ODOT contract 260521 bid tabulation
GUE-IR 70 EB Rest Area TP (PARKING AREAS). Let by Ohio DOT on November 12, 2026, GUE. 8 bids received; low bid $7,379,661 by Shelly & Sands Inc, -3.3% against the engineer's estimate of $7,628,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 131
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Shelly & Sands Inc | $7,379,661 | Low | -3.0% |
| 2 | Miller Bros Const Inc | $7,415,048 | 0.0% | -3.0% |
| 3 | Sunesis Construction Co | $7,599,321 | +3.0% | 0.0% |
| 4 | Complete General Construction Company | $7,713,006 | +5.0% | +1.0% |
| 5 | Alan Stone Co Inc | $7,803,299 | +6.0% | +2.0% |
| 6 | Buds Inc | $7,957,322 | +8.0% | +4.0% |
| 7 | Ruhlin Company | $7,999,901 | +8.0% | +5.0% |
| 8 | Great Lakes Construction Co | $8,179,075 | +11% | +7.0% |
Engineer's estimate: $7,628,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Shelly & Sands Inc | 2. Miller Bros Const Inc | 3. Sunesis Construction Co | 4. Complete General Construction Company | 5. Alan Stone Co Inc | 6. Buds Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $58,000 | $56,600 | $46,708 | $40,000 | $49,000 | $30,000 |
| 2 | Pavement removed, as per plan (202E23001) | SY | 10,852 | $14.00 | $11.07 | $15.69 | $15.00 | $6.00 | $12.00 |
| 3 | Walk removed (202E30000) | SF | 10,079 | $1.00 | $0.72 | $1.39 | $1.00 | $0.60 | $3.00 |
| 4 | Curb removed (202E32000) | FT | 4,696 | $2.50 | $3.43 | $3.93 | $9.00 | $0.50 | $3.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 1,268 | $32.00 | $88.14 | $19.86 | $50.00 | $6.00 | $30.00 |
| 6 | Guardrail removed (202E38000) | FT | 253 | $5.00 | $3.00 | $5.87 | $3.00 | $4.50 | $6.00 |
| 7 | Anchor assembly removed (202E42206) | EACH | 2 | $150.00 | $148.00 | $386.77 | $148.00 | $550.00 | $500.00 |
| 8 | Building demolished (restroom) (202E56100) | EACH | 1 | $14,500 | $24,500 | $10,282 | $14,500 | $35,000 | $10,500 |
| 9 | Building demolished (vending) (202E56100) | EACH | 1 | $4,500.00 | $4,500.00 | $4,747.06 | $4,500.00 | $11,000 | $10,000 |
| 10 | Manhole removed (202E58000) | EACH | 2 | $400.00 | $1,655.79 | $731.11 | $780.00 | $440.00 | $500.00 |
| 11 | Catch basin or inlet removed (202E58300) | EACH | 11 | $550.00 | $1,346.98 | $479.04 | $540.00 | $590.00 | $300.00 |
| 12 | Fence removed (202E75000) | FT | 410 | $2.75 | $2.75 | $5.88 | $2.75 | $7.50 | $10.00 |
| 13 | Valve box removed (202E75610) | EACH | 3 | $220.00 | $252.95 | $142.89 | $500.00 | $120.00 | $500.00 |
| 14 | Removal misc.: sanitary pump station (202E98000) | LS | 1 | $32,500 | $41,454 | $27,341 | $32,500 | $26,000 | $22,000 |
| 15 | Removal misc.: 30" concrete trash can (202E98100) | EACH | 11 | $1,100.00 | $100.00 | $166.37 | $100.00 | $220.00 | $200.00 |
| 16 | Removal misc.: flag pole (202E98100) | EACH | 1 | $100.00 | $100.00 | $285.78 | $100.00 | $480.00 | $2,000.00 |
| 17 | Removal misc.: pavilion structure (202E98100) | EACH | 1 | $2,500.00 | $2,500.00 | $3,185.71 | $2,500.00 | $1,900.00 | $15,000 |
| 18 | Removal misc.: concrete pad (202E98400) | SF | 2,434 | $2.00 | $2.00 | $2.95 | $2.00 | $2.00 | $4.50 |
| 19 | Excavation (203E10000) | CY | 18,435 | $26.00 | $27.90 | $24.40 | $25.00 | $20.00 | $18.00 |
| 20 | Embankment (203E20000) | CY | 5,512 | $22.00 | $4.58 | $14.31 | $15.00 | $5.50 | $15.00 |
