ODOT contract 260398 bid tabulation
HAM-IR 75-07.85 (MAJOR WIDENING). Let by Ohio DOT on October 8, 2026, HAM. 1 bid received; low bid $199,003,213 by John R Jurgensen Company, +35% against the engineer's estimate of $146,875,000.
- Owner
- Ohio DOT
- Letting
- 08 OCT 2026
- Pay items
- 703
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $199,003,213 | Low | +35% |
Engineer's estimate: $146,875,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company |
|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $462,046 |
| 2 | Headwall removed (202E20010) | EACH | 2 | $5,092.33 |
| 3 | Pavement removed, as per plan (202E23001) | SY | 114,234 | $16.64 |
| 4 | Wearing course removed (202E23500) | SY | 114,234 | $7.94 |
| 5 | Walk removed (202E30000) | SF | 9,358 | $4.82 |
| 6 | Concrete barrier removed (202E30700) | FT | 10,796 | $42.26 |
| 7 | Curb removed (202E32000) | FT | 7,733 | $8.87 |
| 8 | Gutter removed (202E32600) | FT | 354 | $19.39 |
| 9 | Pipe removed, 24" and under (202E35100) | FT | 4,704 | $35.65 |
| 10 | Pipe removed, over 24" diameter (202E35200) | FT | 1,450 | $114.54 |
| 11 | Guardrail removed (202E38000) | FT | 8,349 | $8.42 |
| 12 | Manhole removed (202E58000) | EACH | 22 | $1,507.24 |
| 13 | Catch basin removed (202E58100) | EACH | 40 | $1,012.94 |
| 14 | Inlet removed (202E58200) | EACH | 14 | $1,424.17 |
| 15 | Inlet abandoned (202E58400) | EACH | 7 | $2,330.15 |
| 16 | Inlet abandoned, as per plan (202E58401) | EACH | 1 | $11,423 |
| 17 | Catch basin abandoned (202E58500) | EACH | 8 | $1,001.35 |
| 18 | Manhole abandoned (202E58700) | EACH | 18 | $1,744.86 |
| 19 | Manhole abandoned, as per plan (202E58701) | EACH | 1 | $17,295 |
| 20 | Special - fill and plug existing conduit (202E70000) | FT | 6,327 | $152.99 |
| 21 | Fence removed (202E75000) | FT | 10,719 | $12.03 |
| 22 | Removal misc.: drainage structure abandoned, as PE (202E98100) | EACH | 56 | $1,386.20 |
| 23 | Removal misc.: abandoned water line (202E98200) | FT | 230 | $56.13 |
| 24 | Removal misc.: drainage pipe abandoned, as per pla (202E98200) | FT | 1,824 | $52.76 |
| 25 | Excavation (203E10000) | CY | 125,629 | $22.81 |
| 26 | Excavation, as per plan (203E10001) | CY | 73 | $534.41 |
| 27 | Embankment (203E20000) | CY | 144,041 | $25.23 |
| 28 | Subgrade compaction (204E10000) | SY | 1,843 | $5.89 |
| 29 | Proof rolling (204E45000) | HR | 92 | $288.19 |
| 30 | Cement (206E10500) | TON | 4,902 | $270.46 |
| 31 | Curing coat (206E11000) | SY | 162,367 | $1.60 |
| 32 | Cement stabilized subgrade, 14 inches deep (206E15020) | SY | 162,367 | $8.94 |
| 33 | Mixture design for chemically stabilized soils (206E30000) | LS | 1 | $104,679 |
| 34 | 1" preformed expansion joint filler (516E13600) | SF | 1,257 | $11.13 |
| 35 | Guardrail, type MGS (606E15050) | FT | 7,453 | $37.30 |
| 36 | Guardrail, type MGS with long posts (606E15100) | FT | 75 | $45.72 |
| 37 | Anchor assembly, MGS type E (606E26150) | EACH | 12 | $3,399.07 |
| 38 | Anchor assembly, MGS type T (606E26550) | EACH | 5 | $1,804.82 |
| 39 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 15 | $3,368.99 |
| 40 | MGS bridge terminal assembly, type 2 (606E35102) | EACH | 9 | $451.20 |
| 41 | Fence, type CLT (607E23000) | FT | 13,863 | $39.71 |
| 42 | Fenceline seeding and mulching (607E70000) | FT | 13,863 | $1.07 |
| 43 | 4" concrete walk (608E10000) | SF | 15,435 | $21.70 |
| 44 | Curb ramp (608E52000) | SF | 841 | $52.01 |
| 45 | Concrete barrier, single slope, type B1 (622E10100) | FT | 5,151 | $266.21 |
| 46 | Concrete barrier, single slope, type B1, as per plan (622E10101) | FT | 85 | $633.19 |
| 47 | Concrete barrier, single slope, type C1 (622E10140) | FT | 1,957 | $278.24 |
| 48 | Concrete barrier, single slope, type C1, as per plan (622E10141) | FT | 158 | $885.86 |
| 49 | Concrete barrier, single slope, type D (622E10160) | FT | 3,906 | $126.34 |
| 50 | Barrier transition (622E10200) | EACH | 1 | $11,431 |
| 51 | Concrete barrier end section, type D (622E25000) | EACH | 19 | $9,979.78 |
| 52 | Concrete barrier, end anchorage, reinforced, type B1 (622E25006) | EACH | 48 | $8,708.95 |
| 53 | Concrete barrier, end anchorage, reinforced, type B1, as per plan (622E25007) | EACH | 7 | $7,445.21 |
| 54 | Concrete barrier, end anchorage, reinforced, type C1 (622E25014) | EACH | 16 | $8,708.88 |
| 55 | Concrete barrier, end anchorage, reinforced, type C1, as per plan (622E25015) | EACH | 4 | $9,616.73 |
| 56 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 39 | $6,550.69 |
| 57 | Concrete barrier, end anchorage, reinforced, type D, as per plan (622E25051) | EACH | 3 | $6,009.24 |
| 58 | Barrier reflector, type 1, 1 way (626E00102) | EACH | 273 | $14.98 |
| 59 | Barrier reflector, type 2, 1 way (626E00110) | EACH | 81 | $16.84 |
| 60 | Special - work involving water (690E65020) | GAL | 10,000 | $3.61 |
| 61 | Special - work involving non-regulated water (690E65022) | GAL | 15,000 | $2.41 |
| 62 | Special - asbestos abatement friable material, SFN (690E70100) | SF | 50 | $54.14 |
| 63 | Special - asbestos abatement friable material, SFN (690E70100) | SF | 50 | $54.14 |
| 64 | Special - asbestos abatement friable material, SFN (690E70100) | SF | 50 | $54.14 |
| 65 | Special - asbestos abatement friable material, SFN (690E70100) | SF | 50 | $54.14 |
| 66 | Special - asbestos abatement non-friable material, (690E70100) | SF | 160 | $14.44 |
| 67 | Special - asbestos abatement non-friable material, (690E70100) | SF | 160 | $14.44 |
| 68 | Special - asbestos abatement non-friable material, (690E70100) | SF | 160 | $14.44 |
| 69 | Special - asbestos abatement non-friable material, (690E70100) | SF | 160 | $14.44 |
| 70 | Special - asbestos abatement pipe, SFN 3110036 (690E70120) | FT | 260 | $14.44 |
| 71 | Special - asbestos abatement pipe, SFN 3110087 (690E70120) | FT | 260 | $14.44 |
| 72 | Special - asbestos abatement pipe, SFN 3110176 (690E70120) | FT | 260 | $14.44 |
| 73 | Special - asbestos abatement pipe, SFN 3113779 (690E70120) | FT | 260 | $14.44 |
| 74 | Special - asbestos inspection (690E71050) | EACH | 4 | $2,647.06 |
| 75 | Special - contaminated material inspection and tes (690E98400) | LS | 1 | $44,519 |
| 76 | Special - misc.: drainage system cleaning, 36" and (690E98600) | HR | 200 | $893.30 |
| 77 | Special - misc.: drainage system cleaning, over 36 (690E98600) | HR | 100 | $1,043.70 |
| 78 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $1,695,430 |
| 79 | Tied concrete block mat with type 1 underlayment (601E21050) | SY | 22 | $147.42 |
| 80 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 47 | $143.54 |
| 81 | Rock channel protection, type C with filter (601E32200) | CY | 11 | $482.68 |
| 82 | Paved gutter, type 1-2 (601E37500) | FT | 110 | $239.35 |
| 83 | Soil analysis test (659E00100) | EACH | 2 | $150.40 |
| 84 | Topsoil (659E00300) | CY | 10,306 | $5.66 |
| 85 | Seeding and mulching (659E10000) | SY | 92,843 | $1.07 |
| 86 | Repair seeding and mulching (659E14000) | SY | 4,643 | $1.07 |
