ODOT contract 268015 bid tabulation

PRE-IR 70 WB Truck Parking (PARKING AREAS). Let by Ohio DOT on July 30, 2026, PRE. 6 bids received; low bid $11,919,317 by R B Jergens Contractors Inc, -4.5% against the engineer's estimate of $12,479,000.

Owner
Ohio DOT
Letting
30 JUL 2026
Pay items
155
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1R B Jergens Contractors Inc$11,919,317Low-4.0%
2Eagle Bridge Co$12,783,481+7.0%+2.0%
3Great Lakes Construction Co$13,841,717+16%+11%
4Brumbaugh Construction Inc$15,300,000+28%+23%
5Complete General Construction Company$15,619,399+31%+25%
6John R Jurgensen Company$16,946,821+42%+36%
ODOT contract 268015: bids by rank

Engineer's estimate: $12,479,000.

Bid tabulation

LinePay itemUnitQuantity1. R B Jergens Contractors Inc2. Eagle Bridge Co3. Great Lakes Construction Co4. Brumbaugh Construction Inc5. Complete General Construction Company6. John R Jurgensen Company
1Clearing and grubbing (201E11000)LS1$112,327$100,000$158,000$350,000$80,000$83,539
2Headwall removed (202E20010)EACH6$353.35$650.00$370.00$350.00$770.00$1,215.73
3Pavement removed (202E23000)SY37,331$11.83$7.00$11.50$12.00$14.25$16.89
4Curb removed (202E32000)FT4,278$4.32$3.75$2.00$10.00$8.00$6.24
5Pipe removed, 24" and under (202E35100)FT1,856$31.82$12.00$18.00$10.00$35.00$38.91
6Pipe removed, over 24" diameter (202E35200)FT250$52.23$20.00$50.00$60.00$65.00$82.52
7Manhole removed (202E58000)EACH15$758.52$500.00$850.00$600.00$1,000.00$1,215.73
8Inlet removed (202E58200)EACH4$685.35$350.00$850.00$250.00$1,000.00$1,463.32
9Fence removed (202E75000)FT9,231$5.35$4.00$4.50$5.50$2.80$5.00
10Removal misc.: removal of wood pole and disposal (202E98100)EACH1$620.52$250.00$350.00$700.00$1,320.00$580.00
11Excavation (203E10000)CY67,190$9.91$12.00$24.30$12.00$24.00$20.34
12Embankment (203E20000)CY24,032$6.31$3.00$7.50$10.00$4.00$13.98
13Geotextile fabric (204E50000)SY1,767$4.72$2.50$2.00$3.00$4.00$3.07
14Cement (206E10500)TON1,395$253.26$226.00$226.00$210.00$226.00$277.50
15Curing coat (206E11000)SY53,673$1.40$1.40$1.25$1.50$1.39$1.41
16Cement stabilized subgrade, 12 inches deep (206E15010)SY53,673$2.52$4.25$3.80$4.20$2.90$6.61
17Mixture design for chemically stabilized soils (206E30000)LS1$20,593$21,000$19,900$25,000$19,900$24,000
18Ditch cleanout (209E10000)FT2,350$7.45$7.00$10.00$6.00$14.00$18.27
19Fence, type 47RA (607E15100)FT6,357$17.65$15.50$15.50$17.00$16.50$16.50
20Fenceline seeding and mulching (607E70000)FT6,357$1.42$0.50$2.00$3.00$1.10$0.80
214" concrete walk (608E10000)SF9,768$7.20$6.50$9.25$11.00$8.00$10.76
22Curb ramp (608E52000)SF1,001$34.96$14.00$10.00$28.00$24.00$28.14
23Inspection and compaction testing of unbound materials (878E25000)LS1$116,340$80,000$90,200$150,000$125,000$94,306
24Tied concrete block mat with type 1 underlayment (601E21050)SY14$142.45$100.00$195.00$240.00$160.00$438.99
25Dumped rock fill, type D (601E28000)CY978$119.56$100.00$70.00$90.00$95.00$134.68
26Rock channel protection, type C with geotextile fabric (601E32204)CY2$353.57$150.00$270.00$100.00$465.00$745.43