| 21 | Subgrade compaction (204E10000) | SY | 3,923 | $2.50 | $2.50 | $2.98 | $4.00 | $5.00 | $8.00 |
| 22 | Excavation of subgrade (204E13000) | CY | 254 | $40.00 | $70.86 | $44.77 | $47.00 | $35.00 | $40.00 |
| 23 | Granular material, type C (204E30020) | CY | 254 | $100.00 | $112.22 | $114.07 | $84.00 | $140.00 | $135.00 |
| 24 | Proof rolling (204E45000) | HR | 9 | $310.00 | $339.42 | $261.20 | $375.00 | $80.00 | $300.00 |
| 25 | Geotextile fabric (204E50000) | SY | 761 | $2.50 | $3.81 | $2.12 | $5.00 | $1.50 | $2.45 |
| 26 | Lime stabilized subgrade, 14 inches deep (206E10020) | SY | 22,110 | $6.65 | $5.52 | $6.30 | $8.92 | $9.50 | $6.67 |
| 27 | Lime (206E10300) | TON | 668 | $267.20 | $285.00 | $243.48 | $267.19 | $320.00 | $300.00 |
| 28 | Curing coat (206E11000) | SY | 22,110 | $0.65 | $1.28 | $1.35 | $1.35 | $1.50 | $2.35 |
| 29 | Guardrail, type MGS (606E15050) | FT | 337.50 | $25.00 | $25.00 | $22.00 | $27.32 | $30.00 | $26.00 |
| 30 | Anchor assembly, MGS type B (606E26050) | EACH | 2 | $2,750.00 | $2,750.00 | $2,650.00 | $2,920.00 | $3,000.00 | $2,800.00 |
| 31 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,400.00 | $1,400.00 | $1,450.00 | $1,460.00 | $1,500.00 | $1,450.00 |
| 32 | Fence, misc.:wooden slat fence (607E98000) | FT | 104 | $165.00 | $165.00 | $100.00 | $200.17 | $180.00 | $170.00 |
| 33 | Concrete barrier, single slope, type D, as per plan (622E10161) | FT | 525 | $90.00 | $127.00 | $127.00 | $150.00 | $160.00 | $157.00 |
| 34 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 2 | $4,000.00 | $3,800.00 | $3,800.00 | $5,655.00 | $7,700.00 | $4,500.00 |
| 35 | Preconstruction survey monument verification and report (623E50000) | LS | 1 | $4,800.00 | $5,800.00 | $5,800.00 | $1,250.00 | $3,900.00 | $10,000 |
| 36 | Post construction survey monument verification and report (623E51000) | LS | 1 | $4,800.00 | $5,800.00 | $5,800.00 | $1,250.00 | $3,900.00 | $10,000 |
| 37 | Fire hydrant removed (638E10480) | EACH | 1 | $350.00 | $917.31 | $1,098.94 | $2,600.00 | $740.00 | $3,500.00 |
| 38 | Special - bollard (690E50600) | EACH | 8 | $650.00 | $650.00 | $850.00 | $915.00 | $720.00 | $750.00 |
| 39 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $105,000 | $10,800 | $20,570 | $21,500 | $25,000 | $50,000 |
| 40 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 4 | $175.00 | $802.05 | $249.99 | $175.00 | $230.00 | $200.00 |
| 41 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 80 | $110.00 | $220.49 | $178.04 | $250.00 | $160.00 | $145.00 |
| 42 | Topsoil (659E00300) | CY | 936 | $32.00 | $5.84 | $34.64 | $66.00 | $20.00 | $25.00 |
| 43 | Seeding and mulching (659E10000) | SY | 8,505 | $0.75 | $0.74 | $3.24 | $0.80 | $1.50 | $1.00 |
| 44 | Repair seeding and mulching (659E14000) | SY | 422 | $0.80 | $0.80 | $0.80 | $0.80 | $1.50 | $1.00 |
| 45 | Inter-seeding (659E15000) | SY | 422 | $0.80 | $0.80 | $0.80 | $0.80 | $0.70 | $1.00 |
| 46 | Commercial fertilizer (659E20000) | TON | 1.90 | $565.00 | $562.33 | $562.33 | $1,250.00 | $710.00 | $1,300.00 |
| 47 | Lime (659E31000) | ACRE | 1.75 | $160.00 | $160.56 | $160.55 | $150.00 | $0.10 | $175.00 |
| 48 | Water (659E35000) | MGAL | 47 | $1.00 | $1.00 | $1.00 | $1.00 | $0.10 | $1.00 |
| 49 | Storm water pollution prevention plan (832E15000) | LS | 1 | $4,000.00 | $3,000.00 | $2,500.00 | $3,000.00 | $3,900.00 | $4,000.00 |
