MIA-SR 571-IMP 06.38 (BIKEWAYS). Let by Ohio DOT on December 18, 2025, MIA. 7 bids received; low bid $1,488,126 by Eagle Bridge Co, -25% against the engineer's estimate of $1,975,000.

Owner
Ohio DOT
Letting
18 DEC 2025
Pay items
111
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Eagle Bridge Co$1,488,126Low-25%
2Brumbaugh Construction Inc$1,773,281+19%-10%
3Sunesis Construction Co$1,739,534+17%-12%
4R B Jergens Contractors Inc$1,836,629+23%-7.0%
5Double Jay Construction Inc$1,849,541+24%-6.0%
6Complete General Construction Company$1,927,887+30%-2.0%
7John R Jurgensen Company$2,028,269+36%+3.0%
ODOT contract 250592: bids by rank

Engineer's estimate: $1,975,000.

Bid tabulation

LinePay itemUnitQuantity1. Eagle Bridge Co2. Brumbaugh Construction Inc3. Sunesis Construction Co4. R B Jergens Contractors Inc5. Double Jay Construction Inc6. Complete General Construction Company
1Clearing and grubbing (201E11000)LS1$12,500$28,000$22,600$20,853$18,802$20,000
2Pavement removed (202E23000)SY842$22.00$12.00$35.06$23.75$9.40$30.00
3Walk removed (202E30000)SF1,192$2.50$3.00$4.46$3.97$1.85$5.00
4Curb and gutter removed (202E32500)FT259$7.50$15.00$10.93$11.57$11.20$12.00
5Pipe removed, 24" and under (202E35100)FT157$11.00$8.00$17.89$57.21$17.10$30.00
6Guardrail removed (202E38000)FT712$2.00$6.00$5.00$5.37$5.60$3.00
7Catch basin removed (202E58100)EACH1$275.00$250.00$664.66$878.80$491.00$800.00
8Removal misc.: inspection well (202E98100)EACH1$450.00$700.00$757.45$460.12$556.00$600.00
9Removal misc.: conduit (202E98200)FT70$7.00$14.00$8.15$29.97$20.80$20.00
10Excavation, as per plan (203E10001)CY910$25.00$25.00$31.82$35.67$30.65$70.00
11Embankment (203E20000)CY715$20.00$25.00$24.57$26.42$28.90$12.00
12Subgrade compaction (204E10000)SY2,397$6.00$2.00$6.17$2.72$2.15$6.00
13Excavation of subgrade (204E13000)CY200$15.00$22.00$75.11$46.99$23.45$30.00
14Granular material, type C (204E30020)CY200$50.00$70.00$126.73$53.92$53.50$65.00
15Proof rolling (204E45000)HR5$150.00$400.00$370.37$352.50$235.00$250.00
164" concrete walk (608E10000)SF1,662$15.00$15.00$13.43$10.40$8.50$12.00
17Curb ramp (608E52000)SF1,616$22.00$21.00$19.52$24.04$16.45$15.00
18Special - mailbox removed and reset (690E50350)EACH2$225.00$650.00$883.83$406.98$335.00$250.00
19Rock channel protection, type C without filter (601E34200)CY7$225.00$200.00$543.02$292.22$252.00$180.00
20Topsoil (659E00300)CY675$35.00$55.00$45.00$68.19$72.80$40.00
21Seeding and mulching, class 1 (659E00500)SY4,165$1.75$2.00$4.71$2.10$3.35$2.34
22Repair seeding and mulching (659E14000)SY305$2.50$2.00$10.00$2.10$2.25$3.45
23Inter-seeding (659E15000)SY305$1.00$2.00$2.50$2.10$2.25$3.45
24Commercial fertilizer (659E20000)TON0.74$1,500.00$1,750.00$900.00$797.32$850.00$700.00
25Lime (659E31000)ACRE1.25$5.00$450.00$2.50$52.46$56.00$10.00
26Water (659E35000)MGAL20$15.00$5.00$2.50$52.46$56.00$1.00
27Slope erosion protection (670E00500)SY616$2.50$3.00$5.00$4.72$5.05$2.45
28Storm water pollution prevention plan (832E15000)LS1$3,000.00$3,125.00$2,600.00$2,622.76$2,800.00$3,500.00
29Storm water pollution prevention inspections (832E15002)LS1$12,500$8,000.00$10,560$8,812.48$10,584$7,500.00
30Storm water pollution prevention inspection software (832E15010)LS1$6,750.00$7,000.00$5,758.08$6,294.63$7,840.00$5,800.00
31Erosion control (832E30000)EACH10,000$1.00$1.00$1.00$1.00$1.00$1.00
32Class QC1 concrete, headwall (511E46610)CY0.91$4,250.00$6,000.00$6,971.62$6,012.08$3,390.00$5,000.00
334" conduit, type E (611E00400)FT40$20.00$45.00$31.55$46.33$41.15$19.00
3412" conduit, type B (611E04400)FT86$125.00$90.00$174.98$116.43$85.85$170.00
3518" conduit, type C (611E07600)FT180$165.00$95.00$196.89$135.74$115.40$200.00
36Conduit, misc.: type E for drainage continuance (611E97400)FT20$20.00$50.00$161.75$52.22$83.35$20.00
37Catch basin, misc.: type 1 CB, as per plan (611E98690)EACH1$3,750.00$3,000.00$4,844.76$3,166.31$3,039.00$6,000.00
38Inlet, no. 3 for single slope barrier, type D (611E99114)EACH3$13,500$14,175$19,737$9,644.96$17,725$19,000
39Manhole adjusted to grade (611E99654)EACH3$1,250.00$800.00$1,870.78$859.82$502.00$750.00
40Manhole reconstructed to grade (611E99660)EACH2$1,750.00$2,500.00$1,615.60$3,142.84$1,070.00$1,250.00
41Inspection well (611E99720)EACH1$1,000.00$2,650.00$2,533.86$3,184.80$1,922.00$1,250.00
42Pavement planing, asphalt concrete, 1-1/4" (254E01000)SY1,225$3.65$4.00$8.51$8.41$11.70$3.65
43Aggregate base (304E20000)CY474$110.00$72.00$123.92$66.68$74.00$110.00
44Non-tracking tack coat (407E20000)GAL248$1.00$1.00$5.00$5.42$11.20$1.00
45Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000)CY144$315.00$350.00$560.00$606.92$404.00$315.00
46Asphalt concrete intermediate course, type 2, (449) (441E70300)CY152$275.00$305.00$400.00$433.51$381.00$275.00
47Rock excavation, as per plan (503E31101)CY225$175.00$155.00$90.57$93.32$112.00$100.00
48Combination curb and gutter, type 2, as per plan (609E12001)FT349$50.00$85.00$70.16$36.42$51.75$65.00
49Curb, type 6 (609E26000)FT84$40.00$70.00$58.03$54.63$54.90$60.00
50Low strength mortar backfill (613E41200)CY18$350.00$250.00$305.55$336.27$193.00$250.00
51Connection, fused pull apart, as per plan (625E00451)EACH66$83.20$130.00$83.20$87.29$93.20$145.00
52Connection, unfused pull apart (625E00460)EACH22$77.19$150.00$77.19$80.98$86.50$145.00
53Light pole foundation, 24" X 6' deep (625E14000)EACH19$1,750.00$1,600.00$1,750.00$1,835.93$1,960.00$3,000.00
54No. 6 AWG 600 volt distribution cable (625E22990)FT10,209$1.08$2.20$1.08$1.13$1.25$2.50
55No. 2 AWG 600 volt distribution cable (625E23100)FT16,647$3.15$4.00$3.15$3.30$3.55$4.75
56No. 12 AWG pole and bracket cable (625E23410)FT4,307$0.35$0.60$0.35$0.37$0.40$1.25
57Conduit, 2", 725.051 (625E25408)FT897$1.20$4.20$1.20$1.26$1.35$9.00
58Conduit, 3", 725.04, as per plan (625E25501)FT490$30.37$24.00$22.50$23.60$25.20$56.00
59Conduit, 3", 725.051 (625E25504)FT1,404$2.29$4.50$2.29$2.40$2.60$14.00
60Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT288$35.00$26.00$35.00$36.72$39.20$40.00
61Conduit, jacked or drilled, 725.052, as per plan (625E25909)FT186$45.00$28.00$45.00$47.21$50.40$45.00
62Conduit, misc.: conduit expansion/contraction fitt (625E25930)EACH2$25.00$500.00$25.00$26.23$28.00$1,100.00
63Trench (625E29000)FT2,392$16.50$14.00$16.50$17.31$18.50$10.00
64Junction box (625E29900)EACH3$2,323.10$1,600.00$2,323.10$2,437.18$2,602.00$3,500.00
65Pull box, 725.08, 18" (625E30700)EACH3$550.00$850.00$550.00$577.01$616.00$1,400.00
66Ground rod (625E32000)EACH23$125.00$280.00$125.00$131.14$140.00$320.00
67Structure grounding system, as per plan (625E33001)EACH1$7,500.00$4,500.00$7,500.00$1,835.93$8,400.00$19,500
68Power service, as per plan (625E34001)EACH1$2,750.00$7,200.00$2,750.00$2,885.04$3,080.00$10,000
69Underground warning marking tape (625E36010)FT2,392$1.25$0.60$1.25$1.31$1.40$1.50
70Power cable, 3 conductor, no. 4 AWG (632E69300)FT37$5.25$22.00$5.25$5.51$5.90$10.00
74Light pole, decorative, as per plan (625E10481)EACH3$4,089.50$9,000.00$4,089.50$4,290.32$4,581.00$4,000.00
75Light pole, decorative, as per plan (625E10481)EACH19$4,581.61$10,000$4,581.61$4,806.59$5,132.00$4,550.00
76Luminaire, teardrop, solid state (LED), as per plan (625E27507)EACH22$2,463.50$5,000.00$2,463.50$2,584.47$2,760.00$1,700.00
77Delineator, post surface mounted (620E60000)EACH58$49.50$55.00$49.50$112.87$118.00$110.00
78Ground mounted support, no. 3 post (630E03100)FT89.50$15.50$17.00$15.50$25.80$27.00$17.00
79Street name sign support, no. 3 post (630E08520)FT34.50$15.50$17.00$15.50$26.87$28.00$19.00
80Sign, flat sheet (630E80100)SF32.50$16.00$18.00$16.00$32.25$33.60$24.40
81Sign, double faced, street name (630E80500)EACH6$140.00$155.00$140.00$241.86$252.00$230.00
82Removal of ground mounted sign and disposal (630E84900)EACH18$20.00$22.00$20.00$21.50$23.00$10.00
83Removal of ground mounted post support and disposal (630E86002)EACH14$25.00$28.00$25.00$21.50$23.00$15.00
84Removal of pavement markings (645E30000)FT2,910$1.13$1.50$1.25$1.51$1.30$1.13
85Edge line, 4" (646E10000)MI0.92$4,300.00$4,775.00$2,825.00$5,749.78$4,820.00$4,300.00
86Lane line, 4" (646E10100)MI0.04$3,600.00$4,000.00$1,130.00$4,813.75$4,030.00$3,600.00
87Center line (646E10200)MI0.60$8,440.00$9,380.00$5,640.00$11,286$9,453.00$8,440.00
88Channelizing line, 8" (646E10300)FT150$3.00$3.50$1.40$4.01$3.40$3.00
89Crosswalk line, 12" (646E10510)FT348$5.00$5.50$6.50$6.69$5.60$5.00
90Crosswalk line, 24" (646E10520)FT55$10.00$11.00$9.90$13.37$11.20$10.00
91Transverse/diagonal line (646E10600)FT1,200$6.95$8.00$11.85$9.29$7.80$6.95
92Lane arrow (646E20300)EACH2$350.00$390.00$175.00$468.00$392.00$350.00
93Work zone lane line, class III, 6", 642 paint (614E20560)MI0.06$2,900.00$3,200.00$2,970.00$3,877.83$3,250.00$2,900.00
94Work zone center line, class III, 642 paint (614E21550)MI0.25$5,800.00$6,400.00$6,825.00$7,755.52$6,500.00$5,800.00
95Work zone edge line, class III, 6", 642 paint (614E22360)MI0.33$3,870.00$4,300.00$5,635.00$5,174.79$4,340.00$3,870.00
96Portions of structure removed, over 20 foot span, as per plan (202E11203)LS1$25,000$12,000$13,156$36,518$33,600$30,000
97Epoxy coated steel reinforcement (509E10000)LB2,025$2.75$4.00$3.55$5.37$2.50$3.50
98Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001)EACH186$20.00$30.00$26.47$18.29$39.50$60.00
99Class QC2 concrete, bridge deck (parapet) (511E34448)CY85$1,100.00$1,250.00$1,018.63$1,097.61$1,345.00$1,650.00
100Sealing of concrete surfaces, as per plan (512E10001)SY1,285$20.00$14.00$48.30$40.95$49.30$20.00
101Railing, misc.: modified BR-2-15 railing (517E76300)FT428$85.00$95.00$85.00$91.21$95.20$98.00
102Scupper, modification, as per plan (518E12801)EACH8$1,500.00$1,500.00$1,741.29$3,855.91$1,634.00$2,500.00
103Impact attenuator, type 2 (unidirectional), as per plan (606E60023)EACH2$30,000$35,000$28,500$30,635$31,920$31,830
104Fence, misc.: 42" wood fence (607E98000)FT718$48.00$55.00$48.00$51.51$53.80$49.50
105Fence, misc.:perimeter geotextile fence (607E98000)FT139$5.00$7.00$126.00$53.46$5.15$4.00
106Concrete barrier, single slope, type D (622E10160)FT543$80.00$125.00$100.00$211.84$145.60$160.00
107Concrete barrier end section, type D (622E25000)EACH2$6,750.00$5,400.00$4,300.00$7,205.38$6,074.00$7,500.00
108Concrete barrier, end anchorage, reinforced, type D (622E25050)EACH8$3,250.00$4,400.00$3,500.00$7,205.25$4,585.00$6,000.00
109Premium for contract performance bond and for payment bond (103E05000)LS1$12,000$14,000$10,655$12,803$14,784$20,000
110Maintaining traffic (614E11000)LS1$25,000$32,408$80,288$75,000$94,140$60,000
111Field office, type B (619E16010)MNTH12$2,250.00$3,125.00$1,239.17$1,920.44$2,525.00$3,000.00
112Construction layout stakes and surveying (623E10000)LS1$20,000$21,250$13,700$14,373$37,632$42,500
113Mobilization (624E10000)LS1$61,000$65,000$40,000$62,586$108,332$100,000
200Sealing of concrete surfaces (epoxy-urethane) (512E10100)SY959$25.50$22.00$40.62$54.00$41.45$25.50
ODOT contract 250592: unit prices by line, the 6 lowest bidders (all in the CSV)

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy