ODOT contract 260221 bid tabulation
FRA-IR 71-17.22 Ramp (INTERCHANGE). Let by Ohio DOT on April 23, 2026, FRA. 2 bids received; low bid $5,254,158 by Complete General Construction Company, +23% against the engineer's estimate of $4,276,000.
- Owner
- Ohio DOT
- Letting
- 23 APR 2026
- Pay items
- 228
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $5,254,158 | Low | +23% |
| 2 | Shelly & Sands Inc | $5,875,999 | +12% | +37% |
Engineer's estimate: $4,276,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Shelly & Sands Inc |
|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $20,000 | $42,000 |
| 2 | Pavement removed (202E23000) | SY | 7,338 | $28.00 | $25.00 |
| 3 | Concrete barrier removed (202E30700) | FT | 1,398 | $36.00 | $65.00 |
| 4 | Curb removed (202E32000) | FT | 3,419 | $8.00 | $7.00 |
| 5 | Concrete slope protection removed (202E32800) | SY | 671 | $30.00 | $30.00 |
| 6 | Pipe removed, 24" and under (202E35100) | FT | 972 | $30.00 | $42.00 |
| 7 | Guardrail removed (202E38000) | FT | 1,183 | $2.80 | $2.50 |
| 8 | Impact attenuator removed (202E47800) | EACH | 2 | $285.00 | $50.00 |
| 9 | Catch basin removed (202E58100) | EACH | 3 | $640.00 | $750.00 |
| 10 | Inlet removed (202E58200) | EACH | 15 | $940.00 | $850.00 |
| 11 | Inlet abandoned (202E58400) | EACH | 1 | $1,100.00 | $1,900.00 |
| 12 | Special - pipe cleanout, 24" and under (202E70110) | FT | 300 | $40.00 | $17.00 |
| 13 | Fence removed (202E75000) | FT | 110 | $6.50 | $5.00 |
| 14 | Excavation (203E10000) | CY | 14,574 | $32.00 | $40.00 |
| 15 | Embankment (203E20000) | CY | 770 | $9.00 | $25.00 |
| 16 | Subgrade compaction (204E10000) | SY | 9,844 | $3.20 | $8.00 |
| 17 | Proof rolling (204E45000) | HR | 5 | $360.00 | $300.00 |
| 18 | Guardrail, type MGS with long posts (606E15100) | FT | 138 | $32.40 | $28.00 |
| 19 | Anchor assembly, MGS type T (606E26550) | EACH | 1 | $1,940.00 | $1,350.00 |
| 20 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 1 | $925.00 | $550.00 |
| 21 | Impact attenuator, type 2 (unidirectional) 62 MPH, (606E60022) | EACH | 1 | $46,375 | $48,000 |
| 22 | Fence, type CLT (607E23000) | FT | 50 | $83.50 | $54.60 |
| 23 | 4" concrete walk (608E10000) | SF | 9 | $67.00 | $65.00 |
| 24 | Concrete barrier, single slope, type D (622E10160) | FT | 1,476 | $128.00 | $125.00 |
| 25 | Concrete barrier end section, type D (622E25000) | EACH | 3 | $5,450.00 | $8,000.00 |
| 26 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 21 | $5,750.00 | $7,000.00 |
| 27 | Concrete barrier, end anchorage, reinforced, type D, as per plan (622E25051) | EACH | 2 | $6,100.00 | $9,000.00 |
| 28 | Special - survey control verification (690E98400) | LS | 1 | $3,500.00 | $7,500.00 |
| 29 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $27,000 | $44,500 |
| 30 | Concrete slope protection (601E21000) | SY | 368 | $165.00 | $195.00 |
| 31 | Soil analysis test (659E00100) | EACH | 1 | $150.00 | $135.00 |
| 32 | Topsoil (659E00300) | CY | 830 | $32.00 | $34.00 |
| 33 | Seeding and mulching, class 3A (659E00520) | SY | 7,481 | $1.00 | $0.75 |
| 34 | Repair seeding and mulching (659E14000) | SY | 374 | $1.00 | $0.80 |
| 35 | Inter-seeding (659E15000) | SY | 374 | $1.00 | $0.80 |
| 36 | Commercial fertilizer (659E20000) | TON | 3 | $1,250.00 | $940.00 |