| 50 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $10,500 | $12,200 | $6,300.00 | $12,200 | $15,000 | $13,500 |
| 51 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $12,600 | $12,538 | $12,538 | $12,600 | $14,000 | $30,000 |
| 52 | Erosion control (832E30000) | EACH | 46,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 53 | 6" base pipe underdrains (605E14000) | FT | 10,375 | $10.50 | $14.94 | $24.40 | $17.00 | $18.00 | $9.50 |
| 54 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 312 | $35.00 | $67.81 | $20.56 | $50.00 | $20.00 | $12.50 |
| 55 | 6" conduit, type B (611E00900) | FT | 74 | $40.00 | $59.61 | $47.36 | $63.00 | $50.00 | $20.00 |
| 56 | 12" conduit, type B (611E04400) | FT | 384 | $170.00 | $82.48 | $163.78 | $175.00 | $90.00 | $65.00 |
| 57 | 24" conduit, type B (611E10400) | FT | 5 | $585.00 | $1,029.66 | $752.72 | $760.00 | $860.00 | $200.00 |
| 58 | 24" conduit, type B (611E10400) | FT | 25 | $585.00 | $610.38 | $392.90 | $380.00 | $170.00 | $200.00 |
| 59 | Catch basin, no. 2-2B (611E98470) | EACH | 2 | $3,400.00 | $2,712.78 | $2,668.00 | $3,750.00 | $3,900.00 | $3,500.00 |
| 60 | Manhole, no. 3 (611E99574) | EACH | 3 | $5,900.00 | $4,813.80 | $4,642.78 | $5,520.00 | $5,100.00 | $8,000.00 |
| 61 | Precast reinforced concrete outlet (611E99710) | EACH | 3 | $500.00 | $441.16 | $409.94 | $550.00 | $490.00 | $350.00 |
| 62 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 387 | $230.00 | $230.00 | $230.00 | $230.00 | $270.00 | $320.00 |
| 63 | Aggregate base (304E20000) | CY | 6,175 | $98.00 | $109.92 | $131.86 | $85.00 | $95.00 | $107.00 |
| 64 | Non-tracking tack coat (407E20000) | GAL | 253 | $3.50 | $3.50 | $3.50 | $3.50 | $6.00 | $5.00 |
| 65 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 96 | $375.00 | $375.00 | $375.00 | $375.00 | $290.00 | $325.00 |
| 66 | Asphalt concrete intermediate course, 19 MM, type A (446) (442E10100) | CY | 160 | $330.00 | $330.00 | $330.00 | $330.00 | $280.00 | $350.00 |
| 67 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 23,132 | $90.00 | $86.57 | $90.72 | $80.00 | $115.00 | $91.51 |
| 68 | 10" non-reinforced concrete pavement, class QC 1P (452E14010) | SY | 120 | $150.00 | $117.00 | $107.46 | $130.00 | $180.00 | $125.00 |
| 69 | Curb, type 7 (609E28000) | FT | 2,777 | $35.00 | $37.45 | $30.33 | $25.00 | $55.00 | $39.50 |
| 70 | 4" concrete traffic island (609E50000) | SY | 254 | $65.00 | $175.10 | $72.65 | $90.00 | $65.00 | $141.00 |
| 71 | Curb, misc.: curb, type 7 snow turnout (609E98000) | FT | 48 | $300.00 | $69.00 | $60.00 | $260.00 | $300.00 | $69.00 |
| 72 | Connection, fused pull apart (625E00450) | EACH | 50 | $160.00 | $160.00 | $160.00 | $150.00 | $180.00 | $180.00 |
| 73 | Connection, unfused permanent (625E00480) | EACH | 12 | $155.00 | $155.00 | $155.00 | $150.00 | $170.00 | $170.00 |
| 74 | Light pole, conventional AT18B40 (625E10490) | EACH | 15 | $4,820.00 | $4,820.00 | $4,820.00 | $5,675.00 | $5,300.00 | $5,100.00 |
| 75 | Light tower, misc.: B45 (625E13500) | EACH | 10 | $22,920 | $22,920 | $22,920 | $19,575 | $25,000 | $23,100 |
| 76 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 15 | $1,555.00 | $1,555.00 | $1,555.00 | $2,300.00 | $1,700.00 | $1,705.00 |
| 77 | Light tower foundation, misc.: 36" X 10' deep (625E15700) | EACH | 10 | $7,275.00 | $7,275.00 | $7,275.00 | $7,750.00 | $8,000.00 | $7,300.00 |