27Water (616E10000)MGAL550$140.05$15.00$55.00$3.00$100.00$55.83
28Soil analysis test (659E00100)EACH2$206.97$400.00$200.00$100.00$100.00$50.00
29Topsoil (659E00300)CY5,395$41.96$5.00$24.00$30.00$36.00$40.11
30Seeding and mulching (659E10000)SY48,596$0.70$1.25$0.68$1.00$0.98$0.61
31Repair seeding and mulching (659E14000)SY2,431$0.52$1.00$0.50$2.00$0.90$0.61
32Inter-seeding (659E15000)SY2,431$0.01$0.25$0.01$2.00$0.90$0.61
33Commercial fertilizer (659E20000)TON6.78$1,552.25$1,500.00$1,500.00$900.00$700.00$700.00
34Lime (659E31000)ACRE10.05$206.97$1.00$200.00$100.00$10.00$0.15
35Water (659E35000)MGAL270$1.03$1.00$1.00$3.00$1.00$0.15
36Slope erosion protection (670E00500)SY7,348$2.02$2.50$1.95$2.00$1.85$1.63
37Storm water pollution prevention plan (832E15000)LS1$3,156.24$5,000.00$4,500.00$4,000.00$5,000.00$3,200.00
38Storm water pollution prevention inspections (832E15002)LS1$20,179$22,500$17,000$22,000$30,000$10,670
39Storm water pollution prevention inspection software (832E15010)LS1$16,557$17,500$15,000$16,000$13,853$13,852
40Erosion control (832E30000)EACH100,000$1.00$1.00$1.00$1.00$1.00$1.00
41Concrete masonry (602E20000)CY2.80$2,001.03$2,000.00$3,500.00$1,200.00$4,150.00$2,290.85
426" base pipe underdrains with geotextile fabric (605E14020)FT18,272$10.64$11.00$14.50$8.00$18.00$18.19
436" conduit, type F for underdrain outlets (611E00510)FT425$22.35$25.00$35.00$12.00$25.00$67.23
4412" conduit, type B (611E04400)FT764$71.20$100.00$105.00$70.00$170.00$88.25
4515" conduit, type B (611E05900)FT640$65.83$90.00$95.00$80.00$130.00$91.48
4615" conduit, type C (611E06100)FT32$60.45$85.00$125.00$100.00$118.00$133.58
4718" conduit, type B (611E07400)FT588$95.87$175.00$145.00$120.00$268.00$124.56
4824" conduit, type B (611E10400)FT495$140.27$225.00$220.00$175.00$419.00$197.72
4924" conduit, type C (611E10600)FT178$120.25$200.00$145.00$175.00$209.00$221.55
5030" conduit, type B (611E13400)FT380$176.01$250.00$255.00$160.00$495.00$247.48
5136" conduit, type A (611E16200)FT14$256.29$480.00$440.00$320.00$590.00$581.48
5236" conduit, type B (611E16400)FT58$227.56$270.00$325.00$270.00$420.00$389.02
53Catch basin, no. 3, as per plan (611E98151)EACH2$9,315.45$10,500$13,500$14,000$6,700.00$13,148
54Catch basin, no. 3A (611E98180)EACH2$4,647.62$3,500.00$7,700.00$9,000.00$4,450.00$6,727.07
55Catch basin, no. 3A, as per plan (611E98181)EACH4$4,647.62$6,500.00$7,900.00$10,500$5,000.00$8,291.61
56Catch basin, no. 6 (611E98370)EACH4$3,089.43$3,500.00$6,000.00$9,000.00$4,700.00$3,946.29
57Catch basin, no. 2-3 (611E98510)EACH2$2,621.39$3,000.00$3,500.00$6,000.00$2,900.00$2,911.01
58Catch basin, no. 2-4 (611E98540)EACH3$4,454.39$5,500.00$7,200.00$8,000.00$3,600.00$5,569.58
59Manhole, no. 3 (611E99574)EACH1$5,625.79$6,000.00$5,200.00$11,000$7,000.00$4,036.23
60Precast reinforced concrete outlet (611E99710)EACH7$825.41$450.00$500.00$800.00$450.00$772.35
61Pavement planing, asphalt concrete, T = 1.5" min. (254E01000)SY2,852$2.49$2.35$2.35$5.00$2.35$7.50
62Full depth pavement sawing, as per plan (255E20001)FT500$6.21$3.00$3.00$3.00$4.00$3.65
63Asphalt concrete base, PG64-22, (449) (301E56000)CY351$251.69$238.00$238.00$245.00$238.00$290.00
64Aggregate base (304E20000)CY9,057$58.78$68.00$63.50$75.00$72.00$78.52
65Tack coat (407E10000)GAL920$1.06$1.00$1.00$1.00$1.00$5.00
66Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY88$338.41$320.00$320.00$330.00$320.00$425.00
67Asphalt concrete intermediate course, type 2, (446) (441E10200)CY123$290.82$275.00$275.00$280.00$275.00$355.00
68Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000)CY407$322.55$305.00$305.00$315.00$305.00$405.00
69Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100)CY529$301.40$285.00$285.00$290.00$285.00$325.00
70Asphalt concrete intermediate course, 19 MM, type A (449) (442E22400)CY105$311.97$295.00$295.00$300.00$295.00$460.00
7110" non-reinforced concrete pavement, class QC 1P with QC/QA, as per plan (452E14021)SY45,688$94.04$114.50$110.25$150.00$125.00$150.09
72Curb, type 6 (609E26000)FT2,785$16.31$30.00$23.00$30.00$25.00$31.28
73Curb, type 7 (609E28000)FT5,842$23.03$30.00$23.00$32.00$28.00$32.79
74Rumble strips, shoulder (asphalt concrete) (618E40600)MI0.35$19,144$25,000$18,150$46,000$24,000$18,150
75Connection, fused pull apart (625E00450)EACH52$210.39$97.92$97.92$200.00$155.00$202.50
76Connection, unfused pull apart (625E00460)EACH26$198.96$93.87$93.87$195.00$150.00$191.50
77Connection, unfused permanent (625E00480)EACH24$187.53$37.81$37.81$185.00$130.00$180.50
78Light pole, conventional, (AT12B40) (625E10490)EACH4$3,642.59$3,368.89$3,368.89$3,600.00$2,850.00$3,506.00
79Light pole, conventional, (AT8B40) (625E10490)EACH22$3,605.18$3,309.04$3,309.04$3,600.00$2,750.00$3,470.00
80Light tower, misc.:BBBB45 (625E13500)EACH10$21,475$25,136$25,136$21,000$21,500$20,670
81Light pole foundation, 24" X 8' deep (625E14100)EACH26$2,244.15$2,750.00$2,750.00$2,200.00$2,800.00$2,160.00
82Light tower foundation, 36" X 15' deep (625E15000)EACH12$10,266$6,500.00$6,500.00$10,000$18,000$9,881.00
83No. 10 AWG pole and bracket cable (625E23400)FT3,016$2.18$0.71$0.71$2.15$2.40$2.10
841-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320)FT9,553$15.79$14.28$14.28$15.50$17.00$15.20
85Conduit, 3", 725.04 (625E25500)FT287$35.64$28.09$28.09$35.00$40.00$34.30
86Luminaire, conventional, solid state (LED), as per plan (625E26253)EACH26$524.67$463.54$463.54$515.00$640.00$505.00
87Luminaire, high mast, solid state (LED), as per plan (625E26263)EACH52$1,278.96$1,132.75$1,132.75$1,260.00$1,025.00$1,231.00
88Trench, 24" deep (625E29002)FT8,815$11.69$16.50$16.50$11.50$8.50$11.25
89Pull box, 725.08, 18" (625E30700)EACH17$988.05$734.99$734.99$970.00$1,350.00$951.00
90Pull box, 725.08, 24" (625E30706)EACH1$1,379.74$910.00$910.00$1,350.00$1,650.00$1,328.00
91Pull box removed (625E31510)EACH7$555.84$500.00$500.00$550.00$225.00$535.00
92Ground rod (625E32000)EACH50$283.64$135.00$135.00$280.00$325.00$273.00
93Power service, as per plan (625E34001)EACH1$18,497$2,233.96$2,233.96$18,000$13,000$17,803
94Underground warning marking tape (625E36010)FT8,815$4.21$1.62$1.62$4.00$1.75$4.05
95Light pole removed (625E75400)EACH7$249.35$1,250.00$1,250.00$245.00$325.00$240.00
96Delineator, post ground mounted (620E00500)EACH18$126.53$55.00$55.00$100.00$65.00$86.24
97RPM (621E00100)EACH141$52.78$51.00$51.00$62.00$51.00$51.00
98Ground mounted support, no. 3 post (630E03100)FT611.60$19.12$15.00$15.00$17.00$15.00$16.75
99Ground mounted structural beam support, W8X18 (630E07000)FT100.60$52.52$44.00$44.00$47.00$60.00$46.00
100Ground mounted structural beam support, W10X12 (630E07600)FT39.40$41.10$32.00$32.00$37.00$50.00$36.00
101Sign post reflector (630E08600)EACH52$51.38$50.00$50.00$46.00$45.00$45.00
102Breakaway structural beam connection (630E09000)EACH6$913.39$750.00$750.00$815.00$870.00$800.00
103Sign, flat sheet (630E80100)SF328$25.57$22.50$22.50$23.00$21.00$22.40
104Sign, ground mounted extrusheet (630E80200)SF276$37.96$30.00$30.00$34.00$29.50$33.25
105Ground mounted structural beam support foundation (630E84500)EACH6$1,484.26$1,500.00$1,500.00$1,325.00$1,320.00$1,300.00
106Removal of ground mounted sign and disposal (630E84900)EACH9$74.21$25.00$25.00$75.00$15.00$65.00
107Removal of ground mounted post support and disposal (630E86002)EACH9$171.26$25.00$25.00$170.00$20.00$150.00
108Chevron marking (644E00720)FT133$9.31$9.00$9.00$42.00$9.00$9.00
109Parking lot stall marking (646E20200)FT11,830$2.17$2.10$2.10$3.50$2.10$2.10
110Lane arrow (646E20300)EACH22$206.97$200.00$200.00$180.00$200.00$200.00
111Wrong way arrow (646E20320)EACH2$258.71$250.00$250.00$280.00$250.00$250.00
112Wet reflective epoxy pavement marking, edge line, 6" (807E12010)MI0.49$8,278.67$8,000.00$8,000.00$5,500.00$8,000.00$8,000.00
113Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010)MI0.61$4,449.79$4,300.00$4,300.00$4,000.00$4,300.00$4,300.00
114Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310)FT3,298$1.35$1.30$1.30$2.50$1.30$1.30
115Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410)FT1,542$0.93$0.90$0.90$2.50$0.90$0.90
116Grooving for 6" recessed pavement marking, (asphalt) (850E10010)MI0.61$4,656.75$4,500.00$4,500.00$3,600.00$4,500.00$4,500.00
117Grooving for 6" recessed pavement marking, (asphalt) (850E10110)FT1,542$0.78$0.75$0.75$1.25$0.75$0.75
118Grooving for 12" recessed pavement marking, (asphalt) (850E10130)FT3,298$0.98$0.95$0.95$1.50$0.95$0.95
119Grooving for 6" recessed pavement marking, (concrete) (850E20010)MI0.49$5,898.55$5,700.00$5,700.00$4,000.00$5,700.00$5,700.00
120Connection, unfused permanent (625E00480)EACH15$187.53$37.81$37.81$185.00$130.00$180.50
121No. 2 AWG 2400 volt distribution cable (625E23300)FT2,304$6.60$5.04$5.04$6.50$5.85$6.35
122Conduit, 2-1/2", 725.05 (625E25406)FT685$10.13$2.23$2.23$10.00$16.50$9.75
123Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT193$64.57$45.00$45.00$63.00$56.00$62.15
124Trench, 30" deep (625E29010)FT1,871$14.49$25.00$25.00$14.00$8.50$13.95
125Pull box, 725.08, 18" (625E30700)EACH4$1,016.10$734.99$734.99$1,000.00$1,350.00$978.00
126Pull box removed and replaced, as per plan (625E31507)EACH1$1,054.54$1,975.00$1,975.00$1,035.00$4,800.00$1,015.00
127Ground rod, as per plan (625E32001)EACH9$283.64$135.00$135.00$280.00$325.00$273.00
128Underground warning/marking tape, as per plan (625E36011)FT1,871$2.44$1.62$1.62$2.50$1.75$2.35
129Arc flash calculations and label, lighting control (625E76000)EACH1$2,857.13$1,250.00$1,250.00$2,800.00$3,650.00$2,750.00
130Cabinet foundation, as per plan (633E67101)EACH2$5,953.23$4,250.00$4,250.00$5,800.00$6,900.00$5,730.00
131ITS pull box with pad and standard lid assembly, 3 (809E01900)EACH5$5,057.65$2,240.00$2,240.00$5,000.00$4,585.00$4,868.00
132Micro-duct pathway, 4 cell 14/10 (809E20020)FT1,379$11.95$3.35$3.35$12.00$12.00$11.50
133Micro-duct pathway, jacked or drilled, 4 cell, 14/ (809E22000)FT412$52.68$35.00$35.00$52.00$19.50$50.70
134ITS power service, ground mounted, 120/240V, 60 amp (809E51000)EACH1$18,067$9,642.50$9,642.50$17,500$11,000$17,390
135CCTV IP-camera system, quad multi-view fixed with PTZ (809E60040)EACH2$11,195$10,840$10,840$11,000$10,700$10,775
136CCTV lowering unit (809E61090)EACH2$18,618$10,387$10,387$18,000$9,000.00$17,920
137ITS cabinet - ground mounted (809E65000)EACH2$11,709$7,807.10$7,807.10$11,500$11,500$11,270
138ITS device, misc.: CCTV pole, 90 feet tall (809E65990)EACH2$41,997$26,983$26,983$41,000$48,350$40,422
139As-built construction plans (809E70050)LS1$28,636$12,500$12,500$15,500$7,500.00$15,400
140Traffic compacted surface, type A or B, as per plan (410E12001)CY930$74.02$50.00$50.00$110.00$182.00$192.98
141Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380)EACH2$1,992.19$1,930.00$1,925.13$7,500.00$5,000.00$3,639.34
142Work zone increased penalties sign (614E12484)EACH2$260.18$300.00$251.42$250.00$550.00$256.45
143Barrier reflector, type 1 (one-way) (614E13310)EACH111$11.18$12.00$10.80$13.00$7.00$28.95
144Object marker, one way (614E13350)EACH111$21.23$20.00$20.52$38.00$20.00$28.95
145Portable barrier, unanchored (622E41100)FT5,490$37.04$30.00$30.00$45.00$40.00$47.94
146Premium for contract performance bond and for payment bond (103E05000)LS1$26,361$165,000$85,000$100,000$77,000$65,471
147Maintaining traffic (614E11000)LS1$28,920$15,000$25,000$100,000$23,000$173,111
148Field office, type B (619E16010)MNTH9$3,374.22$3,000.00$3,500.00$1,500.00$2,900.00$3,113.61
149Construction layout stakes and surveying (623E10000)LS1$72,438$65,000$55,000$75,000$150,000$50,981
150Mobilization (624E10000)LS1$370,065$600,000$692,500$287,594$780,000$500,000
200Walk removed (202E30000)SF2,522$2.97$3.00$4.25$1.50$3.00$7.77
201Asphalt concrete base, PG64-22, (449) (302E56000)CY1,461$236.89$224.00$224.00$230.00$224.00$285.00
202Curb, misc.:curb turnout (609E98100)EACH5$1,673.51$850.00$1,400.00$570.00$2,000.00$500.00
203Light tower, misc.:BBBBBB45 (625E13500)EACH2$21,543$25,326$25,326$21,160$21,500$20,735
204CPM progress schedule (108E10000)LS1$21,089$12,500$1,000.00$17,000$20,000$10,567
ODOT contract 268015: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of July 30, 2026. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy