ODOT contract 250592 bid tabulation
MIA-SR 571-IMP 06.38 (BIKEWAYS). Let by Ohio DOT on December 18, 2025, MIA. 7 bids received; low bid $1,488,126 by Eagle Bridge Co, -25% against the engineer's estimate of $1,975,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 111
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Eagle Bridge Co | $1,488,126 | Low | -25% |
| 2 | Brumbaugh Construction Inc | $1,773,281 | +19% | -10% |
| 3 | Sunesis Construction Co | $1,739,534 | +17% | -12% |
| 4 | R B Jergens Contractors Inc | $1,836,629 | +23% | -7.0% |
| 5 | Double Jay Construction Inc | $1,849,541 | +24% | -6.0% |
| 6 | Complete General Construction Company | $1,927,887 | +30% | -2.0% |
| 7 | John R Jurgensen Company | $2,028,269 | +36% | +3.0% |
Engineer's estimate: $1,975,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Eagle Bridge Co | 2. Brumbaugh Construction Inc | 3. Sunesis Construction Co | 4. R B Jergens Contractors Inc | 5. Double Jay Construction Inc | 6. Complete General Construction Company |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $12,500 | $28,000 | $22,600 | $20,853 | $18,802 | $20,000 |
| 2 | Pavement removed (202E23000) | SY | 842 | $22.00 | $12.00 | $35.06 | $23.75 | $9.40 | $30.00 |
| 3 | Walk removed (202E30000) | SF | 1,192 | $2.50 | $3.00 | $4.46 | $3.97 | $1.85 | $5.00 |
| 4 | Curb and gutter removed (202E32500) | FT | 259 | $7.50 | $15.00 | $10.93 | $11.57 | $11.20 | $12.00 |
| 5 | Pipe removed, 24" and under (202E35100) | FT | 157 | $11.00 | $8.00 | $17.89 | $57.21 | $17.10 | $30.00 |
| 6 | Guardrail removed (202E38000) | FT | 712 | $2.00 | $6.00 | $5.00 | $5.37 | $5.60 | $3.00 |
| 7 | Catch basin removed (202E58100) | EACH | 1 | $275.00 | $250.00 | $664.66 | $878.80 | $491.00 | $800.00 |
| 8 | Removal misc.: inspection well (202E98100) | EACH | 1 | $450.00 | $700.00 | $757.45 | $460.12 | $556.00 | $600.00 |
| 9 | Removal misc.: conduit (202E98200) | FT | 70 | $7.00 | $14.00 | $8.15 | $29.97 | $20.80 | $20.00 |
| 10 | Excavation, as per plan (203E10001) | CY | 910 | $25.00 | $25.00 | $31.82 | $35.67 | $30.65 | $70.00 |
| 11 | Embankment (203E20000) | CY | 715 | $20.00 | $25.00 | $24.57 | $26.42 | $28.90 | $12.00 |
| 12 | Subgrade compaction (204E10000) | SY | 2,397 | $6.00 | $2.00 | $6.17 | $2.72 | $2.15 | $6.00 |
| 13 | Excavation of subgrade (204E13000) | CY | 200 | $15.00 | $22.00 | $75.11 | $46.99 | $23.45 | $30.00 |
| 14 | Granular material, type C (204E30020) | CY | 200 | $50.00 | $70.00 | $126.73 | $53.92 | $53.50 | $65.00 |
| 15 | Proof rolling (204E45000) | HR | 5 | $150.00 | $400.00 | $370.37 | $352.50 | $235.00 | $250.00 |
| 16 | 4" concrete walk (608E10000) | SF | 1,662 | $15.00 | $15.00 | $13.43 | $10.40 | $8.50 | $12.00 |
| 17 | Curb ramp (608E52000) | SF | 1,616 | $22.00 | $21.00 | $19.52 | $24.04 | $16.45 | $15.00 |
