ODOT letting results, December 18, 2025
36 contracts let by Ohio DOT on December 18, 2025, $108,160,396 in low bids, a median of 3 bidders per contract. On the 36 with an engineer's estimate, the low bid came in under it 23 times; median low bid -6.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 36
- Low bids, total
- $108,160,396
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250610 | CUY-IR 77-15.46/VAR Decks (BRIDGE REPAIR) | CUY | 5 | Great Lakes Construction Co | $25,286,681 | $26,571,061 | +5.0% | +12% | ODOT |
| 250601 | WOO-IR 75/IR 475-24.85/00.00 Resurf (PART 1 AND PART 2) (FOUR LANE RESURFACING) | WOO | 3 | Gerken Paving Inc | $10,954,808 | $11,257,807 | +3.0% | +8.0% | ODOT |
| 250590 | MAD-IR 70-00.00 (FOUR LANE RESURFACING) | MAD | 4 | Kokosing Construction Company Inc | $9,132,215 | $9,616,896 | +5.0% | -9.0% | ODOT |
| 250557 | HAM-CR 14-03.49 Dry Fork Rd (INTERCHANGE) | HAM | 4 | Eagle Bridge Co | $8,255,027 | $8,556,751 | +4.0% | -3.0% | ODOT |
| 250587 | JEF-SR 7-(10.75)(14.61) (FOUR LANE RESURFACING) | JEF | 2 | Shelly & Sands Inc | $5,394,700 | $5,945,378 | +10% | +4.0% | ODOT |
| 250582 | CUY-IR 71-00.00 (FOUR LANE RESURFACING) | CUY | 3 | Kokosing Construction Company Inc | $4,720,151 | $5,375,384 | +14% | -2.0% | ODOT |
| 250600 | WAY-SR 226-00.905 (TWO LANE RESURFACING) | WAY | 2 | Kokosing Construction Company Inc | $4,290,993 | $5,258,169 | +23% | -9.0% | ODOT |
| 250599 | TRU-US 62-04.56 (FOUR LANE RESURFACING) | TRU | 4 | Kirila Contractors Inc | $4,111,119 | $4,119,251 | 0.0% | -7.0% | ODOT |
| 250583 | D01-OL FY26 (BRIDGE REPAIR) | District 1 | 5 | Ohio Concrete Maintenance LLC | $2,929,630 | $3,056,549 | +4.0% | -17% | ODOT |
| 250584 | D05-Guardrail FY2026 (GUARDRAIL REBUILDING) | District 5 | 2 | Lake Erie Construction Company | $2,887,120 | $2,994,927 | +4.0% | +3.0% | ODOT |
| 250595 | PAU-US 24-00.00 (SPOT PATCHING / PAVEMENT REPAIR) | PAU | 3 | Smith Paving & Excavating Inc | $2,423,992 | $2,785,249 | +15% | -5.0% | ODOT |
| 250555 | FAY-US 22-06.21 (INTERSECTION) | FAY | 5 | John R Jurgensen Company | $2,247,017 | $2,248,937 | 0.0% | +6.0% | ODOT |
| 250597 | ROS-US 50-04.00/25.27 (TWO LANE RESURFACING) | ROS | 3 | Shelly & Sands Inc | $2,195,259 | $2,363,237 | +8.0% | -12% | ODOT |
| 250594 | NOB-CEVSD Campus Connectivity (SIDEWALK) | NOB | 5 | Shelly & Sands Inc | $2,043,338 | $2,099,551 | +3.0% | -10% | ODOT |
| 250581 | CLI-US 22-00.00 (TWO LANE RESURFACING) | CLI | 3 | John R Jurgensen Company | $1,981,865 | $2,291,000 | +16% | -3.0% | ODOT |
| 250585 | D07-CHIP-FY26 (B) (CHIP SEAL) | District 7 | 3 | Shelly Company | $1,911,440 | $1,921,802 | +1.0% | -9.0% | ODOT |
| 254032 | FAI-US 22-03.68 (BRIDGE REPLACEMENT (1 BRIDGE)) | FAI | 4 | Alan Stone Co Inc | $1,795,146 | $1,823,052 | +2.0% | -2.0% | ODOT |
| 250606 | FRA-IR 670 SP FY26 Concrete (SPOT PATCHING / PAVEMENT REPAIR) | FRA | 2 | Shelly & Sands Inc | $1,793,153 | $1,982,943 | +11% | +9.0% | ODOT |
| 250586 | DEL-SR 229-00.12 (TWO LANE RESURFACING) | DEL | 3 | Shelly & Sands Inc | $1,686,864 | $1,789,621 | +6.0% | -12% | ODOT |
| 250592 | MIA-SR 571-IMP 06.38 (BIKEWAYS) | MIA | 7 | Eagle Bridge Co | $1,488,126 | $1,773,281 | +19% | -25% | ODOT |
| 250591 | MAR-SR 95-00.45 (TWO LANE RESURFACING) | MAR | 2 | Kokosing Construction Company Inc | $1,228,202 | $1,366,393 | +11% | -16% | ODOT |
| 250593 | MOE-TR 1004-02.27 (BRIDGE REPLACEMENT (1 BRIDGE)) | MOE | 6 | Alan Stone Co Inc | $1,206,919 | $1,315,052 | +9.0% | -17% | ODOT |
| 250602 | D03-GR FY2026 (GUARDRAIL REBUILDING) | District 3 | 2 | Lake Erie Construction Company | $1,023,825 | $1,098,959 | +7.0% | +4.0% | ODOT |
| 250609 | SCI-/JAC-52/93-35.72/15.48 (BRIDGE REPAIR) | SCI | 3 | Evers Steel Construction LLC | $983,011 | $1,097,805 | +12% | +23% | ODOT |
| 250588 | LAK-US 20-17.13 (FOUR LANE RESURFACING) | LAK | 6 | Ronyak Paving Inc | $900,574 | $970,902 | +8.0% | +1.0% | ODOT |
| 250580 | BEL-TR 428-00.30 (BRIDGE REPLACEMENT (1 BRIDGE)) | BEL | 4 | Stanley Miller Construction Company | $884,486 | $949,094 | +7.0% | -17% | ODOT |
| 250561 | LAK-SR 174-04.39 (TWO LANE RESURFACING) | LAK | 7 | Specialized Construction Inc | $747,366 | $754,765 | +1.0% | -20% | ODOT |
| 250605 | D08-R-W/R-FY26 (PAVEMENT MARKING) | District 8 | 3 | Oglesby Construction Inc | $673,856 | $747,000 | +11% | -27% | ODOT |
| 250596 | ROS-SR 138-00.26 (CHIP SEAL) | ROS | 5 | Runway Incorporated | $639,623 | $643,520 | +1.0% | -14% | ODOT |
| 250604 | D07-GR FY 2026 (GUARDRAIL REBUILDING) | District 7 | 2 | M P Dory Co | $511,844 | $514,820 | +1.0% | -9.0% | ODOT |
| 250608 | FRA-SR 3-16.59 Damage Repair (BRIDGE REPAIR) | FRA | 3 | Evers Steel Construction LLC | $493,258 | $553,926 | +12% | +75% | ODOT |
| 254034 | MOE-SR 78-08.35 (SLIDE REPAIR) | MOE | 4 | S.T.A.R.T., LLC | $426,626 | $463,758 | +9.0% | 0.0% | ODOT |
| 250589 | LAW-SR 243-04.38 (CULVERT REPLACEMENT) | LAW | 4 | Axis Civil Construction LLC | $289,778 | $327,549 | +13% | +11% | ODOT |
| 250603 | D03-RPM FY2026 (RAILROAD GRADE SEPARATION) | District 3 | 3 | Alpha Space Control LLC | $263,327 | $368,666 | +40% | -21% | ODOT |
| 250598 | TRU-US 422-08.01 (SIGNALIZATION) | TRU | 6 | Cornerstone Electric Inc | $204,472 | $208,078 | +2.0% | -14% | ODOT |
| 254033 | KNO-SR 3-25.94 (SIDEWALK) | KNO | 3 | Crawford Construction Company Inc | $154,585 | $158,025 | +2.0% | 0.0% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.