| 104 | Sign, ground mounted extrusheet (630E80200) | SF | 276 | $37.96 | $30.00 | $30.00 | $34.00 | $29.50 | $33.25 |
| 105 | Ground mounted structural beam support foundation (630E84500) | EACH | 6 | $1,484.26 | $1,500.00 | $1,500.00 | $1,325.00 | $1,320.00 | $1,300.00 |
| 106 | Removal of ground mounted sign and disposal (630E84900) | EACH | 9 | $74.21 | $25.00 | $25.00 | $75.00 | $15.00 | $65.00 |
| 107 | Removal of ground mounted post support and disposal (630E86002) | EACH | 9 | $171.26 | $25.00 | $25.00 | $170.00 | $20.00 | $150.00 |
| 108 | Chevron marking (644E00720) | FT | 133 | $9.31 | $9.00 | $9.00 | $42.00 | $9.00 | $9.00 |
| 109 | Parking lot stall marking (646E20200) | FT | 11,830 | $2.17 | $2.10 | $2.10 | $3.50 | $2.10 | $2.10 |
| 110 | Lane arrow (646E20300) | EACH | 22 | $206.97 | $200.00 | $200.00 | $180.00 | $200.00 | $200.00 |
| 111 | Wrong way arrow (646E20320) | EACH | 2 | $258.71 | $250.00 | $250.00 | $280.00 | $250.00 | $250.00 |
| 112 | Wet reflective epoxy pavement marking, edge line, 6" (807E12010) | MI | 0.49 | $8,278.67 | $8,000.00 | $8,000.00 | $5,500.00 | $8,000.00 | $8,000.00 |
| 113 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 0.61 | $4,449.79 | $4,300.00 | $4,300.00 | $4,000.00 | $4,300.00 | $4,300.00 |
| 114 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 3,298 | $1.35 | $1.30 | $1.30 | $2.50 | $1.30 | $1.30 |
| 115 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 1,542 | $0.93 | $0.90 | $0.90 | $2.50 | $0.90 | $0.90 |
| 116 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 0.61 | $4,656.75 | $4,500.00 | $4,500.00 | $3,600.00 | $4,500.00 | $4,500.00 |
| 117 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 1,542 | $0.78 | $0.75 | $0.75 | $1.25 | $0.75 | $0.75 |
| 118 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,298 | $0.98 | $0.95 | $0.95 | $1.50 | $0.95 | $0.95 |
| 119 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 0.49 | $5,898.55 | $5,700.00 | $5,700.00 | $4,000.00 | $5,700.00 | $5,700.00 |
| 120 | Connection, unfused permanent (625E00480) | EACH | 15 | $187.53 | $37.81 | $37.81 | $185.00 | $130.00 | $180.50 |
| 121 | No. 2 AWG 2400 volt distribution cable (625E23300) | FT | 2,304 | $6.60 | $5.04 | $5.04 | $6.50 | $5.85 | $6.35 |
| 122 | Conduit, 2-1/2", 725.05 (625E25406) | FT | 685 | $10.13 | $2.23 | $2.23 | $10.00 | $16.50 | $9.75 |
| 123 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 193 | $64.57 | $45.00 | $45.00 | $63.00 | $56.00 | $62.15 |
| 124 | Trench, 30" deep (625E29010) | FT | 1,871 | $14.49 | $25.00 | $25.00 | $14.00 | $8.50 | $13.95 |
| 125 | Pull box, 725.08, 18" (625E30700) | EACH | 4 | $1,016.10 | $734.99 | $734.99 | $1,000.00 | $1,350.00 | $978.00 |
| 126 | Pull box removed and replaced, as per plan (625E31507) | EACH | 1 | $1,054.54 | $1,975.00 | $1,975.00 | $1,035.00 | $4,800.00 | $1,015.00 |
| 127 | Ground rod, as per plan (625E32001) | EACH | 9 | $283.64 | $135.00 | $135.00 | $280.00 | $325.00 | $273.00 |
| 128 | Underground warning/marking tape, as per plan (625E36011) | FT | 1,871 | $2.44 | $1.62 | $1.62 | $2.50 | $1.75 | $2.35 |
| 129 | Arc flash calculations and label, lighting control (625E76000) | EACH | 1 | $2,857.13 | $1,250.00 | $1,250.00 | $2,800.00 | $3,650.00 | $2,750.00 |
| 130 | Cabinet foundation, as per plan (633E67101) | EACH | 2 | $5,953.23 | $4,250.00 | $4,250.00 | $5,800.00 | $6,900.00 | $5,730.00 |
| 131 | ITS pull box with pad and standard lid assembly, 3 (809E01900) | EACH | 5 | $5,057.65 | $2,240.00 | $2,240.00 | $5,000.00 | $4,585.00 | $4,868.00 |
| 132 | Micro-duct pathway, 4 cell 14/10 (809E20020) | FT | 1,379 | $11.95 | $3.35 | $3.35 | $12.00 | $12.00 | $11.50 |
| 133 | Micro-duct pathway, jacked or drilled, 4 cell, 14/ (809E22000) | FT | 412 | $52.68 | $35.00 | $35.00 | $52.00 | $19.50 | $50.70 |
| 134 | ITS power service, ground mounted, 120/240V, 60 amp (809E51000) | EACH | 1 | $18,067 | $9,642.50 | $9,642.50 | $17,500 | $11,000 | $17,390 |
| 135 | CCTV IP-camera system, quad multi-view fixed with PTZ (809E60040) | EACH | 2 | $11,195 | $10,840 | $10,840 | $11,000 | $10,700 | $10,775 |
| 136 | CCTV lowering unit (809E61090) | EACH | 2 | $18,618 | $10,387 | $10,387 | $18,000 | $9,000.00 | $17,920 |
| 137 | ITS cabinet - ground mounted (809E65000) | EACH | 2 | $11,709 | $7,807.10 | $7,807.10 | $11,500 | $11,500 | $11,270 |
| 138 | ITS device, misc.: CCTV pole, 90 feet tall (809E65990) | EACH | 2 | $41,997 | $26,983 | $26,983 | $41,000 | $48,350 | $40,422 |
| 139 | As-built construction plans (809E70050) | LS | 1 | $28,636 | $12,500 | $12,500 | $15,500 | $7,500.00 | $15,400 |
| 140 | Traffic compacted surface, type A or B, as per plan (410E12001) | CY | 930 | $74.02 | $50.00 | $50.00 | $110.00 | $182.00 | $192.98 |
| 141 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 2 | $1,992.19 | $1,930.00 | $1,925.13 | $7,500.00 | $5,000.00 | $3,639.34 |
| 142 | Work zone increased penalties sign (614E12484) | EACH | 2 | $260.18 | $300.00 | $251.42 | $250.00 | $550.00 | $256.45 |
| 143 | Barrier reflector, type 1 (one-way) (614E13310) | EACH | 111 | $11.18 | $12.00 | $10.80 | $13.00 | $7.00 | $28.95 |
| 144 | Object marker, one way (614E13350) | EACH | 111 | $21.23 | $20.00 | $20.52 | $38.00 | $20.00 | $28.95 |
| 145 | Portable barrier, unanchored (622E41100) | FT | 5,490 | $37.04 | $30.00 | $30.00 | $45.00 | $40.00 | $47.94 |
| 146 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $26,361 | $165,000 | $85,000 | $100,000 | $77,000 | $65,471 |
| 147 | Maintaining traffic (614E11000) | LS | 1 | $28,920 | $15,000 | $25,000 | $100,000 | $23,000 | $173,111 |
| 148 | Field office, type B (619E16010) | MNTH | 9 | $3,374.22 | $3,000.00 | $3,500.00 | $1,500.00 | $2,900.00 | $3,113.61 |
| 149 | Construction layout stakes and surveying (623E10000) | LS | 1 | $72,438 | $65,000 | $55,000 | $75,000 | $150,000 | $50,981 |
| 150 | Mobilization (624E10000) | LS | 1 | $370,065 | $600,000 | $692,500 | $287,594 | $780,000 | $500,000 |
| 200 | Walk removed (202E30000) | SF | 2,522 | $2.97 | $3.00 | $4.25 | $1.50 | $3.00 | $7.77 |
| 201 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 1,461 | $236.89 | $224.00 | $224.00 | $230.00 | $224.00 | $285.00 |
| 202 | Curb, misc.:curb turnout (609E98100) | EACH | 5 | $1,673.51 | $850.00 | $1,400.00 | $570.00 | $2,000.00 | $500.00 |
| 203 | Light tower, misc.:BBBBBB45 (625E13500) | EACH | 2 | $21,543 | $25,326 | $25,326 | $21,160 | $21,500 | $20,735 |
| 204 | CPM progress schedule (108E10000) | LS | 1 | $21,089 | $12,500 | $1,000.00 | $17,000 | $20,000 | $10,567 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of July 30, 2026. Compiled by Mirage Metrics.