Concrete barrier, end anchorage, reinforced, type D, ODOT 622E25050
Low bidders on ODOT contracts carried a median of $5,000.00 per EACH for this item, over the 24 months to 12 NOV 2026, across 26 low bids. Half of all 79 bids fell between $4,350.00 and $6,000.00.
- Owner
- Ohio DOT
- Item
- 622E25050
- Unit
- EACH
- Data through
- 12 NOV 2026
ODOT prints this item as “CONCRETE BARRIER, END ANCHORAGE, REINFORCED, TYPE”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 8 | 9 | $3,500.00 | 35 | $3,500.00 |
| 2021 | 11 | 11 | $4,000.00 | 57 | $4,000.00 |
| 2022 | 18 | 19 | $3,700.00 | 71 | $3,810.96 |
| 2023 | 18 | 19 | $4,645.00 | 63 | $4,254.81 |
| 2024 | 12 | 12 | $4,856.88 | 36 | $5,000.00 |
| 2025 | 12 | 12 | $4,650.00 | 39 | $4,585.00 |
| 2026 | 13 | 13 | $5,500.00 | 37 | $5,500.00 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| FRA | 6 | $4,610.00 | 16 | $5,000.00 |
| HAM | 5 | $6,550.69 | 11 | $5,365.00 |
| CUY | 3 | $5,000.00 | 10 | $5,500.00 |
Countys with at least three low bids, over the last 24 months.
By quantity
| Quantity (EACH) | Low bids | Low-bid median |
|---|---|---|
| 1 to 2 | 6 | $4,885.00 |
| 2 to 4 | 7 | $5,000.00 |
| 4 to 9 | 6 | $4,500.00 |
| 11 to 39 | 7 | $4,841.40 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Kokosing Construction Company Inc | 32 | 19 (59%) |
| Shelly & Sands Inc | 39 | 8 (21%) |
| Complete General Construction Company | 36 | 7 (19%) |
| Sunesis Construction Co | 18 | 7 (39%) |
| Eagle Bridge Co | 15 | 7 (47%) |
| Miller Bros Const Inc | 11 | 6 (55%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260521 | GUE | 2 | $4,000.00 | $5,077.50 | 8 | Shelly & Sands Inc | ODOT |
| 29 OCT 2026 | 260399 | CUY | 2 | $7,500.00 | $6,750.00 | 4 | Tri-Mor Corp | ODOT |
| 08 OCT 2026 | 260398 | HAM | 39 | $6,550.69 | $6,550.69 | 1 | John R Jurgensen Company | ODOT |
| 07 MAY 2026 | 260237 | FRA | 6 | $7,500.00 | $6,400.00 | 2 | Shelly & Sands Inc | ODOT |
| 07 MAY 2026 | 260251 | MOT | 2 | $5,787.77 | $4,893.89 | 2 | John R Jurgensen Company | ODOT |
| 23 APR 2026 | 260221 | FRA | 21 | $5,750.00 | $6,375.00 | 2 | Complete General Construction Company | ODOT |
| 26 MAR 2026 | 260148 | FRA | 2 | $4,770.00 | $5,000.00 | 3 | Complete General Construction Company | ODOT |
| 26 MAR 2026 | 260152 | HAS | 2 | $5,500.00 | $5,250.00 | 2 | Shelly & Sands Inc | ODOT |
| 26 FEB 2026 | 260041 | LIC | 2 | $5,000.00 | $5,175.00 | 2 | Kokosing Construction Company Inc | ODOT |
| 05 FEB 2026 | 260003 | MAH | 11 | $5,400.00 | $6,875.00 | 4 | Shelly & Sands Inc | ODOT |
| 29 JAN 2026 | 260001 | CUY | 2 | $3,200.00 | $4,400.00 | 3 | Ruhlin Company | ODOT |
| 29 JAN 2026 | 260002 | HEN | 9 | $3,525.00 | $3,525.00 | 3 | E S Wagner - Vernon Nagel Joint Venture | ODOT |
| 15 JAN 2026 | 260016 | HAM | 2 | $7,000.00 | $7,000.00 | 1 | 360 Construction Company Inc | ODOT |
| 18 DEC 2025 | 250557 | HAM | 2 | $4,500.00 | $4,650.00 | 4 | Eagle Bridge Co | ODOT |
| 18 DEC 2025 | 250592 | MIA | 8 | $3,250.00 | $4,400.00 | 7 | Eagle Bridge Co | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.