| 37 | Lime (659E31000) | ACRE | 2 | $150.00 | $161.00 |
| 38 | Water (659E35000) | MGAL | 46 | $1.00 | $1.00 |
| 39 | Mowing (659E40000) | MSF | 0.02 | $25,000 | $100.00 |
| 40 | Ditch erosion protection mat, type B (670E00720) | SY | 783 | $2.50 | $1.50 |
| 41 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $3,500.00 |
| 42 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $12,500 | $14,000 |
| 43 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $13,000 | $12,900 |
| 44 | Erosion control (832E30000) | EACH | 50,000 | $1.00 | $1.00 |
| 45 | 4" shallow pipe underdrains with geotextile fabric (605E05110) | FT | 569 | $20.00 | $22.00 |
| 46 | 4" shallow pipe underdrains with geotextile fabric (605E05110) | FT | 1,905 | $21.00 | $23.00 |
| 47 | 4" shallow pipe underdrains with geotextile fabric (605E05110) | FT | 846 | $26.00 | $25.00 |
| 48 | 4" unclassified pipe underdrains (605E05200) | FT | 100 | $28.50 | $18.00 |
| 49 | 4" base pipe underdrains with geotextile fabric (605E06020) | FT | 2,383 | $21.00 | $21.00 |
| 50 | 4" base pipe underdrains with geotextile fabric (605E06020) | FT | 320 | $16.00 | $20.00 |
| 51 | 4" conduit, type F (611E00406) | FT | 100 | $15.00 | $25.00 |
| 52 | 4" conduit, type F for underdrain outlet (611E00410) | FT | 331 | $15.00 | $50.00 |
| 53 | 12" conduit, type B (611E04400) | FT | 141 | $240.00 | $170.00 |
| 54 | 12" conduit, type C (611E04600) | FT | 9 | $190.00 | $285.00 |
| 55 | 15" conduit, type B (611E05900) | FT | 374 | $240.00 | $175.00 |
| 56 | 15" conduit, type C (611E06100) | FT | 251 | $160.00 | $180.00 |
| 57 | 18" conduit, type B (611E07400) | FT | 73 | $290.00 | $205.00 |
| 58 | 18" conduit, type C (611E07600) | FT | 22 | $270.00 | $225.00 |
| 59 | Catch basin, no. 3 (611E98150) | EACH | 1 | $5,000.00 | $6,000.00 |
| 60 | Catch basin, no. 3A (611E98180) | EACH | 5 | $4,250.00 | $6,200.00 |
| 61 | Catch basin, no. 8 (611E98410) | EACH | 3 | $5,300.00 | $7,500.00 |
| 62 | Catch basin, no. 8 without apron (611E98430) | EACH | 2 | $4,500.00 | $5,500.00 |
| 63 | Inlet, no. 3B (611E98800) | EACH | 1 | $13,500 | $17,000 |
| 64 | Inlet, no. 3D (611E98820) | EACH | 6 | $13,100 | $15,000 |
| 65 | Inlet, no. 3D, as per plan (611E98821) | EACH | 1 | $12,500 | $16,000 |
| 66 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $2,700.00 | $5,500.00 |
| 67 | Special - 12" conduit, type 1 (690E98000) | EACH | 6 | $260.00 | $400.00 |
| 68 | Special - 60" curb inlet (690E98100) | FT | 1 | $5,800.00 | $6,000.00 |
| 69 | Full depth pavement sawing (252E01500) | FT | 1,260 | $5.00 | $5.50 |
| 70 | Pavement planing, asphalt concrete, 1.50" (254E01000) | SY | 14,505 | $7.30 | $9.00 |
| 71 | Pavement planing, asphalt concrete, 3.25" (254E01000) | SY | 461 | $14.25 | $22.50 |
| 72 | Pavement planing, asphalt concrete, variable depth (254E01000) | SY | 649 | $11.50 | $22.50 |
| 73 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 3,043 | $184.00 | $205.00 |
| 74 | Aggregate base (304E20000) | CY | 1,641 | $92.00 | $95.00 |
| 75 | Non-tracking tack coat (407E20000) | GAL | 3,158 | $4.25 | $4.00 |
| 76 | Anti-segregation equipment (442E00100) | CY | 1,085 | $12.50 | $15.00 |
| 77 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 1,027 | $330.00 | $355.00 |