| 87 | Inter-seeding (659E15000) | SY | 4,643 | $1.07 |
| 88 | Commercial fertilizer (659E20000) | TON | 12.90 | $902.41 |
| 89 | Lime (659E31000) | ACRE | 19.19 | $12.03 |
| 90 | Water (659E35000) | MGAL | 527 | $1.20 |
| 91 | Mowing (659E40000) | MSF | 209 | $13.96 |
| 92 | Ditch erosion protection (670E00700) | SY | 6,334 | $3.01 |
| 93 | Storm water pollution prevention plan (832E15000) | LS | 1 | $14,439 |
| 94 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $84,441 |
| 95 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $50,723 |
| 96 | Erosion control (832E30000) | EACH | 698,286 | $1.00 |
| 97 | Concrete masonry (602E20000) | CY | 11 | $4,596.68 |
| 98 | 6" shallow pipe underdrains (605E11100) | FT | 39,512 | $26.89 |
| 99 | 6" unclassified pipe underdrains (605E13300) | FT | 2,666 | $45.85 |
| 100 | 6" base pipe underdrains (605E14000) | FT | 32,697 | $23.42 |
| 101 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 4,500 | $57.79 |
| 102 | 6" conduit, type B (611E00900) | FT | 100 | $125.62 |
| 103 | 6" conduit, type C (611E01100) | FT | 100 | $125.62 |
| 104 | 6" conduit, type E (611E01400) | FT | 100 | $120.77 |
| 105 | 6" conduit, type F (611E01500) | FT | 100 | $120.77 |
| 106 | 15" conduit, type B (611E05900) | FT | 198 | $174.70 |
| 107 | 15" conduit, type B, as per plan (611E05901) | FT | 4,091 | $197.67 |
| 108 | 15" conduit, type C (611E06100) | FT | 505 | $190.37 |
| 109 | 15" conduit, type C (611E06100) | FT | 66 | $200.82 |
| 110 | 15" conduit, type F (611E06700) | FT | 290 | $220.23 |
| 111 | 18" conduit, type B, as per plan (611E07401) | FT | 2,749 | $214.27 |
| 112 | 18" conduit, type C (611E07600) | FT | 247 | $241.79 |
| 113 | 21" conduit, type B, as per plan (611E08901) | FT | 201 | $313.93 |
| 114 | 21" conduit, type C (611E09100) | FT | 55 | $326.70 |
| 115 | 24" conduit, type B, as per plan (611E10401) | FT | 585 | $275.79 |
| 116 | 24" conduit, type C (611E10600) | FT | 773 | $316.25 |
| 117 | 24" conduit, type C (611E10600) | FT | 21 | $1,041.30 |
| 118 | 30" conduit, type B, as per plan (611E13401) | FT | 402 | $370.92 |
| 119 | 30" conduit, type C (611E13600) | FT | 576 | $359.90 |
| 120 | 36" conduit, type B, as per plan (611E16401) | FT | 464 | $471.31 |
| 121 | 36" conduit, type C (611E16600) | FT | 1,148 | $572.06 |
| 122 | 36" conduit, type C (611E16600) | FT | 226 | $981.37 |
| 123 | 42" conduit, type B, as per plan (611E19401) | FT | 929 | $617.84 |
| 124 | 42" conduit, type C (611E19600) | FT | 340 | $1,037.69 |
| 125 | Conduit, misc.: conduit installed with trenchless (611E97400) | FT | 380 | $2,171.73 |
| 126 | Conduit, misc.: conduit installed with trenchless (611E97400) | FT | 192 | $2,619.72 |
| 127 | Conduit, misc.: conduit installed with trenchless (611E97400) | FT | 167 | $2,829.44 |
| 128 | Conduit, misc.: conduit installed with trenchless (611E97400) | FT | 340 | $4,475.27 |
| 129 | Catch basin, no. 3 (611E98150) | EACH | 1 | $6,769.73 |
| 130 | Catch basin, no. 3A (611E98180) | EACH | 12 | $5,147.00 |
| 131 | Catch basin, no. 4 (611E98230) | EACH | 3 | $14,156 |
| 132 | Catch basin, no. 5 (611E98300) | EACH | 3 | $7,916.07 |
| 133 | Catch basin, no. 5A (611E98344) | EACH | 3 | $11,973 |
| 134 | Catch basin, no. 6 (611E98370) | EACH | 1 | $4,907.54 |
| 135 | Catch basin, no. 8 (611E98410) | EACH | 16 | $7,022.57 |
| 136 | Catch basin, no. 8A (611E98434) | EACH | 2 | $13,925 |
| 137 | Catch basin, no. 2-2B (611E98470) | EACH | 1 | $4,464.77 |
| 138 | Catch basin adjusted to grade (611E98630) | EACH | 1 | $1,291.04 |
| 139 | Inlet, no. 3 for single slope barrier, type B1 (611E99100) | EACH | 9 | $30,571 |
| 140 | Inlet, no. 3 for single slope barrier, type B1, as per plan (611E99101) | EACH | 2 | $22,530 |
| 141 | Inlet, no. 3 for single slope barrier, type B1, as per plan (611E99101) | EACH | 10 | $29,451 |
| 142 | Inlet, no. 3 for single slope barrier, type C1 (611E99110) | EACH | 2 | $29,181 |
| 143 | Inlet, no. 3 for single slope barrier, type C1, as per plan (611E99111) | EACH | 8 | $12,664 |
| 144 | Inlet, no. 3 for single slope barrier, type D (611E99114) | EACH | 30 | $26,098 |
| 145 | Inlet, no. 3 for single slope barrier, type D, as per plan (611E99115) | EACH | 5 | $30,440 |
| 146 | Inlet adjusted to grade (611E99150) | EACH | 1 | $1,582.72 |
| 147 | Manhole, no. 3 (611E99574) | EACH | 32 | $14,581 |
| 148 | Manhole adjusted to grade (611E99654) | EACH | 7 | $1,291.05 |
| 149 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $6,455.21 |
| 150 | Precast reinforced concrete outlet (611E99710) | EACH | 11 | $804.98 |
| 151 | Special - miscellaneous metal (611E99820) | LB | 1,000 | $4.21 |
| 152 | Drainage structure, misc.: check valve for 24" con (611E99900) | EACH | 1 | $20,871 |
| 153 | Drainage structure, misc.: check valve for 36'' CO (611E99900) | EACH | 2 | $35,433 |
| 154 | 30" steel pipe encasement, open cut (638E06712) | FT | 72 | $567.41 |
| 155 | 48" steel pipe encasement, bored or jacked (638E07320) | FT | 211 | $6,425.35 |
| 156 | Special - stormwater detention system 1 (690E98400) | LS | 1 | $2,427,674 |
| 157 | Special - stormwater detention system 2 (690E98400) | LS | 1 | $938,925 |
| 158 | Special - stormwater detention system 3 (690E98400) | LS | 1 | $1,898,318 |
| 159 | Pavement planing, asphalt concrete, 1.5" depth (254E01000) | SY | 30,877 | $6.42 |
| 160 | Pavement planing, asphalt concrete, variable depth (254E01000) | SY | 3,216 | $15.38 |
| 161 | Full depth pavement removal and rigid replacement, type 1, class QC MS (255E15000) | SY | 494 | $351.66 |
| 162 | Asphalt concrete base, PG64-22, (449) (302E56000) | CY | 42,804 | $265.36 |
| 163 | Aggregate base (304E20000) | CY | 45,491 | $112.45 |
| 164 | Non-tracking tack coat (407E20000) | GAL | 26,622 | $5.00 |
| 165 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 134 | $369.52 |
| 166 | Asphalt concrete intermediate course, type 1, (448) (441E50200) | CY | 94 | $426.25 |
| 167 | Anti-segregation equipment (442E00100) | CY | 15,155 | $13.50 |
| 168 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 7,451 | $275.81 |
| 169 | Asphalt concrete surface course, 12.5 MM, type A (447), as per plan (442E10301) | CY | 7,620 | $375.23 |
| 170 | 8" non-reinforced concrete pavement, class QC 1P (452E12010) | SY | 47 | $274.42 |
| 171 | 13" non-reinforced concrete pavement, class QC 1P (452E16010) | SY | 4,293 | $190.73 |
| 172 | Curb, type 2-A (609E14000) | FT | 37 | $52.78 |
| 173 | Curb, type 4-C, as per plan (609E24511) | FT | 4,150 | $48.78 |
| 174 | Curb, type 6 (609E26000) | FT | 1,775 | $56.28 |
| 175 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 8.42 | $2,063.51 |
| 176 | Excavation, as per plan (203E10001) | CY | 5 | $154.56 |
| 177 | Excavation, as per plan (203E10001) | CY | 5 | $348.09 |
| 178 | Uncoated steel reinforcement (509E25000) | LB | 216 | $4.74 |
| 179 | Concrete masonry, as per plan (602E20001) | CY | 2 | $1,730.36 |
| 180 | Masonry, misc.: brick masonry, (cin. 602) (602E98200) | CY | 1 | $1,477.55 |
| 181 | Special - 6" water main dip and fittings, furnishi (638E11602) | FT | 19 | $802.14 |
| 182 | Special - 8" water main dip and fittings, furnishi (638E11604) | FT | 145 | $363.07 |
| 183 | Special - 12" water main dip and fittings, furnish (638E11608) | FT | 5 | $2,995.20 |
| 184 | Special - 16" water main dip and fittings, furnish (638E11610) | FT | 20 | $1,562.93 |
| 185 | Special - valve box, furnishing and installing VA (638E20498) | EACH | 3 | $1,376.92 |
| 186 | Special - valve box adjusted to grade, (cin. 1125) (638E20500) | EACH | 8 | $850.90 |
| 187 | Special - 6" fire hydrant, furnishing and installi (638E20750) | EACH | 2 | $7,133.70 |
| 188 | Special - fire hydrant removed and disposed of, (C (638E20760) | EACH | 2 | $853.02 |
| 189 | Special - fire hydrant service line extended and adjusted to grade (638E20762) | EACH | 2 | $1,763.01 |
| 191 | Special - service box, furnishing and installing C (638E20904) | EACH | 1 | $1,040.90 |
| 192 | Special - sheeting and bracing ordered left in place (638E30002) | MBF | 1 | $2,114.74 |
| 193 | Water work, misc.: fire hydrant flow testing (exis (638E98000) | EACH | 1 | $412.84 |
| 194 | Water work, misc.: fire hydrant flow testing (new) (638E98000) | EACH | 2 | $412.83 |
| 195 | Water work, misc.: fire hydrant painting (existing (638E98000) | EACH | 1 | $1,074.33 |
| 196 | Water work, misc.: fire hydrant painting (new), (C (638E98000) | EACH | 2 | $1,074.37 |
| 197 | Water work, misc.: removing existing manhole curb (638E98000) | EACH | 1 | $772.82 |
| 198 | Water work, misc.: removing existing valve box, (C (638E98000) | EACH | 2 | $772.84 |
| 199 | Water work, misc.: resetting existing curb and roa (638E98000) | EACH | 2 | $676.61 |
| 200 | 8" conduit, type B (611E01800) | FT | 292 | $524.26 |
| 201 | 8" conduit, type C (611E02000) | FT | 100 | $726.41 |
| 202 | 42" conduit, type B (611E19400) | FT | 21 | $1,416.05 |
| 203 | 42" conduit, type C (611E19600) | FT | 60 | $1,547.39 |
| 204 | 60" conduit, type B (611E23800) | FT | 233 | $1,896.24 |
| 205 | Manhole, misc.: sanitary manhole adjust to grade P (611E99690) | EACH | 2 | $5,704.53 |
| 206 | Manhole, misc.: sanitary manhole per MSD STD acc. (611E99690) | EACH | 1 | $21,789 |
| 207 | Manhole, misc.: sanitary manhole per MSD STD acc. (611E99690) | EACH | 1 | $21,789 |
| 208 | Manhole, misc.: sanitary manhole per MSD STD acc. (611E99690) | EACH | 3 | $84,040 |
| 209 | Manhole, misc.: sanitary manhole per MSD STD acc. (611E99690) | EACH | 1 | $61,324 |
| 210 | Junction box removed (202E62000) | EACH | 1 | $327.27 |
| 211 | Connection, fused pull apart (625E00450) | EACH | 88 | $205.75 |
| 212 | Connection, fused pull apart, as per plan (625E00451) | EACH | 14 | $250.27 |
| 213 | Connection, unfused permanent (625E00480) | EACH | 48 | $172.06 |
| 214 | Light pole, low mast, ALM50 (625E10494) | EACH | 38 | $4,873.00 |
| 215 | Light pole (installation only), as per plan (625E10503) | EACH | 9 | $1,233.29 |
| 216 | Light tower, BBBB100 (625E13200) | EACH | 5 | $39,104 |
| 217 | Light tower, BBBBBB100 (625E13400) | EACH | 6 | $39,369 |
| 218 | Light pole foundation, 24" X 6' deep, as per plan (625E14001) | EACH | 3 | $2,707.22 |
| 219 | Median light pole foundation, 10' deep (625E14306) | EACH | 42 | $9,821.21 |
| 220 | Median light pole foundation, 10' deep, as per plan (625E14307) | EACH | 2 | $12,571 |
| 221 | Light tower foundation, 36" X 20' deep (625E15100) | EACH | 4 | $11,190 |
| 222 | Light tower foundation, 36" X 25' deep (625E15200) | EACH | 4 | $12,513 |
| 223 | Light tower foundation, misc.:, median, 36" X 20' (625E15700) | EACH | 4 | $21,237 |
| 224 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 31,763 | $6.92 |
| 225 | No. 2 AWG 2400 volt distribution cable (625E23300) | FT | 2,496 | $8.72 |
| 226 | No. 10 AWG pole and bracket cable (625E23400) | FT | 6,600 | $3.31 |
| 227 | 1-1/2" duct cable with three no. 4 AWG 2400 volt cables (625E24320) | FT | 2,062 | $23.04 |
| 228 | Conduit, 3", 725.04 (625E25500) | FT | 1,227 | $39.59 |
| 229 | Conduit, 4", 725.051, as per plan (625E25605) | FT | 386 | $14.14 |
| 230 | Conduit, jacked or drilled, 725.052, 3" (625E25908) | FT | 1,320 | $58.96 |
| 231 | Luminaire, high mast, solid state (LED), as per plan (625E26263) | EACH | 62 | $1,333.16 |
| 232 | Luminaire, low mast, solid state (LED), as per plan (625E26273) | EACH | 12 | $1,216.45 |
| 233 | Luminaire, low mast, solid state (LED), as per plan (625E26273) | EACH | 26 | $1,293.45 |
| 234 | Luminaire, underpass, solid state (LED), as per plan (625E27503) | EACH | 7 | $1,293.45 |
| 235 | Luminaire, underpass, solid state (LED), as per plan (625E27503) | EACH | 7 | $1,383.69 |
| 236 | Luminaire, installation only, as per plan (625E27561) | EACH | 15 | $176.87 |
| 237 | Trench (625E29000) | FT | 3,077 | $17.03 |
| 238 | Transition junction box (625E29910) | EACH | 6 | $4,289.45 |
| 239 | Median junction box (625E29930) | EACH | 57 | $4,289.45 |
| 240 | Pull box, 725.08, 18" (625E30700) | EACH | 17 | $1,410.16 |
| 241 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $1,704.95 |
| 242 | Pull box removed (625E31510) | EACH | 45 | $327.27 |
| 243 | Ground rod (625E32000) | EACH | 152 | $398.26 |
| 244 | Structure grounding system (625E33000) | EACH | 6 | $11,551 |
| 245 | Power service, as per plan (625E34001) | EACH | 4 | $18,289 |
| 246 | RE-erect existing light tower, as per plan (625E35021) | EACH | 1 | $6,256.69 |
| 247 | Underground warning marking tape (625E36010) | FT | 3,077 | $2.35 |
| 248 | Service to underpass lighting, as per plan (625E37101) | EACH | 3 | $20,996 |
| 249 | High voltage test (625E38000) | LS | 1 | $12,694 |
| 250 | Special - maintain existing lighting (625E40000) | LS | 1 | $1,070,857 |
| 251 | Special - replacement of existing lighting unit (625E40010) | EACH | 2 | $8,422.48 |
| 252 | Light tower removed (625E75350) | EACH | 9 | $3,609.63 |
| 253 | Light pole removed (625E75400) | EACH | 37 | $902.41 |
| 254 | Light pole removed for storage (625E75402) | EACH | 3 | $1,203.21 |
| 255 | Light pole foundation removed (625E75500) | EACH | 40 | $2,408.82 |
| 256 | Luminaire removed for storage (625E75504) | EACH | 3 | $150.40 |
| 257 | Luminaire removed (625E75506) | EACH | 73 | $150.40 |
| 258 | Power service removed (625E75510) | EACH | 4 | $1,203.21 |
| 259 | Light tower foundation removed (625E75540) | EACH | 9 | $2,916.57 |
| 260 | Distribution cable removed, as per plan (625E75551) | FT | 42,580 | $0.96 |
| 261 | Disconnect circuit (625E75800) | EACH | 6 | $601.61 |
| 262 | Arc flash calculations and label, PS-A (625E76000) | EACH | 1 | $2,797.46 |
| 263 | Arc flash calculations and label, PS-B (625E76000) | EACH | 1 | $2,797.46 |
| 264 | Arc flash calculations and label, PS-C (625E76000) | EACH | 1 | $2,797.46 |
| 265 | Arc flash calculations and label, PS-F (625E76000) | EACH | 1 | $2,797.46 |
| 266 | Arc flash calculations and label, PS-G (625E76000) | EACH | 1 | $2,797.46 |
| 267 | Arc flash calculations and label, PS-H (625E76000) | EACH | 1 | $2,797.46 |
| 268 | Lighting, misc.: removal of underpass lighting (625E98000) | EACH | 3 | $2,256.02 |
| 269 | Lighting, misc.: removal of existing temporary lig (625E98200) | LS | 1 | $12,032 |
| 270 | Delineator, post ground mounted (620E00500) | EACH | 59 | $360.96 |
| 271 | Delineator, bracket mounted (620E11000) | EACH | 6 | $330.88 |
| 272 | Removal of delineator (620E31200) | EACH | 16 | $45.53 |
| 273 | Delineator, post surface mounted (620E60000) | EACH | 7 | $391.04 |
| 274 | RPM (621E00100) | EACH | 1,209 | $51.44 |
| 275 | Raised pavement marker removed (621E54000) | EACH | 755 | $19.80 |
| 276 | Ground rod (625E32000) | EACH | 18 | $398.26 |
| 277 | Ground mounted support, no. 3 post (630E03100) | FT | 1,163 | $20.45 |
| 278 | Ground mounted support, no. 4 post (630E04100) | FT | 48 | $36.10 |
| 279 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 97.20 | $31.28 |
| 280 | Ground mounted structural beam support, W6X9 (630E06500) | FT | 32.90 | $33.09 |
| 281 | Ground mounted structural beam support, W10X22 (630E07500) | FT | 47 | $67.98 |
| 282 | Ground mounted structural beam support, W12X30 (630E08000) | FT | 53.60 | $90.84 |
| 283 | One way support, no. 3 post (630E08004) | FT | 12 | $30.08 |
| 284 | Sign post reflector (630E08600) | EACH | 61 | $90.24 |
| 285 | Breakaway structural beam connection (630E09000) | EACH | 12 | $782.09 |
| 286 | Overhead sign support, type TC-12.31, design 12 (630E72340) | EACH | 5 | $54,566 |
| 287 | Overhead sign support, type TC-15.116, design 1 (630E72410) | EACH | 3 | $76,404 |
| 288 | Overhead sign support, type TC-15.116, design 3 (630E72430) | EACH | 4 | $158,824 |
| 289 | Sign attachment assembly (630E75000) | EACH | 12 | $571.53 |
| 290 | Sign, flat sheet (630E80100) | SF | 869.13 | $31.89 |
| 291 | Sign, ground mounted extrusheet (630E80200) | SF | 318 | $42.11 |
| 292 | Sign, overhead extrusheet (630E80224) | SF | 5,384.50 | $52.94 |
| 293 | Concrete median barrier sign bracket, as per plan (630E81021) | EACH | 18 | $782.09 |
| 294 | Concrete barrier median overhead sign support foundation, type TC-21.50 (630E84010) | EACH | 6 | $18,966 |
| 295 | Ground mounted structural beam support foundation (630E84500) | EACH | 12 | $2,045.46 |
| 296 | Rigid overhead sign support foundation (630E84510) | EACH | 12 | $12,694 |
| 297 | Removal of ground mounted sign and disposal (630E84900) | EACH | 72 | $78.21 |
| 298 | Removal of ground mounted major sign and disposal (630E85400) | EACH | 3 | $421.12 |
| 299 | Removal of ground mounted major sign and reerection (630E85600) | EACH | 1 | $2,105.62 |
| 300 | Removal of ground mounted post support and disposal (630E86002) | EACH | 58 | $150.40 |
| 301 | Removal of ground mounted structural beam support (630E86102) | EACH | 13 | $300.80 |
| 302 | Removal of overhead mounted sign and reerection (630E87100) | EACH | 2 | $2,406.42 |
| 303 | Removal of overhead mounted sign and disposal (630E87400) | EACH | 29 | $1,203.21 |
| 304 | Removal of pole mounted sign and disposal (630E87500) | EACH | 13 | $72.19 |
| 305 | Removal of overhead sign support and disposal, type TC-12.30 (630E89706) | EACH | 5 | $1,744.66 |
| 306 | Removal of overhead sign support and disposal, type TC-7.65 (630E89802) | EACH | 5 | $3,609.63 |
| 307 | Removal of temporary overlay sign and disposal (630E89894) | EACH | 10 | $1,203.21 |
| 308 | Removal of miscellaneous traffic control item, bar (630E89902) | EACH | 10 | $360.96 |
| 309 | Removal of miscellaneous traffic control item, par (630E89902) | EACH | 1 | $1,203.21 |
| 310 | Center line (644E00300) | MI | 0.18 | $12,080 |
| 311 | Stop line (644E00500) | FT | 25 | $10.05 |
| 312 | Crosswalk line, 12" (644E00620) | FT | 153 | $9.20 |
| 313 | Transverse/diagonal line (644E00700) | FT | 17 | $9.51 |
| 314 | Chevron marking (644E00720) | FT | 574 | $9.51 |
| 315 | Lane arrow (644E01300) | EACH | 11 | $300.80 |
| 316 | Lane reduction arrow (644E01350) | EACH | 2 | $421.13 |
| 317 | Wrong way arrow (644E01360) | EACH | 2 | $300.81 |
| 318 | Removal of pavement marking (644E30000) | FT | 1,652 | $3.37 |
| 319 | Edge line, 6", type A4 (645E00118) | MI | 0.58 | $39,375 |
| 320 | Lane line, 6", type A4 (645E00220) | MI | 0.56 | $20,713 |
| 321 | Channelizing line, 12", type A4 (645E00418) | FT | 412 | $11.73 |
| 322 | Dotted line, 6", type A4 (645E01522) | FT | 265 | $8.72 |
| 323 | Dotted line, 12", type A4 (645E01566) | FT | 394 | $9.02 |
| 324 | Chevron marking (646E10620) | FT | 40 | $165.14 |
| 325 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 10.78 | $8,572.87 |
| 326 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 10.77 | $4,421.80 |
| 327 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 10,346 | $3.31 |
| 328 | Wet reflective thermoplastic pavement marking, dotted line, 6" (807E14410) | FT | 5,933 | $1.62 |
| 329 | Wet reflective thermoplastic pavement marking, dotted line, 12" (807E14430) | FT | 10,795 | $1.93 |
| 330 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 21.55 | $3,248.67 |
| 331 | Grooving for 6" recessed pavement marking, (asphalt) (850E10110) | FT | 5,933 | $2.11 |
| 332 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 21,141 | $2.59 |
| 333 | Grooving for 6" recessed pavement marking, (concrete) (850E20010) | MI | 1.14 | $4,632.36 |
| 334 | Grooving for 6" recessed pavement marking, (concrete) (850E20110) | FT | 265 | $2.53 |
| 335 | Grooving for 12" recessed pavement marking, (concrete) (850E20130) | FT | 806 | $2.89 |
| 336 | Conduit, 2", 725.04 (625E25400) | FT | 38 | $29.96 |
| 337 | Conduit, 2", 725.051 (625E25408) | FT | 56 | $11.85 |
| 338 | Conduit, 3", 725.04 (625E25500) | FT | 463 | $45.90 |
| 339 | Conduit, 3", 725.051 (625E25504) | FT | 174 | $10.29 |
| 340 | Conduit, jacked or drilled, 725.04, 3" (625E25902) | FT | 305 | $132.35 |
| 341 | Trench (625E29000) | FT | 1,562 | $17.03 |
| 342 | Pull box, 725.08, 18" (625E30700) | EACH | 8 | $1,408.96 |
| 343 | Pull box removed (625E31510) | EACH | 47 | $300.80 |
| 344 | Ground rod (625E32000) | EACH | 13 | $398.26 |
| 345 | Underground warning marking tape (625E36010) | FT | 1,562 | $2.35 |
| 346 | Power service removed (625E75510) | EACH | 2 | $1,203.21 |
| 347 | Arc flash calculations and label, CCTV #113 (625E76000) | EACH | 1 | $2,797.46 |
| 348 | Arc flash calculations and label, CCTV #12 (625E76000) | EACH | 1 | $2,797.46 |
| 349 | Arc flash calculations and label, DMS #12 (625E76000) | EACH | 1 | $2,797.46 |
| 350 | Arc flash calculations and label, VDS (625E76000) | EACH | 1 | $2,797.46 |
| 351 | Overhead sign support, DMS truss, 115', as per plan (630E70021) | EACH | 1 | $141,738 |
| 352 | Catwalk, DMS truss, as per plan (630E70051) | EACH | 1 | $66,899 |
| 353 | Concrete barrier median overhead sign support foundation, DMS truss (630E70070) | EACH | 1 | $19,567 |
| 354 | Overhead sign support foundation, DMS truss (630E70080) | EACH | 1 | $12,874 |
| 355 | Removal of overhead sign support and disposal (630E89702) | EACH | 2 | $3,609.63 |
| 356 | Removal of wood pole and disposal (630E89812) | EACH | 5 | $601.61 |
| 357 | Power cable, 1 conductor, no. 2 AWG (632E69310) | FT | 1,048 | $8.00 |
| 358 | Power cable, misc.: 1 conductor, 1/0 AWG (632E69350) | FT | 3,498 | $10.65 |
| 359 | Conduit riser, 2" diameter (632E70400) | EACH | 1 | $1,263.37 |
| 360 | Signalization, misc.: removal of fiber optic cable (632E90300) | LS | 1 | $15,040 |
| 361 | Cabinet foundation, as per plan (633E67101) | EACH | 4 | $2,165.78 |
| 362 | Controller work pad, as per plan (633E67201) | EACH | 4 | $4,602.28 |
| 363 | Fiber optic cable, airblown/pushable, 72 fiber (804E21030) | FT | 17,288 | $5.53 |
| 364 | ITS JUNCTION BOX, 17x24x6 INCHES (809E00530) | EACH | 25 | $2,701.21 |
| 365 | ITS pull box with pad and standard lid assembly, 3 (809E01900) | EACH | 2 | $7,742.66 |
| 366 | ITS pull box with pad and hinged lid assembly, 32" wide, type 1 (809E01920) | EACH | 7 | $9,078.22 |
| 367 | Communication cable marker (809E11000) | EACH | 9 | $234.63 |
| 368 | Conduit, multicell, misc.: 2" HDPE with 4-14MM/10M (809E25000) | FT | 951 | $30.38 |
| 369 | Conduit, multicell, misc.: 2" HDPE with 4-14MM/10M (809E25000) | FT | 848 | $72.37 |
| 370 | Conduit, multicell, misc.: 2" HDPE with 4-14MM/10M (809E25000) | FT | 491 | $41.57 |
| 371 | Conduit, multicell, misc.: 4" HDPE (809E25000) | FT | 974 | $22.26 |
| 372 | Conduit, multicell, misc.: 4" HDPE, jacked or dril (809E25000) | FT | 848 | $54.26 |
| 373 | Conduit, multicell, misc.: 4" HDPE, on structure (809E25000) | FT | 491 | $47.95 |
| 374 | ITS power service, pole mounted, 120/240V, 60 amp (809E55000) | EACH | 2 | $5,715.25 |
| 375 | Ethernet cable, outdoor-rated (809E64550) | FT | 452 | $4.33 |
| 376 | ITS cabinet - ground mounted (809E65000) | EACH | 3 | $11,551 |
| 377 | ITS cabinet - DMS (809E65040) | EACH | 1 | $13,235 |
| 378 | ITS device, misc.: relocate CCTV camera and wirele (809E65990) | EACH | 1 | $5,805.49 |
| 379 | ITS device, misc.: relocate existing DMS (809E65990) | EACH | 1 | $22,644 |
| 380 | ITS device, misc.: removal of CCTV pole, camera, F (809E65990) | EACH | 1 | $12,032 |
| 381 | ITS device, misc.: removal of DMS sign (809E65990) | EACH | 1 | $9,385.04 |
| 382 | ITS device, misc.: removal of ITS cabinet assembly (809E65990) | EACH | 9 | $1,203.21 |
| 383 | ITS device, misc.: removal of side-fired radar veh (809E65990) | EACH | 5 | $601.61 |
| 384 | ITS device, misc.: removal of wireless radio equip (809E65990) | EACH | 9 | $601.61 |
| 385 | Maintaining ITS during construction (809E70000) | LS | 1 | $220,789 |
| 386 | As-built construction plans (809E70050) | LS | 1 | $193,589 |
| 387 | Stop line radar detection, as per plan (809E69101) | EACH | 1 | $13,356 |
| 388 | Structural steel, misc.: C10X15.3 (513E95000) | FT | 36 | $234.79 |
| 389 | Structural steel, misc.: L4X4X1/2 (513E95000) | FT | 5 | $379.13 |
| 390 | Structural steel, misc.: 5/8" dia. A325 bolts (513E95030) | EACH | 11 | $108.89 |
| 391 | Structural steel, misc.: 5/8" dia. threaded anchor (513E95030) | EACH | 19 | $117.51 |
| 392 | Special - noise barrier (reflective) (606E10210) | SF | 25,265 | $102.04 |
| 393 | Special - noise barrier (metal panels) (606E10920) | SF | 36 | $526.59 |
| 394 | Special - noise barrier (reflective), parapet moun (606E10920) | SF | 8,562 | $138.02 |
| 395 | Pavement repair, misc.: performed in 2027 (253E90000) | CY | 400 | $665.58 |
| 396 | Pavement repair, misc.: performed in 2028 (253E90000) | CY | 400 | $665.58 |
| 397 | Pavement repair, misc.: performed in 2029 (253E90000) | CY | 400 | $665.58 |
| 398 | Asphalt concrete intermediate course, type 1, (449), as per plan (441E70201) | CY | 408 | $348.23 |
| 399 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $140,296 |
| 400 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $245,854 |
| 401 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $493,056 |
| 402 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $166,960 |
| 403 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $21,857 |
| 404 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $451,667 |
| 405 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $449,611 |
| 406 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $616,069 |
| 407 | Impact attenuator, type 3 unidirectional (606E60040) | EACH | 2 | $57,355 |
| 408 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 2,100 | $136.77 |
| 409 | Special - work zone traffic signal (614E11300) | EACH | 3 | $21,056 |
| 410 | Increased barrier delineation (614E11630) | FT | 8,000 | $3.96 |
| 411 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 15 | $4,488.88 |
| 412 | Work zone impact attenuator, 24" wide hazards, (bidirectional) (614E12384) | EACH | 6 | $5,483.58 |
| 413 | Work zone impact attenuator, misc.: 24" wide hazar (614E12400) | EACH | 3 | $3,825.75 |
| 414 | Detour signing (614E12420) | LS | 1 | $524,367 |
| 415 | Work zone increased penalties sign (614E12484) | EACH | 11 | $264.23 |
| 416 | Replacement sign (614E12500) | EACH | 15 | $264.23 |
| 417 | Replacement drum (614E12600) | EACH | 150 | $128.67 |
| 418 | Work zone crossover lighting system (614E12756) | EACH | 2 | $55,348 |
| 419 | Work zone raised pavement marker (614E12800) | EACH | 200 | $29.97 |
| 420 | Work zone raised pavement marker, as per plan (614E12801) | EACH | 5,035 | $61.63 |
| 421 | Asphalt concrete for maintaining traffic (614E13000) | CY | 90 | $247.67 |
| 422 | Barrier reflector, type 1, bidirectional (614E13310) | EACH | 1,235 | $17.41 |
| 423 | Barrier reflector, type 2, bidirectional (614E13312) | EACH | 43 | $17.41 |
| 424 | Object marker, one way (614E13350) | EACH | 1,260 | $17.41 |
| 425 | Object marker, two way (614E13360) | EACH | 230 | $17.41 |
| 426 | Maintaining traffic, misc.: optimized traffic sign (614E18000) | EACH | 750,000 | $1.00 |
| 427 | Maintaining traffic, misc.: maintain existing ramp (614E18002) | LS | 1 | $1,000.00 |
| 428 | Maintaining traffic, misc.: maintain existing ramp (614E18002) | LS | 1 | $1,000.00 |
| 429 | Portable changeable message sign (614E18600) | SNMT | 320 | $1,197.19 |
| 430 | Work zone lane line, class I, 6", 807 paint (614E20056) | MI | 11.20 | $3,170.46 |
| 431 | Work zone lane line, class I, 6", 648 (614E20366) | MI | 2.10 | $4,566.19 |
| 432 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 11.33 | $679.81 |
| 433 | Work zone edge line, class I, 6", 807 paint (614E22056) | MI | 38.10 | $4,000.67 |
| 434 | Work zone edge line, class I, 6", 648 (614E22336) | MI | 5 | $7,628.35 |
| 435 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 11.34 | $1,275.40 |
| 436 | Work zone channelizing line, class I, 12", 807 paint (614E23110) | FT | 58,772 | $2.41 |
| 437 | Work zone channelizing line, class I, 8", 648 (614E23140) | FT | 2,825 | $3.61 |
| 438 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 10,758 | $1.50 |
| 439 | Work zone dotted line, class I, 6", 807 paint (614E24102) | FT | 19,999 | $1.99 |
| 440 | Work zone dotted line, class I, 6", 648 (614E24142) | FT | 1,290 | $3.31 |
| 441 | Work zone dotted line, class III, 6", 642 paint (614E24612) | FT | 17,387 | $1.44 |
| 442 | Work zone gore marking, class II, 642 paint (614E28200) | FT | 418 | $5.41 |
| 443 | Work zone arrow, class I, 642 paint (614E30200) | EACH | 11 | $246.66 |
| 444 | Roads for maintaining traffic (615E10000) | LS | 1 | $411,220 |
| 445 | Roads for maintaining traffic, as per plan (615E10001) | LS | 1 | $50,227 |
| 446 | Pavement for maintaining traffic, class A (615E20000) | SY | 958 | $185.75 |
| 447 | Pavement for maintaining traffic, class A, as per plan (615E20001) | SY | 5,480 | $37.66 |
| 448 | Water (616E10000) | MGAL | 1,230 | $55.76 |
| 449 | Portable barrier, 50", as per plan (622E41011) | FT | 26,590 | $49.51 |
| 450 | Dual portable barrier transition/termination (622E41060) | EACH | 2 | $5,433.03 |
| 451 | Portable barrier, unanchored (622E41100) | FT | 33,300 | $38.44 |
| 452 | Portable barrier, anchored (622E41110) | FT | 6,520 | $84.44 |
| 453 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 223 | $551.65 |
| 454 | Portable non-intrusive traffic sensor, class I (896E00010) | SNMT | 84 | $563.79 |
| 455 | Portable changeable message sign, as per plan (896E00021) | SNMT | 84 | $941.84 |
| 456 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $500,350 |
| 457 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $1,532,760 |
| 458 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $37,977 |
| 459 | Steel piles, misc.: soldier piles HP12X53 (507E00400) | FT | 2,329 | $152.13 |
| 460 | Steel piles, misc.: soldier piles W18X86 (507E00400) | FT | 1,779 | $196.17 |
| 461 | Epoxy coated steel reinforcement (509E10000) | LB | 50,490 | $2.73 |
| 462 | Class QC1 concrete, retaining/wingwall not including footing, as per plan (511E46011) | CY | 490 | $2,880.73 |
| 463 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 1,012 | $56.85 |
| 464 | Type 2 waterproofing, as per plan (512E33001) | SY | 136 | $67.85 |
| 465 | 1" preformed expansion joint filler (516E13600) | SF | 1,024 | $16.47 |
| 466 | Prefabricated geocomposite drain (518E20000) | SY | 1,239 | $46.04 |
| 467 | 4" non-perforated corrugated plastic pipe, including specials (518E39900) | FT | 256 | $97.41 |
| 468 | Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503) | FT | 2,478 | $307.77 |
| 469 | Drilled shafts, 30" diameter, above bedrock, as per plan (524E94603) | FT | 2,234 | $283.21 |
| 470 | Special - retaining wall, timber lagging (530E51020) | SF | 11,499 | $35.19 |
| 471 | Concrete slope protection (601E21000) | SY | 77 | $234.63 |
| 472 | Paved gutter, type 1-2 (601E37500) | FT | 807 | $367.58 |
| 473 | 6" conduit, type C (611E01100) | FT | 379 | $38.50 |
| 474 | Ground anchor 30 kip max test load (866E00100) | EACH | 3 | $7,700.55 |
| 475 | Ground anchor 63 kip max test load (866E00100) | EACH | 39 | $9,024.08 |
| 476 | Ground anchor 89 kip max test load (866E00100) | EACH | 39 | $13,837 |
| 477 | Investigative anchor pullout tests (866E00300) | LS | 1 | $30,080 |
| 478 | Performance test (866E00400) | EACH | 5 | $1,203.21 |
| 479 | Extended creep test (866E00500) | EACH | 2 | $1,804.82 |
| 480 | Embankment, using natural soils, 703.16.A (203E22000) | CY | 42 | $236.13 |
| 481 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $4,758.61 |
| 482 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $191,010 |
| 483 | Unclassified excavation, as per plan (503E21301) | LS | 1 | $132,308 |
| 484 | Epoxy coated steel reinforcement (509E10000) | LB | 17,651 | $2.15 |
| 485 | Class QC1 concrete with QC/QA, substructure (511E50212) | CY | 176 | $2,144.86 |
| 486 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 151 | $56.85 |
| 487 | Type 2 waterproofing (512E33000) | SY | 23 | $67.27 |
| 488 | 3/4" preformed expansion joint filler (516E13400) | SF | 19 | $32.45 |
| 489 | 1" preformed expansion joint filler (516E13600) | SF | 42 | $33.26 |
| 490 | Porous backfill with geotextile fabric (518E21200) | CY | 71 | $262.56 |
| 491 | 6" perforated corrugated plastic pipe (518E40000) | FT | 191 | $16.24 |
| 492 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 10 | $106.01 |
| 493 | 8" perforated corrugated steel pipe, 707.01 (518E42200) | FT | 22 | $76.64 |
| 494 | 8" non-perforated corrugated steel pipe, including specials, 707.01 (518E42300) | FT | 2 | $432.94 |
| 495 | Special - form liner (530E13000) | SF | 153 | $33.39 |
| 496 | Paved gutter, type 1-2 (601E37500) | FT | 252 | $389.92 |
| 497 | Paved gutter, type 1-2, as per plan (601E37501) | FT | 28 | $860.51 |
| 499 | Embankment (203E20000) | CY | 3,877 | $104.72 |
| 500 | Granular material, type B (203E35110) | CY | 9,704 | $138.45 |
| 501 | Granular material, type B, as per plan (203E35111) | CY | 551 | $110.47 |
| 502 | Special - settlement platform (203E65000) | EACH | 31 | $2,880.85 |
| 503 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $4,782,457 |
| 504 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 7,519 | $56.85 |
| 505 | 1/2" preformed expansion joint filler (516E13200) | SF | 752 | $14.44 |
| 506 | 1" preformed expansion joint filler (516E13600) | SF | 472 | $19.25 |
| 507 | 2" preformed expansion joint filler (516E13900) | SF | 24 | $29.32 |
| 508 | Railing, misc.: traffic barrier on MSE wall (517E76300) | FT | 106 | $1,279.85 |
| 509 | Railing (combination noise and traffic barrier on MSE wall with flexible pavement) (517E80010) | FT | 1,355 | $1,493.10 |
| 510 | Concrete slope protection (601E21000) | SY | 236 | $276.74 |
| 511 | Paved gutter, type 1-2 (601E37500) | FT | 23 | $391.04 |
| 512 | Special - temporary surcharge wall B (690E98400) | LS | 1 | $132,353 |
| 513 | Special - temporary surcharge wall C (690E98400) | LS | 1 | $385,027 |
| 514 | Special - temporary surcharge wall F (690E98400) | LS | 1 | $451,204 |
| 515 | Special - temporary surcharge wall G (690E98400) | LS | 1 | $421,124 |
| 516 | Special - temporary surcharge wall H1 (690E98400) | LS | 1 | $358,013 |
| 517 | Special - temporary surcharge wall I1 (690E98400) | LS | 1 | $340,916 |
| 518 | Mechanically stabilized earth wall, as per plan (840E20001) | SF | 55,516 | $71.41 |
| 519 | Wall excavation (840E21000) | CY | 28,818 | $51.11 |
| 520 | Foundation preparation (840E22000) | SY | 5,153 | $57.74 |
| 521 | Foundation preparation, as per plan (840E22001) | SY | 2,583 | $222.70 |
| 522 | Select granular backfill (840E23000) | CY | 44,190 | $106.48 |
| 523 | Natural soil (840E23050) | CY | 257 | $60.16 |
| 524 | 6" drainage pipe, perforated (840E25010) | FT | 6,692 | $16.08 |
| 525 | 6" drainage pipe, non-perforated (840E25020) | FT | 369 | $34.89 |
| 526 | Concrete coping (840E26000) | FT | 2,969 | $402.43 |
| 527 | Aesthetic surface treatment (840E26050) | SF | 49,485 | $2.30 |
| 528 | On-site assistance (840E27000) | DAY | 12 | $904.10 |
| 529 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $120,321 |
| 530 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $114,305 |
| 531 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $42,112 |
| 532 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $42,112 |
| 533 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $36,096 |
| 534 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $36,096 |
| 535 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $205,662 |
| 536 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $60,161 |
| 537 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $228,087 |
| 538 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $72,193 |
| 539 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $1,022,729 |
| 540 | Approach slab removed (202E22900) | SY | 109 | $120.32 |
| 541 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $661,766 |
| 542 | Unclassified excavation (503E21300) | LS | 1 | $571,525 |
| 543 | Pile driving equipment mobilization (505E11100) | LS | 1 | $180,482 |
| 544 | 16" cast-in-place reinforced concrete piles, driven (507E00700) | FT | 8,890 | $66.18 |
| 545 | 16" cast-in-place reinforced concrete piles, furnished, as per plan (507E00751) | FT | 9,485 | $132.35 |
| 546 | Epoxy coated steel reinforcement (509E10000) | LB | 94,506 | $2.29 |
| 547 | Stainless steel reinforcement, as per plan (509E28001) | LB | 112,426 | $5.05 |
| 548 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 14,835 | $1.80 |
| 549 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 1,772 | $2.11 |
| 550 | Class QC SCC concrete with QC/QA, bridge deck (parapet), as per plan (511E34463) | CY | 136 | $2,677.14 |
| 551 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 338 | $1,052.81 |
| 552 | Class QC3 concrete, misc.: concrete with QC/QA, AB (511E53014) | CY | 271 | $2,075.54 |
| 553 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 346 | $2,286.10 |
| 554 | Class QC3 concrete, misc.: concrete with QC/QA, PI (511E53014) | CY | 170 | $2,316.18 |
| 555 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,530 | $56.85 |
| 556 | Structural steel members, level 5 (513E10300) | LB | 757,074 | $5.11 |
| 557 | Welded stud shear connectors (513E20000) | EACH | 5,436 | $4.99 |
| 558 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 9,152 | $30.08 |
| 559 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 9,152 | $18.05 |
| 560 | Armorless preformed joint seal (516E10010) | FT | 34 | $138.37 |
| 561 | Structural expansion joint including elastomeric strip seal (516E11210) | FT | 66 | $1,203.21 |
| 562 | 1" preformed expansion joint filler (516E13600) | SF | 111 | $24.06 |
| 563 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $5,534.77 |
| 564 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 2 | $6,016.05 |
| 565 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 3 | $4,090.92 |
| 566 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 5 | $6,016.05 |
| 567 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 2 | $6,016.05 |
| 568 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44201) | EACH | 3 | $4,812.84 |
| 569 | Porous backfill with geotextile fabric (518E21200) | CY | 136 | $240.64 |
| 570 | 6" perforated corrugated plastic pipe (518E40000) | FT | 94 | $31.28 |
| 571 | 6" non-perforated corrugated plastic pipe, including specials, as per plan (518E40011) | FT | 21 | $83.02 |
| 572 | Dynamic load testing (523E20000) | EACH | 8 | $5,895.73 |
| 573 | Restrike (523E20500) | EACH | 8 | $5,173.81 |
| 574 | Reinforced concrete approach slabs (T=17"), as per plan (526E30001) | SY | 224 | $1,022.73 |
| 575 | Type A installation (526E90010) | FT | 33 | $571.52 |
| 576 | Type C installation (526E90030) | FT | 34 | $571.53 |
| 577 | Crushed aggregate slope protection (601E20000) | SY | 469 | $48.13 |
| 578 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $1,173,130 |
| 579 | Approach slab removed (202E22900) | SY | 582 | $120.32 |
| 580 | Embankment, as per plan (203E20001) | CY | 44 | $198.53 |
| 581 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $721,926 |
| 582 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $902,408 |
| 583 | Unclassified excavation (503E21300) | LS | 1 | $571,525 |
| 584 | Pile driving equipment mobilization (505E11100) | LS | 1 | $240,642 |
| 585 | 16" cast-in-place reinforced concrete piles, driven (507E00700) | FT | 9,520 | $66.18 |
| 586 | 16" cast-in-place reinforced concrete piles, furnished, as per plan (507E00751) | FT | 10,140 | $132.35 |
| 587 | Epoxy coated steel reinforcement (509E10000) | LB | 266,397 | $2.29 |
| 588 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 6,635 | $1.80 |
| 589 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 800 | $2.11 |
| 590 | No. 6 GFRP deformed bars (509E30040) | FT | 6,259 | $2.23 |
| 591 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 4 | $7,219.26 |
| 592 | Class QC SCC concrete with QC/QA, bridge deck (parapet), as per plan (511E34463) | CY | 51 | $2,677.14 |
| 593 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 415 | $1,052.81 |
| 594 | Class QC3 concrete, misc.: concrete with QC/QA, AB (511E53014) | CY | 230 | $1,985.30 |
| 595 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 66 | $1,985.30 |
| 596 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 845 | $2,045.46 |
| 597 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,348 | $56.85 |
| 598 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 72 | $36.10 |
| 599 | Type 2 waterproofing (512E33000) | SY | 61 | $42.11 |
| 600 | Structural steel members, level 4 (513E10280) | LB | 834,999 | $4.51 |
| 601 | Welded stud shear connectors (513E20000) | EACH | 6,696 | $5.29 |
| 602 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 2,629 | $30.08 |
| 603 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 2,629 | $24.06 |
| 604 | 1" preformed expansion joint filler (516E13600) | SF | 524 | $24.06 |
| 605 | 1-1/2" preformed expansion joint filler (516E13800) | SF | 142 | $26.47 |
| 606 | 2" preformed expansion joint filler (516E13900) | SF | 198 | $27.67 |
| 607 | Semi-integral abutment expansion joint seal (516E14020) | FT | 491 | $120.32 |
| 608 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44401) | EACH | 36 | $3,729.95 |
| 609 | Porous backfill with geotextile fabric (518E21200) | CY | 180 | $246.66 |
| 610 | 6" perforated corrugated plastic pipe (518E40000) | FT | 317 | $24.06 |
| 611 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 71 | $39.71 |
| 612 | Dynamic load testing (523E20000) | EACH | 8 | $6,016.05 |
| 613 | Restrike (523E20500) | EACH | 8 | $5,173.81 |
| 614 | Reinforced concrete approach slabs (T=17"), as per plan (526E30001) | SY | 1,028 | $992.65 |
| 615 | Type A installation (526E90010) | FT | 422 | $439.17 |
| 616 | Crushed aggregate slope protection (601E20000) | SY | 948 | $54.14 |
| 617 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $30,080 |
| 618 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $30,080 |
| 619 | Temporary wire faced mechanically stabilized earth wall (867E00100) | LS | 1 | $7,820.87 |
| 620 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $1,684,495 |
| 621 | Approach slab removed (202E22900) | SY | 407 | $120.32 |
| 622 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $90,241 |
| 623 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $90,241 |
| 624 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $78,209 |
| 625 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $78,209 |
| 626 | Unclassified excavation (503E21300) | LS | 1 | $1,203.21 |
| 627 | Pile driving equipment mobilization (505E11100) | LS | 1 | $240,642 |
| 628 | 16" cast-in-place reinforced concrete piles, driven (507E00700) | FT | 11,625 | $66.18 |
| 629 | 16" cast-in-place reinforced concrete piles, furnished (507E00750) | FT | 12,400 | $132.35 |
| 630 | Epoxy coated steel reinforcement (509E10000) | LB | 207,660 | $2.29 |
| 631 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 4,288 | $1.80 |
| 632 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 627 | $2.11 |
| 633 | No. 6 GFRP deformed bars (509E30040) | FT | 4,168 | $2.23 |
| 634 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 4 | $7,219.26 |
| 635 | Class QC SCC concrete with QC/QA, bridge deck (parapet), as per plan (511E34463) | CY | 30 | $2,677.14 |
| 636 | Class QC1 concrete with QC/QA, footing (511E46512) | CY | 372 | $1,052.81 |
| 637 | Class QC3 concrete, misc.: concrete with QC/QA, AB (511E53014) | CY | 148 | $2,165.78 |
| 638 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 36 | $1,985.30 |
| 639 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 689 | $1,925.14 |
| 640 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,434 | $56.85 |
| 641 | Type 2 waterproofing (512E33000) | SY | 9 | $44.52 |
| 642 | Draped strand prestressed concrete bridge I-beam members, level 3, type 3 (515E15010) | EACH | 24 | $60,161 |
| 643 | Draped strand prestressed concrete bridge I-beam members, level 3, type 3 (515E15010) | EACH | 1 | $60,161 |
| 644 | Intermediate diaphragms (515E20000) | EACH | 23 | $6,617.66 |
| 645 | 1" preformed expansion joint filler (516E13600) | SF | 41 | $24.06 |
| 646 | 2" preformed expansion joint filler (516E13900) | SF | 91 | $27.67 |
| 647 | Semi-integral abutment expansion joint seal (516E14020) | FT | 454 | $108.29 |
| 648 | Elastomeric bearing with internal laminates and load plate (516E44200) | EACH | 50 | $3,368.99 |
| 649 | Dynamic load testing (523E20000) | EACH | 8 | $6,016.05 |
| 650 | Restrike (523E20500) | EACH | 8 | $5,173.81 |
| 651 | Reinforced concrete approach slabs (T=17"), as per plan (526E30001) | SY | 1,404 | $902.41 |
| 652 | Type A installation (526E90010) | FT | 422 | $451.20 |
| 653 | Concrete barrier end section, type D, as per plan (622E25001) | EACH | 2 | $13,235 |
| 654 | Polymer modified asphalt expansion joint system (846E00110) | CF | 176 | $872.33 |
| 655 | Structure removed, over 20 foot span, as per plan (202E11003) | LS | 1 | $1,664,642 |
| 656 | Approach slab removed (202E22900) | SY | 473 | $120.32 |
| 657 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $421,124 |
| 658 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $360,963 |
| 659 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $360,963 |
| 660 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $330,883 |
| 661 | Unclassified excavation (503E21300) | LS | 1 | $1,203.21 |
| 662 | Pile driving equipment mobilization (505E11100) | LS | 1 | $240,642 |
| 663 | 12" cast-in-place reinforced concrete piles, driven (507E00500) | FT | 7,940 | $60.16 |
| 664 | 12" cast-in-place reinforced concrete piles, furnished (507E00550) | FT | 8,550 | $78.21 |
| 665 | Epoxy coated steel reinforcement (509E10000) | LB | 146,644 | $2.29 |
| 666 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 5,498 | $1.80 |
| 667 | No. 5 deformed GFRP reinforcement (509E30030) | FT | 2,352 | $2.11 |
| 668 | No. 6 GFRP deformed bars (509E30040) | FT | 3,295 | $2.23 |
| 669 | Semi-integral diaphragm guide, as per plan (511E33501) | EACH | 8 | $7,219.26 |
| 670 | Class QC SCC concrete with QC/QA, bridge deck (parapet), as per plan (511E34463) | CY | 26 | $2,677.14 |
| 671 | Class QC1 concrete with QC/QA, footing, as per plan (511E46513) | CY | 316 | $1,052.81 |
| 672 | Class QC3 concrete, misc.: concrete with QC/QA, AB (511E53014) | CY | 152 | $2,075.54 |
| 673 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 32 | $1,985.30 |
| 674 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 531 | $1,985.30 |
| 675 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,010 | $56.85 |
| 676 | Type 2 waterproofing (512E33000) | SY | 7 | $45.72 |
| 677 | Structural steel members, level 1 (513E10220) | LB | 328,782 | $3.97 |
| 678 | Welded stud shear connectors (513E20000) | EACH | 7,383 | $4.87 |
| 679 | Field painting structural steel, intermediate coat, as per plan (514E00061) | SF | 636 | $72.19 |
| 680 | Field painting structural steel, finish coat, as per plan (514E00067) | SF | 636 | $48.13 |
| 681 | Final inspection repair (514E10000) | EACH | 10 | $1.20 |
| 682 | Armorless preformed joint seal (516E10010) | FT | 396 | $144.39 |
| 683 | 1" preformed expansion joint filler (516E13600) | SF | 353 | $24.06 |
| 684 | 2" preformed expansion joint filler (516E13900) | SF | 44 | $28.88 |
| 685 | Semi-integral abutment expansion joint seal (516E14020) | FT | 414 | $103.48 |
| 686 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 46 | $3,008.03 |
| 687 | Dynamic load testing (523E20000) | EACH | 8 | $6,016.05 |
| 688 | Restrike (523E20500) | EACH | 8 | $5,173.81 |
| 689 | Reinforced concrete approach slabs (T=17"), as per plan (526E30001) | SY | 1,267 | $962.57 |
| 690 | Type C installation (526E90030) | FT | 396 | $481.28 |
| 691 | Department'S share of the dispute resolution board (100E51100) | EACH | 220,000 | $1.00 |
| 692 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $1,749,574 |
| 693 | CPM progress schedule (108E10000) | LS | 1 | $106,100 |
| 694 | Special - departments share facilitated partnering costs (111E10100) | EACH | 11,000 | $1.00 |
| 695 | Maintaining traffic (614E11000) | LS | 1 | $11,515,556 |
| 696 | Field office, type C, as per plan (619E16021) | MNTH | 48 | $5,160.51 |
| 697 | Construction layout stakes and surveying (623E10000) | LS | 1 | $1,792,319 |
| 698 | Mobilization, as per plan (624E10001) | LS | 1 | $9,950,000 |
| 700 | Water work, misc.:reconnecting existing 3/4? servi (638E98000) | EACH | 1 | $1,888.54 |
| 701 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $407,912 |
| 702 | 18" conduit, type B (611E07400) | FT | 97 | $261.48 |
| 703 | Special -pre-construction sewer video (690E98400) | LS | 1 | $30,080 |
| 704 | Special -post-construction sewer video (690E98400) | LS | 1 | $30,080 |
| 705 | Structure removed (202E11000) | LS | 1 | $23,758 |
| 706 | Class QC3 concrete, misc.: concrete with QC/QA, BR (511E53014) | CY | 10 | $8,121.67 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 8, 2026. Compiled by Mirage Metrics.