| 18 | Special - mailbox removed and reset (690E50350) | EACH | 2 | $225.00 | $650.00 | $883.83 | $406.98 | $335.00 | $250.00 |
| 19 | Rock channel protection, type C without filter (601E34200) | CY | 7 | $225.00 | $200.00 | $543.02 | $292.22 | $252.00 | $180.00 |
| 20 | Topsoil (659E00300) | CY | 675 | $35.00 | $55.00 | $45.00 | $68.19 | $72.80 | $40.00 |
| 21 | Seeding and mulching, class 1 (659E00500) | SY | 4,165 | $1.75 | $2.00 | $4.71 | $2.10 | $3.35 | $2.34 |
| 22 | Repair seeding and mulching (659E14000) | SY | 305 | $2.50 | $2.00 | $10.00 | $2.10 | $2.25 | $3.45 |
| 23 | Inter-seeding (659E15000) | SY | 305 | $1.00 | $2.00 | $2.50 | $2.10 | $2.25 | $3.45 |
| 24 | Commercial fertilizer (659E20000) | TON | 0.74 | $1,500.00 | $1,750.00 | $900.00 | $797.32 | $850.00 | $700.00 |
| 25 | Lime (659E31000) | ACRE | 1.25 | $5.00 | $450.00 | $2.50 | $52.46 | $56.00 | $10.00 |
| 26 | Water (659E35000) | MGAL | 20 | $15.00 | $5.00 | $2.50 | $52.46 | $56.00 | $1.00 |
| 27 | Slope erosion protection (670E00500) | SY | 616 | $2.50 | $3.00 | $5.00 | $4.72 | $5.05 | $2.45 |
| 28 | Storm water pollution prevention plan (832E15000) | LS | 1 | $3,000.00 | $3,125.00 | $2,600.00 | $2,622.76 | $2,800.00 | $3,500.00 |
| 29 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $12,500 | $8,000.00 | $10,560 | $8,812.48 | $10,584 | $7,500.00 |
| 30 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $6,750.00 | $7,000.00 | $5,758.08 | $6,294.63 | $7,840.00 | $5,800.00 |
| 31 | Erosion control (832E30000) | EACH | 10,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 32 | Class QC1 concrete, headwall (511E46610) | CY | 0.91 | $4,250.00 | $6,000.00 | $6,971.62 | $6,012.08 | $3,390.00 | $5,000.00 |
| 33 | 4" conduit, type E (611E00400) | FT | 40 | $20.00 | $45.00 | $31.55 | $46.33 | $41.15 | $19.00 |
| 34 | 12" conduit, type B (611E04400) | FT | 86 | $125.00 | $90.00 | $174.98 | $116.43 | $85.85 | $170.00 |
| 35 | 18" conduit, type C (611E07600) | FT | 180 | $165.00 | $95.00 | $196.89 | $135.74 | $115.40 | $200.00 |
| 36 | Conduit, misc.: type E for drainage continuance (611E97400) | FT | 20 | $20.00 | $50.00 | $161.75 | $52.22 | $83.35 | $20.00 |
| 37 | Catch basin, misc.: type 1 CB, as per plan (611E98690) | EACH | 1 | $3,750.00 | $3,000.00 | $4,844.76 | $3,166.31 | $3,039.00 | $6,000.00 |
| 38 | Inlet, no. 3 for single slope barrier, type D (611E99114) | EACH | 3 | $13,500 | $14,175 | $19,737 | $9,644.96 | $17,725 | $19,000 |
| 39 | Manhole adjusted to grade (611E99654) | EACH | 3 | $1,250.00 | $800.00 | $1,870.78 | $859.82 | $502.00 | $750.00 |
| 40 | Manhole reconstructed to grade (611E99660) | EACH | 2 | $1,750.00 | $2,500.00 | $1,615.60 | $3,142.84 | $1,070.00 | $1,250.00 |
| 41 | Inspection well (611E99720) | EACH | 1 | $1,000.00 | $2,650.00 | $2,533.86 | $3,184.80 | $1,922.00 | $1,250.00 |
| 42 | Pavement planing, asphalt concrete, 1-1/4" (254E01000) | SY | 1,225 | $3.65 | $4.00 | $8.51 | $8.41 | $11.70 | $3.65 |
| 43 | Aggregate base (304E20000) | CY | 474 | $110.00 | $72.00 | $123.92 | $66.68 | $74.00 | $110.00 |
| 44 | Non-tracking tack coat (407E20000) | GAL | 248 | $1.00 | $1.00 | $5.00 | $5.42 | $11.20 | $1.00 |
| 45 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 144 | $315.00 | $350.00 | $560.00 | $606.92 | $404.00 | $315.00 |
| 46 | Asphalt concrete intermediate course, type 2, (449) (441E70300) | CY | 152 | $275.00 | $305.00 | $400.00 | $433.51 | $381.00 | $275.00 |
| 47 | Rock excavation, as per plan (503E31101) | CY | 225 | $175.00 | $155.00 | $90.57 | $93.32 | $112.00 | $100.00 |
| 48 | Combination curb and gutter, type 2, as per plan (609E12001) | FT | 349 | $50.00 | $85.00 | $70.16 | $36.42 | $51.75 | $65.00 |
| 49 | Curb, type 6 (609E26000) | FT | 84 | $40.00 | $70.00 | $58.03 | $54.63 | $54.90 | $60.00 |
| 50 | Low strength mortar backfill (613E41200) | CY | 18 | $350.00 | $250.00 | $305.55 | $336.27 | $193.00 | $250.00 |
| 51 | Connection, fused pull apart, as per plan (625E00451) | EACH | 66 | $83.20 | $130.00 | $83.20 | $87.29 | $93.20 | $145.00 |
| 52 | Connection, unfused pull apart (625E00460) | EACH | 22 | $77.19 | $150.00 | $77.19 | $80.98 | $86.50 | $145.00 |
| 53 | Light pole foundation, 24" X 6' deep (625E14000) | EACH | 19 | $1,750.00 | $1,600.00 | $1,750.00 | $1,835.93 | $1,960.00 | $3,000.00 |
| 54 | No. 6 AWG 600 volt distribution cable (625E22990) | FT | 10,209 | $1.08 | $2.20 | $1.08 | $1.13 | $1.25 | $2.50 |
| 55 | No. 2 AWG 600 volt distribution cable (625E23100) | FT | 16,647 | $3.15 | $4.00 | $3.15 | $3.30 | $3.55 | $4.75 |
| 56 | No. 12 AWG pole and bracket cable (625E23410) | FT | 4,307 | $0.35 | $0.60 | $0.35 | $0.37 | $0.40 | $1.25 |
| 57 | Conduit, 2", 725.051 (625E25408) | FT | 897 | $1.20 | $4.20 | $1.20 | $1.26 | $1.35 | $9.00 |
| 58 | Conduit, 3", 725.04, as per plan (625E25501) | FT | 490 | $30.37 | $24.00 | $22.50 | $23.60 | $25.20 | $56.00 |
| 59 | Conduit, 3", 725.051 (625E25504) | FT | 1,404 | $2.29 | $4.50 | $2.29 | $2.40 | $2.60 | $14.00 |
| 60 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 288 | $35.00 | $26.00 | $35.00 | $36.72 | $39.20 | $40.00 |
| 61 | Conduit, jacked or drilled, 725.052, as per plan (625E25909) | FT | 186 | $45.00 | $28.00 | $45.00 | $47.21 | $50.40 | $45.00 |
| 62 | Conduit, misc.: conduit expansion/contraction fitt (625E25930) | EACH | 2 | $25.00 | $500.00 | $25.00 | $26.23 | $28.00 | $1,100.00 |
| 63 | Trench (625E29000) | FT | 2,392 | $16.50 | $14.00 | $16.50 | $17.31 | $18.50 | $10.00 |
| 64 | Junction box (625E29900) | EACH | 3 | $2,323.10 | $1,600.00 | $2,323.10 | $2,437.18 | $2,602.00 | $3,500.00 |
| 65 | Pull box, 725.08, 18" (625E30700) | EACH | 3 | $550.00 | $850.00 | $550.00 | $577.01 | $616.00 | $1,400.00 |
