ODOT contract 250608 bid tabulation
FRA-SR 3-16.59 Damage Repair (BRIDGE REPAIR). Let by Ohio DOT on December 18, 2025, FRA. 3 bids received; low bid $493,258 by Evers Steel Construction LLC, +75% against the engineer's estimate of $282,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 16
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Evers Steel Construction LLC | $493,258 | Low | +75% |
| 2 | Advanced Painting & Contracting LLC | $553,926 | +12% | +96% |
| 3 | Vimas Painting Company Inc | $590,360 | +20% | +109% |
Engineer's estimate: $282,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Evers Steel Construction LLC | 2. Advanced Painting & Contracting LLC | 3. Vimas Painting Company Inc |
|---|---|---|---|---|---|---|
| 1 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 80 | $115.00 | $150.00 | $70.00 |
| 2 | Detour signing (614E12420) | LS | 1 | $10,000 | $4,192.27 | $8,000.00 |
| 3 | Portable changeable message sign, as per plan (614E18601) | SNMT | 2 | $3,000.00 | $996.62 | $1,500.00 |
| 4 | Portions of structure removed, as per plan (second (202E11401) | LB | 720 | $25.00 | $10.66 | $11.00 |
| 5 | Structural steel members, level UF, as per plan (513E10201) | LB | 720 | $25.00 | $14.21 | $30.00 |
| 6 | Structural steel, misc.: repair of damaged main ME (513E95000) | FT | 8 | $2,000.00 | $1,335.50 | $1,400.00 |
| 7 | Structural steel, misc.:repair of damaged main or (513E95000) | FT | 3 | $1,500.00 | $1,364.00 | $1,400.00 |
| 8 | Structural steel, misc.:repair of damaged members, (513E95030) | EACH | 5 | $150.00 | $511.50 | $550.00 |
| 9 | Field painting of damaged structural steel, as per plan (514E20001) | SF | 449 | $192.00 | $300.00 | $410.00 |
| 10 | Damage assessment (849E10000) | LS | 1 | $3,500.00 | $4,978.00 | $7,000.00 |
| 11 | Surface preparation (849E10500) | LS | 1 | $3,000.00 | $120,000 | $80,000 |
| 12 | Repairing damaged members by grinding (849E10600) | HR | 2 | $750.00 | $500.00 | $500.00 |
| 13 | Straightening damaged members (849E10700) | LS | 1 | $95,000 | $90,861 | $100,000 |
| 14 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $14,000 | $20,000 | $7,000.00 |
| 15 | Maintaining traffic (614E11000) | LS | 1 | $105,600 | $74,411 | $120,000 |
| 16 | Mobilization (624E10000) | LS | 1 | $102,000 | $54,550 | $27,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.