| 78 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,968 | $4.50 | $4.50 | $4.50 | $5.00 | $5.00 | $4.65 |
| 79 | No. 10 AWG pole and bracket cable (625E23400) | FT | 4,080 | $1.08 | $1.08 | $1.08 | $1.25 | $1.00 | $1.10 |
| 80 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 5,108 | $13.70 | $13.67 | $13.67 | $15.50 | $15.00 | $13.72 |
| 81 | Conduit, 2", 725.04 (625E25400) | FT | 591 | $25.00 | $24.57 | $24.57 | $30.00 | $25.00 | $25.00 |
| 82 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 10 | $1,342.00 | $1,342.00 | $1,342.00 | $1,800.00 | $1,500.00 | $1,400.00 |
| 83 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 15 | $515.00 | $515.00 | $515.00 | $420.00 | $570.00 | $525.00 |
| 84 | Trench, 24" deep (625E29002) | FT | 4,906 | $7.15 | $7.14 | $7.14 | $6.50 | $8.00 | $7.30 |
| 85 | Trench in paved area (625E29400) | FT | 548 | $15.05 | $15.05 | $15.05 | $17.00 | $15.00 | $16.00 |
| 86 | Pull box, 725.08, 18" (625E30700) | EACH | 5 | $1,305.00 | $1,305.00 | $1,305.00 | $1,400.00 | $1,400.00 | $1,350.00 |
| 87 | Pull box removed (625E31510) | EACH | 12 | $176.00 | $176.00 | $176.00 | $300.00 | $190.00 | $196.00 |
| 88 | Ground rod (625E32000) | EACH | 25 | $451.00 | $451.00 | $451.00 | $375.00 | $500.00 | $465.00 |
| 89 | Power service, as per plan (625E34001) | EACH | 1 | $19,481 | $19,481 | $19,481 | $12,500 | $21,000 | $21,300 |
| 90 | Underground warning marking tape (625E36010) | FT | 5,699 | $0.60 | $0.06 | $0.06 | $1.50 | $0.10 | $0.07 |
| 91 | Light pole removed (625E75400) | EACH | 25 | $220.00 | $220.00 | $220.00 | $450.00 | $240.00 | $235.00 |
| 92 | Light pole foundation removed (625E75500) | EACH | 25 | $231.00 | $231.00 | $231.00 | $250.00 | $250.00 | $240.00 |
| 93 | Luminaire removed (625E75506) | EACH | 25 | $55.00 | $55.00 | $55.00 | $100.00 | $60.00 | $60.00 |
| 94 | Arc flash calculations and label, power service (625E76000) | EACH | 1 | $3,410.00 | $3,410.00 | $3,410.00 | $4,000.00 | $3,800.00 | $3,500.00 |
| 95 | Ground mounted support, no. 3 post (630E03100) | FT | 37 | $18.00 | $18.00 | $14.00 | $23.00 | $20.00 | $19.00 |
| 96 | Ground mounted structural beam support, W8X18 (630E07000) | FT | 92 | $48.00 | $48.00 | $150.00 | $95.00 | $55.00 | $49.00 |
| 97 | Breakaway structural beam connection (630E09000) | EACH | 2 | $750.00 | $750.00 | $500.00 | $960.00 | $830.00 | $800.00 |
| 98 | Sign, flat sheet (630E80100) | SF | 28 | $27.00 | $27.00 | $21.50 | $20.00 | $30.00 | $28.00 |
| 99 | Sign, ground mounted extrusheet (630E80200) | SF | 90 | $32.00 | $32.00 | $42.50 | $29.60 | $35.00 | $33.00 |
| 100 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $2,200.00 | $2,200.00 | $1,000.00 | $1,425.00 | $2,400.00 | $2,400.00 |
| 101 | Removal of ground mounted sign and disposal (630E84900) | EACH | 3 | $25.00 | $25.00 | $50.00 | $15.00 | $30.00 | $25.00 |
| 102 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $25.00 | $25.00 | $50.00 | $20.00 | $30.00 | $25.00 |
| 103 | Edge line, 6" (646E10010) | MI | 0.71 | $6,500.00 | $6,500.00 | $6,500.00 | $6,500.00 | $7,200.00 | $7,500.00 |
| 104 | Channelizing line, 8" (646E10300) | FT | 2,104 | $2.65 | $2.65 | $2.65 | $2.65 | $3.00 | $3.00 |