| 66 | Ground rod (625E32000) | EACH | 23 | $125.00 | $280.00 | $125.00 | $131.14 | $140.00 | $320.00 |
| 67 | Structure grounding system, as per plan (625E33001) | EACH | 1 | $7,500.00 | $4,500.00 | $7,500.00 | $1,835.93 | $8,400.00 | $19,500 |
| 68 | Power service, as per plan (625E34001) | EACH | 1 | $2,750.00 | $7,200.00 | $2,750.00 | $2,885.04 | $3,080.00 | $10,000 |
| 69 | Underground warning marking tape (625E36010) | FT | 2,392 | $1.25 | $0.60 | $1.25 | $1.31 | $1.40 | $1.50 |
| 70 | Power cable, 3 conductor, no. 4 AWG (632E69300) | FT | 37 | $5.25 | $22.00 | $5.25 | $5.51 | $5.90 | $10.00 |
| 74 | Light pole, decorative, as per plan (625E10481) | EACH | 3 | $4,089.50 | $9,000.00 | $4,089.50 | $4,290.32 | $4,581.00 | $4,000.00 |
| 75 | Light pole, decorative, as per plan (625E10481) | EACH | 19 | $4,581.61 | $10,000 | $4,581.61 | $4,806.59 | $5,132.00 | $4,550.00 |
| 76 | Luminaire, teardrop, solid state (LED), as per plan (625E27507) | EACH | 22 | $2,463.50 | $5,000.00 | $2,463.50 | $2,584.47 | $2,760.00 | $1,700.00 |
| 77 | Delineator, post surface mounted (620E60000) | EACH | 58 | $49.50 | $55.00 | $49.50 | $112.87 | $118.00 | $110.00 |
| 78 | Ground mounted support, no. 3 post (630E03100) | FT | 89.50 | $15.50 | $17.00 | $15.50 | $25.80 | $27.00 | $17.00 |
| 79 | Street name sign support, no. 3 post (630E08520) | FT | 34.50 | $15.50 | $17.00 | $15.50 | $26.87 | $28.00 | $19.00 |
| 80 | Sign, flat sheet (630E80100) | SF | 32.50 | $16.00 | $18.00 | $16.00 | $32.25 | $33.60 | $24.40 |
| 81 | Sign, double faced, street name (630E80500) | EACH | 6 | $140.00 | $155.00 | $140.00 | $241.86 | $252.00 | $230.00 |
| 82 | Removal of ground mounted sign and disposal (630E84900) | EACH | 18 | $20.00 | $22.00 | $20.00 | $21.50 | $23.00 | $10.00 |
| 83 | Removal of ground mounted post support and disposal (630E86002) | EACH | 14 | $25.00 | $28.00 | $25.00 | $21.50 | $23.00 | $15.00 |
| 84 | Removal of pavement markings (645E30000) | FT | 2,910 | $1.13 | $1.50 | $1.25 | $1.51 | $1.30 | $1.13 |
| 85 | Edge line, 4" (646E10000) | MI | 0.92 | $4,300.00 | $4,775.00 | $2,825.00 | $5,749.78 | $4,820.00 | $4,300.00 |
| 86 | Lane line, 4" (646E10100) | MI | 0.04 | $3,600.00 | $4,000.00 | $1,130.00 | $4,813.75 | $4,030.00 | $3,600.00 |
| 87 | Center line (646E10200) | MI | 0.60 | $8,440.00 | $9,380.00 | $5,640.00 | $11,286 | $9,453.00 | $8,440.00 |
| 88 | Channelizing line, 8" (646E10300) | FT | 150 | $3.00 | $3.50 | $1.40 | $4.01 | $3.40 | $3.00 |
| 89 | Crosswalk line, 12" (646E10510) | FT | 348 | $5.00 | $5.50 | $6.50 | $6.69 | $5.60 | $5.00 |
| 90 | Crosswalk line, 24" (646E10520) | FT | 55 | $10.00 | $11.00 | $9.90 | $13.37 | $11.20 | $10.00 |
| 91 | Transverse/diagonal line (646E10600) | FT | 1,200 | $6.95 | $8.00 | $11.85 | $9.29 | $7.80 | $6.95 |
| 92 | Lane arrow (646E20300) | EACH | 2 | $350.00 | $390.00 | $175.00 | $468.00 | $392.00 | $350.00 |
| 93 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 0.06 | $2,900.00 | $3,200.00 | $2,970.00 | $3,877.83 | $3,250.00 | $2,900.00 |
| 94 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.25 | $5,800.00 | $6,400.00 | $6,825.00 | $7,755.52 | $6,500.00 | $5,800.00 |
| 95 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 0.33 | $3,870.00 | $4,300.00 | $5,635.00 | $5,174.79 | $4,340.00 | $3,870.00 |
| 96 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $25,000 | $12,000 | $13,156 | $36,518 | $33,600 | $30,000 |
| 97 | Epoxy coated steel reinforcement (509E10000) | LB | 2,025 | $2.75 | $4.00 | $3.55 | $5.37 | $2.50 | $3.50 |
| 98 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 186 | $20.00 | $30.00 | $26.47 | $18.29 | $39.50 | $60.00 |
| 99 | Class QC2 concrete, bridge deck (parapet) (511E34448) | CY | 85 | $1,100.00 | $1,250.00 | $1,018.63 | $1,097.61 | $1,345.00 | $1,650.00 |
| 100 | Sealing of concrete surfaces, as per plan (512E10001) | SY | 1,285 | $20.00 | $14.00 | $48.30 | $40.95 | $49.30 | $20.00 |
| 101 | Railing, misc.: modified BR-2-15 railing (517E76300) | FT | 428 | $85.00 | $95.00 | $85.00 | $91.21 | $95.20 | $98.00 |
| 102 | Scupper, modification, as per plan (518E12801) | EACH | 8 | $1,500.00 | $1,500.00 | $1,741.29 | $3,855.91 | $1,634.00 | $2,500.00 |
| 103 | Impact attenuator, type 2 (unidirectional), as per plan (606E60023) | EACH | 2 | $30,000 | $35,000 | $28,500 | $30,635 | $31,920 | $31,830 |
| 104 | Fence, misc.: 42" wood fence (607E98000) | FT | 718 | $48.00 | $55.00 | $48.00 | $51.51 | $53.80 | $49.50 |
| 105 | Fence, misc.:perimeter geotextile fence (607E98000) | FT | 139 | $5.00 | $7.00 | $126.00 | $53.46 | $5.15 | $4.00 |
| 106 | Concrete barrier, single slope, type D (622E10160) | FT | 543 | $80.00 | $125.00 | $100.00 | $211.84 | $145.60 | $160.00 |
| 107 | Concrete barrier end section, type D (622E25000) | EACH | 2 | $6,750.00 | $5,400.00 | $4,300.00 | $7,205.38 | $6,074.00 | $7,500.00 |
| 108 | Concrete barrier, end anchorage, reinforced, type D (622E25050) | EACH | 8 | $3,250.00 | $4,400.00 | $3,500.00 | $7,205.25 | $4,585.00 | $6,000.00 |
| 109 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,000 | $14,000 | $10,655 | $12,803 | $14,784 | $20,000 |
| 110 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $32,408 | $80,288 | $75,000 | $94,140 | $60,000 |
| 111 | Field office, type B (619E16010) | MNTH | 12 | $2,250.00 | $3,125.00 | $1,239.17 | $1,920.44 | $2,525.00 | $3,000.00 |
| 112 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $21,250 | $13,700 | $14,373 | $37,632 | $42,500 |
| 113 | Mobilization (624E10000) | LS | 1 | $61,000 | $65,000 | $40,000 | $62,586 | $108,332 | $100,000 |
| 200 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 959 | $25.50 | $22.00 | $40.62 | $54.00 | $41.45 | $25.50 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.