Kirila Contractors Inc: ODOT bid record

Kirila Contractors Inc submitted 16 bids on Ohio DOT contracts in the data, from 17 DEC 2020 to 18 DEC 2025, and was the low bidder on 4 of them (25%). When it was not low, its total sat a median +10% above the low bid.

Owner
Ohio DOT
Low bid volume
$12,192,687
Latest bid
18 DEC 2025
Data through
12 NOV 2026
16Bids
4Low bids
25Win rate, percent
+10%Median gap to the low bid when not low, 12 bids

By year

YearBidsLow bidsWin rate
2020100%
20215240%
2022200%
2023300%
2024200%
20253267%
Kirila Contractors Inc, ODOT: bids and low bids by year of letting

By county

CountyBidsLow bidsWin rate
TRU10440%
COL300%
MAH200%
POR100%
Kirila Contractors Inc, ODOT: bids and low bids by county

Pay items where it is most often lowest

Pay itemCodeUnitLines bidLowest on the lineIts median priceAll bidders' median
Sealing of concrete surfaces (epoxy-urethane)512E10100SY3127 (87%)$40.00$34.00
Ground mounted support, no. 2 post630E02100FT2424 (100%)$10.00$15.00
Treating concrete bridge decks with gravity fed resin512E73500SY2322 (96%)$9.00$11.00
Erosion control832E30000EACH2121 (100%)$1.00$1.00
Patching concrete structure, as per plan519E11101SF2220 (91%)$100.00$150.00
Sign, flat sheet630E80100SF2519 (76%)$20.00$24.00
Removal of ground mounted post support and disposal630E86002EACH2818 (64%)$15.00$23.50
Removal of ground mounted sign and disposal630E84900EACH2818 (64%)$25.00$20.00
Law enforcement officer with patrol car for assistance614E11110HR1817 (94%)$55.00$80.00
Removal of existing pavement marking512E74500FT1615 (94%)$3.00$3.00
Sign, flat sheet630E80100SF1515 (100%)$20.00$20.00
Removal of existing coatings from concrete surfaces512E74000SY1614 (88%)$25.00$27.00
Kirila Contractors Inc, ODOT: pay items where its unit price was the lowest on the line

A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.

Who it meets most

FirmContracts in commonThat firm ranked ahead
Shelly & Sands Inc1510 of 15
Karvo Companies Inc133 of 13
Shelly Company136 of 13
Chagrin Valley Paving Inc30 of 3
Ronyak Paving Inc21 of 2
S E T Inc20 of 2
NLS Paving, Inc22 of 2
A P O'Horo Company21 of 2
Eclipse Co LLC20 of 2
Barbicas Construction Company Inc20 of 2
Kirila Contractors Inc, ODOT: the firms on the same contracts most often

Latest bids

LetContractCountyProjectRankIts bidAgainst the low bid
18 DEC 2025250599TRUTRU-US 62-04.56 (FOUR LANE RESURFACING)1 of 4$4,111,119Low, 0.0% under the second
28 AUG 2025250398TRUTRU-SR 46-07.81 (PARTS 1-4) (INTERSECTION)1 of 6$6,206,766Low, 3.0% under the second
27 FEB 2025250127MAHMAH-SR 14/SR 165-00.00/01.67 (MINOR RECONSTRUCTION)4 of 4$4,079,766+6.0%
14 NOV 2024240516COLCOL-SR-SR 9/VAR-14.72/VAR (TWO LANE RESURFACING)2 of 5$830,370+2.0%
17 OCT 2024240474TRUTRU-SR 7/SR 7D-08.74/00.00 (TWO LANE RESURFACING)2 of 5$1,573,000+5.0%
12 OCT 2023230499TRUTRU-SR 5-14.36 (TWO LANE RESURFACING)3 of 5$1,622,678+8.0%
30 MAR 2023230195TRUTRU-Ellsworth-Bailey Rd (TWO LANE RESURFACING)2 of 6$359,183+1.0%
26 JAN 2023230061TRUTRU-US 62-07.47 (INTERSECTION)2 of 5$2,157,879+12%
10 MAR 2022220151TRUTRU-SR 5-08.30 (FOUR LANE RESURFACING)3 of 4$3,810,966+17%
13 JAN 2022220003COLCOL-SR 267-01.74 (TWO LANE RESURFACING)5 of 6$1,176,308+15%
16 DEC 2021210674COLCOL-SR 11-15.99 (FOUR LANE RESURFACING)5 of 5$3,647,731+28%
02 DEC 2021210640PORPOR-SR 44/VAR-16.48/VAR (PART 1, 2, 3) (TWO LANE RESURFACING)5 of 6$6,549,828+24%
30 SEP 2021210513MAHMAH-US 62/SR 7-13.16/11.26 (FOUR LANE RESURFACING)2 of 5$1,384,000+8.0%
29 APR 2021210283TRUTRU-SR 11-07.68 (TWO LANE RESURFACING)1 of 4$1,655,396Low, 16% under the second
15 APR 2021210246TRUTRU-SR 46-06.50 (INTERSECTION)1 of 4$219,406Low, 7.0% under the second
17 DEC 2020200606TRUTRU-SR 82-22.74 (FOUR LANE RESURFACING)2 of 5$5,917,006+14%
Kirila Contractors Inc: latest ODOT bids in the data

How this record was read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
  • The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
  • A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.

A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.

Your own bid history, read the same way