| 78 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 512 | $265.00 | $305.00 |
| 79 | Curb, type 4-C (609E24510) | FT | 1,374 | $28.00 | $35.00 |
| 80 | Curb, type 6 (609E26000) | FT | 376 | $43.00 | $70.00 |
| 81 | Void reducing asphalt membrane (vram) (872E10000) | FT | 3,100 | $13.06 | $3.00 |
| 82 | Special - 6" water main dip and fittings (col 801) (638E11602) | FT | 27 | $500.00 | $300.00 |
| 83 | Special - 8" water main dip and fittings (col 801) (638E11604) | FT | 5 | $300.00 | $1,300.00 |
| 84 | Special - valve box adjusted to grade (col 807) (638E20500) | EACH | 3 | $200.00 | $800.00 |
| 85 | Special - 6" gate valve (col 802) (638E20536) | EACH | 2 | $1,800.00 | $1,800.00 |
| 86 | Special - 6" fire hydrant (col 809) (638E20750) | EACH | 1 | $5,500.00 | $6,000.00 |
| 87 | Special - fire hydrant abandoned (col 809) (638E20758) | EACH | 1 | $850.00 | $7,500.00 |
| 88 | Connection, fused pull apart (625E00450) | EACH | 8 | $150.00 | $150.00 |
| 89 | Connection, unfused pull apart (625E00460) | EACH | 8 | $145.00 | $145.00 |
| 90 | Connection, unfused permanent (625E00480) | EACH | 10 | $130.00 | $130.00 |
| 91 | Light pole, conventional, AT15B40 (625E10490) | EACH | 6 | $4,025.00 | $4,025.00 |
| 92 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 6 | $2,800.00 | $2,800.00 |
| 93 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 402 | $3.50 | $3.50 |
| 94 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,006 | $3.00 | $3.00 |
| 95 | 1-1/2" duct cable with two no. 4 AWG 2400 volt cables (625E24100) | FT | 648 | $15.00 | $15.00 |
| 96 | Conduit, 3", 725.04 (625E25500) | FT | 181 | $41.00 | $41.00 |
| 97 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 6 | $525.00 | $525.00 |
| 98 | Trench, 24" deep (625E29002) | FT | 765 | $9.00 | $9.00 |
| 99 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $1,450.00 | $1,450.00 |
| 100 | Pull box removed (625E31510) | EACH | 2 | $250.00 | $250.00 |
| 101 | Ground rod (625E32000) | EACH | 6 | $350.00 | $350.00 |
| 102 | Underground warning marking tape (625E36010) | FT | 765 | $1.00 | $1.00 |
| 103 | Special - maintain existing lighting (625E40000) | LS | 1 | $28,000 | $23,000 |
| 104 | Special - replacement of existing lighting unit (625E40010) | EACH | 1 | $3,900.00 | $3,900.00 |
| 105 | Light pole removed (625E75400) | EACH | 8 | $350.00 | $350.00 |
| 106 | Light pole foundation removed (625E75500) | EACH | 8 | $350.00 | $350.00 |
| 107 | Luminaire removed (625E75506) | EACH | 8 | $60.00 | $60.00 |
| 108 | Disconnect circuit (625E75800) | EACH | 4 | $400.00 | $400.00 |
| 109 | Lighting, misc.: 13" X 24" pull box (mis-54) (625E98000) | EACH | 2 | $1,100.00 | $1,100.00 |
| 110 | Lighting, misc.: aluminum, 12' bracket, T-base, 30 (625E98000) | EACH | 1 | $3,500.00 | $3,500.00 |
| 111 | Lighting, misc.: aluminum, 8' bracket, T-base, 30' (625E98000) | EACH | 1 | $3,375.00 | $3,375.00 |
| 112 | Lighting, misc.: foundation removal (mis-900) (625E98000) | EACH | 3 | $350.00 | $350.00 |
| 113 | Lighting, misc.: luminaire, LED, cobra head (mis-8 (625E98000) | EACH | 2 | $625.00 | $625.00 |
| 114 | Lighting, misc.: mis-201 street light foundation, (625E98000) | EACH | 2 | $2,100.00 | $2,100.00 |
| 115 | Lighting, misc.: pole to BE wired, 2-wire, (mis-50 (625E98000) | EACH | 3 | $700.00 | $700.00 |
| 116 | Lighting, misc.: 2" conduit, concrete encased (mis (625E98100) | FT | 384 | $36.00 | $36.00 |
| 117 | Lighting, misc.: mis-702 3" rigid steel with 2" CO (625E98100) | FT | 113 | $75.00 | $75.00 |
| 118 | Lighting, misc.: underground circuit, 2 wire (mis- (625E98100) | FT | 548 | $8.00 | $8.00 |
| 119 | Lighting, misc.: existing underground system remov (625E98200) | LS | 1 | $1,450.00 | $1,450.00 |
| 120 | Lighting, misc.: maintain existing and temporary L (625E98200) | LS | 1 | $16,000 | $16,000 |
| 121 | RPM (621E00100) | EACH | 164 | $52.00 | $51.00 |
| 122 | Barrier reflector, type 1, bidirectional (626E00102) | EACH | 16 | $14.90 | $12.50 |
| 123 | Barrier reflector, type 1, one-way (626E00102) | EACH | 3 | $15.00 | $12.50 |
| 124 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 3 | $16.00 | $12.50 |
| 125 | Ground mounted support, no. 2 post (630E02100) | FT | 76 | $18.00 | $23.00 |
| 126 | Ground mounted support, no. 3 post (630E03100) | FT | 94.40 | $20.00 | $24.00 |
| 127 | Ground mounted support, no. 4 post (630E04100) | FT | 66.70 | $25.00 | $28.00 |
| 128 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 66.60 | $40.00 | $25.00 |
| 129 | One way support, no. 3 post (630E08004) | FT | 57 | $20.50 | $23.50 |
| 130 | Sign post reflector (630E08600) | EACH | 18 | $45.00 | $50.00 |
| 131 | Breakaway structural beam connection (630E09000) | EACH | 4 | $635.00 | $310.00 |
| 132 | Sign attachment assembly (630E75000) | EACH | 6 | $855.00 | $861.00 |
| 133 | Sign hanger assembly, span wire (630E79000) | EACH | 3 | $525.00 | $638.00 |
| 134 | Sign support assembly, pole mounted (630E79500) | EACH | 4 | $285.00 | $165.00 |
| 135 | Sign support assembly, barrier mounted (630E79610) | EACH | 1 | $1,825.00 | $1,446.00 |
| 136 | Sign, flat sheet (630E80100) | SF | 270 | $21.00 | $25.00 |
| 137 | Sign, flat sheet, as per plan (630E80101) | SF | 14 | $35.00 | $68.00 |
| 138 | Sign, ground mounted extrusheet (630E80200) | SF | 55 | $28.00 | $28.00 |
| 139 | Sign, overhead extrusheet (630E80224) | SF | 288 | $28.00 | $28.00 |
| 140 | Sign, temporary overlay (630E80300) | SF | 185 | $36.00 | $32.00 |
| 141 | Covering of sign (630E83000) | SF | 56 | $30.00 | $25.00 |
| 142 | Ground mounted structural beam support foundation (630E84500) | EACH | 4 | $1,485.00 | $1,000.00 |
| 143 | Removal of ground mounted sign and disposal (630E84900) | EACH | 5 | $15.00 | $25.00 |
| 144 | Removal of ground mounted sign and reerection (630E85100) | EACH | 1 | $65.00 | $350.00 |
| 145 | Removal of ground mounted post support and disposal (630E86002) | EACH | 6 | $20.00 | $25.00 |
| 146 | Removal of ground mounted structural beam support (630E86102) | EACH | 2 | $365.00 | $400.00 |
| 147 | Removal of ground mounted pipe support and disposal (630E86272) | EACH | 1 | $95.00 | $400.00 |
| 148 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 6 | $595.00 | $400.00 |
| 149 | Removal of pole mounted sign and disposal (630E87500) | EACH | 5 | $55.00 | $25.00 |
| 150 | Removal of temporary overlay sign and disposal (630E89894) | EACH | 13 | $345.00 | $450.00 |
| 151 | Signing, misc.:traffic signal signs (630E97700) | EACH | 1 | $325.00 | $1,100.00 |
| 152 | Signing, misc.:wayfinding ground mounted support, (630E97700) | EACH | 2 | $1,950.00 | $2,000.00 |