| 105 | Transverse/diagonal line, as per plan (646E10601) | FT | 2,203 | $2.95 | $2.95 | $2.95 | $2.95 | $3.50 | $3.15 |
| 106 | Parking lot stall marking (646E20200) | FT | 6,031 | $2.95 | $2.95 | $2.95 | $2.95 | $3.50 | $3.25 |
| 107 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 1 | $2,200.00 | $2,200.00 | $2,375.00 | $3,480.00 | $2,400.00 | $3,000.00 |
| 108 | Water (616E10000) | MGAL | 51 | $80.00 | $78.69 | $17.38 | $75.00 | $1.00 | $1.00 |
| 109 | Portable barrier, unanchored (622E41100) | FT | 870 | $40.00 | $46.87 | $43.00 | $30.00 | $30.00 | $33.00 |
| 110 | Unclassified excavation (503E21300) | LS | 1 | $48,000 | $56,648 | $4,404.71 | $132,700 | $165,000 | $250,000 |
| 111 | Steel piles, misc.: W24X104, furnished (507E00400) | FT | 2,320 | $175.00 | $208.56 | $245.34 | $292.00 | $210.00 | $230.00 |
| 112 | Concrete, misc.: class QC1 concrete for raised pan (511E81300) | EACH | 5 | $300.00 | $492.68 | $138.09 | $151.00 | $310.00 | $320.00 |
| 113 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 900 | $25.50 | $32.29 | $0.01 | $26.00 | $35.00 | $40.00 |
| 114 | Elastomeric bearing pad, misc.: 6" X 10" X 3/8" TH (516E42000) | EACH | 996 | $20.00 | $23.02 | $49.60 | $60.00 | $25.00 | $43.00 |
| 115 | Prefabricated geocomposite drain (518E20000) | SY | 780 | $16.00 | $21.60 | $13.59 | $70.00 | $30.00 | $33.00 |
| 116 | Porous backfill with geotextile fabric (518E21200) | CY | 43 | $750.00 | $182.12 | $160.68 | $280.00 | $170.00 | $200.00 |
| 117 | 6" perforated corrugated plastic pipe (518E40000) | FT | 570 | $35.00 | $7.72 | $2.82 | $10.00 | $10.00 | $12.00 |
| 118 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 40 | $55.00 | $15.02 | $10.07 | $38.00 | $20.00 | $25.00 |
| 119 | Drilled shafts, 36" diameter, above bedrock, as per plan (524E94703) | FT | 300 | $255.00 | $67.00 | $363.20 | $186.00 | $140.00 | $145.00 |
| 120 | Drilled shafts, 36" diameter, into bedrock, as per plan (524E94705) | FT | 1,080 | $115.00 | $204.31 | $154.43 | $186.00 | $95.00 | $113.00 |
| 121 | Special - retaining wall, precast concrete lagging (530E51010) | SF | 7,000 | $38.00 | $33.22 | $53.44 | $41.00 | $35.00 | $40.00 |
| 122 | Paved gutter, type 1-2 (601E37500) | FT | 570 | $80.00 | $91.70 | $73.17 | $85.00 | $160.00 | $84.50 |
| 123 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $42,460 | $31,652 | $34,461 | $39,000 | $50,000 | $100,000 |
| 124 | Maintaining traffic (614E11000) | LS | 1 | $17,500 | $26,213 | $10,690 | $17,500 | $62,000 | $75,000 |
| 125 | Field office, type B (619E16010) | MNTH | 7 | $5,000.00 | $6,752.41 | $917.57 | $3,850.00 | $1,600.00 | $1,000.00 |
| 126 | Construction layout stakes and surveying (623E10000) | LS | 1 | $65,700 | $33,750 | $63,500 | $100,000 | $121,000 | $100,000 |
| 127 | Mobilization (624E10000) | LS | 1 | $350,000 | $370,752 | $162,616 | $385,000 | $60,000 | $500,000 |
| 200 | Removal misc.: bench (202E98100) | EACH | 3 | $150.00 | $150.00 | $183.71 | $150.00 | $480.00 | $600.00 |
| 201 | Removal misc.: picnic table (202E98100) | EACH | 3 | $150.00 | $150.00 | $71.77 | $150.00 | $480.00 | $500.00 |
| 202 | Removal misc.: grill (202E98100) | EACH | 3 | $150.00 | $150.00 | $71.77 | $150.00 | $480.00 | $500.00 |
| 203 | Special - asbestos inspection (690E71050) | EACH | 150,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.
Your own bid history, read the same way