| 153 | Signing, misc.:wayfinding sign (630E97800) | SF | 6.20 | $350.00 | $100.00 |
| 154 | Edge line, 6" (644E00104) | MI | 0.04 | $6,500.00 | $10,000 |
| 155 | Lane line, 6" (644E00204) | MI | 0.22 | $4,000.00 | $3,510.00 |
| 156 | Center line (644E00300) | MI | 0.21 | $10,300 | $12,950 |
| 157 | Channelizing line, 12" (644E00404) | FT | 46 | $3.00 | $4.00 |
| 158 | Stop line (644E00500) | FT | 118 | $8.00 | $9.50 |
| 159 | Transverse/diagonal line (644E00700) | FT | 244 | $8.00 | $9.50 |
| 160 | Chevron marking (644E00720) | FT | 276 | $7.00 | $9.50 |
| 161 | Lane arrow (644E01300) | EACH | 32 | $125.00 | $120.00 |
| 162 | Wrong way arrow (644E01360) | EACH | 2 | $150.00 | $230.00 |
| 163 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 0.78 | $6,000.00 | $7,950.00 |
| 164 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 0.65 | $2,000.00 | $3,100.00 |
| 165 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 3,497 | $3.50 | $2.90 |
| 166 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 1,308 | $2.50 | $1.50 |
| 167 | Interstate elongated route shield symbol marking, type B125 (814E00010) | EACH | 1 | $1,800.00 | $4,500.00 |
| 168 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 1.43 | $1,700.00 | $2,550.00 |
| 169 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 1,308 | $1.50 | $1.15 |
| 170 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,497 | $2.00 | $1.75 |
| 171 | Ground rod (625E32000) | EACH | 4 | $325.00 | $325.00 |
| 172 | Vehicular signal head, (LED), 3-section, 12" lens, 1-way, polycarbonate (632E05006) | EACH | 8 | $900.00 | $900.00 |
| 173 | Covering of vehicular signal head (632E25000) | EACH | 8 | $35.00 | $35.00 |
| 174 | Messenger wire, 7 strand, 7/16" diameter with accessories (632E30300) | FT | 435 | $19.20 | $19.20 |
| 175 | Tether wire, with accessories (632E30600) | FT | 435 | $26.00 | $26.00 |
| 176 | Signal cable, 7 conductor, no. 14 AWG (632E40700) | FT | 478 | $3.50 | $3.50 |
| 177 | Strain pole foundation (632E64000) | EACH | 4 | $18,250 | $18,250 |
| 178 | Strain pole, misc.:type 4170, design 11 (632E83600) | EACH | 4 | $13,500 | $13,500 |
| 179 | Removal of traffic signal installation (632E90100) | EACH | 1 | $3,500.00 | $3,500.00 |
| 180 | Signalization, misc.:foundation pre-excavation (632E90400) | EACH | 1 | $3,800.00 | $3,800.00 |
| 181 | Signalization, misc.:stop line radar detection (632E90400) | EACH | 1 | $9,300.00 | $9,300.00 |
| 182 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 136 | $125.00 | $110.00 |
| 183 | Special - work zone traffic signal (614E11300) | EACH | 1 | $31,500 | $25,000 |
| 184 | Increased barrier delineation (614E11630) | FT | 2,704 | $1.85 | $0.75 |
| 185 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 3 | $2,920.00 | $2,200.00 |
| 186 | Detour signing (614E12420) | LS | 1 | $16,000 | $43,000 |
| 187 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 536 | $70.00 | $48.00 |
| 188 | Barrier reflector, type 1, one way (614E13310) | EACH | 26 | $11.00 | $15.00 |
| 189 | Barrier reflector, type 2, one way (614E13312) | EACH | 20 | $20.00 | $15.00 |
| 190 | Object marker, one way (614E13350) | EACH | 90 | $21.00 | $20.00 |
| 191 | Portable changeable message sign, as per plan (614E18601) | SNMT | 28 | $1,200.00 | $800.00 |
| 192 | Work zone lane line, class I, 6" (614E20010) | MI | 0.19 | $7,000.00 | $675.00 |
| 193 | Work zone center line, class I (614E21000) | MI | 0.17 | $7,300.00 | $2,532.00 |
| 194 | Work zone edge line, class I, 6" (614E22010) | MI | 0.25 | $7,100.00 | $1,479.00 |
| 195 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 1.22 | $4,200.00 | $2,921.00 |
| 196 | Work zone channelizing line, class I, 12", 807 paint (614E23110) | FT | 6,857 | $1.10 | $1.45 |
| 197 | Work zone dotted line, class I (614E24000) | FT | 74 | $1.00 | $0.50 |
| 198 | Work zone transverse/diagonal line, class I (614E25000) | FT | 268 | $12.00 | $1.35 |
| 199 | Work zone stop line, class I (614E26000) | FT | 81 | $12.00 | $3.60 |
| 200 | Work zone gore marking, class II (614E28000) | FT | 87 | $10.00 | $1.40 |
| 201 | Work zone arrow, class I (614E30000) | EACH | 22 | $80.00 | $115.00 |
| 202 | Pavement for maintaining traffic, class A (615E20000) | SY | 81 | $280.00 | $190.00 |
| 203 | Water (616E10000) | MGAL | 53 | $95.00 | $70.00 |
| 204 | Portable barrier, unanchored (622E41100) | FT | 2,600 | $26.00 | $30.00 |
| 205 | Sealing of concrete surfaces (512E10000) | SY | 1,796 | $13.50 | $15.00 |
| 206 | Unclassified excavation (503E21300) | LS | 1 | $50,000 | $42,500 |
| 207 | Pile driving equipment mobilization (505E11100) | LS | 1 | $16,000 | $27,000 |
| 208 | Steel piles HP12X53, furnished (507E00200) | FT | 1,770 | $51.50 | $67.00 |
| 209 | Prebored holes (507E92200) | FT | 175 | $370.00 | $325.00 |
| 215 | Porous backfill with geotextile fabric (518E21200) | CY | 219 | $138.00 | $190.00 |
| 216 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $30,150 | $34,468 |
| 217 | CPM progress schedule (108E10000) | LS | 1 | $11,400 | $8,500.00 |
| 218 | Maintaining traffic (614E11000) | LS | 1 | $130,000 | $225,000 |
| 219 | Field office, type B (619E16010) | MNTH | 9 | $2,500.00 | $5,000.00 |
| 220 | Construction layout stakes and surveying (623E10000) | LS | 1 | $82,000 | $77,500 |
| 221 | Mobilization (624E10000) | LS | 1 | $260,000 | $290,800 |
| 300 | Interconnect cable, misc.:, cat 5E cable, outdoor (632E62810) | FT | 42 | $2.50 | $2.50 |
| 301 | Interconnect, misc.:, spread spectrum radio assemb (632E62820) | EACH | 1 | $1,500.00 | $1,500.00 |
| 302 | Steel piles HP12X53, driven (507E00250) | FT | 1,136 | $77.50 | $62.00 |
| 303 | Special - retaining wall, precast concrete lagging (530E51010) | SF | 2,695 | $45.00 | $57.00 |
| 304 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.29 | $7,000.00 | $586.00 |
| 305 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.21 | $7,300.00 | $1,689.00 |
| 306 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.60 | $7,100.00 | $1,095.00 |
| 307 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 2,858 | $1.10 | $0.75 |
| 308 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 1,308 | $1.00 | $0.50 |
| 309 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 520 | $9.00 | $1.15 |
| 310 | Work zone stop line, class III, 642 paint (614E26610) | FT | 118 | $12.00 | $3.30 |
| 311 | Work zone arrow, class III, 642 paint (614E30650) | EACH | 34 | $80.00 | $110.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of April 23, 2026. Compiled by Mirage Metrics.