ODOT letting results, January 26, 2023
34 contracts let by Ohio DOT on January 26, 2023, $87,079,403 in low bids, a median of 4 bidders per contract. On the 34 with an engineer's estimate, the low bid came in under it 22 times; median low bid -7.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 34
- Low bids, total
- $87,079,403
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 230002 | DEL-US 36-11.03 (BRIDGE REPLACEMENT (1 BRIDGE)) | DEL | 3 | Shelly & Sands Inc | $31,104,829 | $34,498,927 | +11% | -8.0% | ODOT |
| 230046 | CUY-SR 17-07.09 (MAJOR RECONSTRUCTION) | CUY | 5 | Ronyak Paving Inc | $11,521,176 | $11,896,966 | +3.0% | +16% | ODOT |
| 230050 | HAN-SR 15/CR 180-19.56/00.21 (BRIDGE REPLACEMENT (1 BRIDGE)) | HAN | 2 | Eagle Bridge Co | $4,839,606 | $5,263,031 | +9.0% | -18% | ODOT |
| 230040 | ALL-SR 66-11.22 (MINOR RECONSTRUCTION) | ALL | 3 | Underground Utilities Inc | $3,356,163 | $3,539,031 | +5.0% | +4.0% | ODOT |
| 230041 | ATH-SR 681-07.24 and Various (TWO LANE RESURFACING) | ATH | 2 | Shelly & Sands Inc | $3,169,962 | $3,233,602 | +2.0% | +1.0% | ODOT |
| 230057 | PIC-US 22-17.12 (MINOR RECONSTRUCTION) | PIC | 2 | Complete General Construction Company | $3,117,056 | $3,262,831 | +5.0% | +21% | ODOT |
| 230054 | MAH-SR 165/SR 534-05.46/03.02 (TWO LANE RESURFACING) | MAH | 4 | Shelly & Sands Inc | $3,003,121 | $3,153,345 | +5.0% | -1.0% | ODOT |
| 230045 | CUY-IR 90-18.72 (FOUR LANE RESURFACING) | CUY | 3 | Karvo Companies Inc | $2,648,000 | $2,653,618 | 0.0% | +20% | ODOT |
| 230059 | POR-IR 76-20.05 Slide (SLIDE REPAIR) | POR | 5 | A P O'Horo Company | $2,454,000 | $2,595,181 | +6.0% | -23% | ODOT |
| 230047 | ERI-SR 4-04.65 (INTERSECTION) | ERI | 4 | Great Lakes Demolition Company | $2,409,517 | $3,217,752 | +34% | -15% | ODOT |
| 230065 | D01-PM FY23 (PAVEMENT MARKING) | District 1 | 2 | The Aero-Mark Company LLC | $2,125,000 | $2,178,922 | +3.0% | +10% | ODOT |
| 230061 | TRU-US 62-07.47 (INTERSECTION) | TRU | 4 of 5 | A P O'Horo Company | $1,929,000 | $2,157,879 | +12% | -18% | ODOT |
| 230067 | D05-PM FY2023 (B) Fast Dry West (PAVEMENT MARKING) | District 5 | 2 | Dura Mark Inc | $1,900,000 | $1,944,980 | +2.0% | -3.0% | ODOT |
| 230055 | MRG-SR 376-01.10 (SLIDE REPAIR) | MRG | 4 | Shelly & Sands Inc | $1,334,853 | $1,374,497 | +3.0% | -15% | ODOT |
| 230060 | POR-SR 14-06.43 (MINOR WIDENING) | POR | 5 | Shelly & Sands Inc | $1,326,861 | $1,439,696 | +9.0% | +5.0% | ODOT |
| 230071 | MAH-IR 76-06.04 (INTERCHANGE) | MAH | 4 | Shelly & Sands Inc | $1,215,042 | $1,279,000 | +5.0% | -8.0% | ODOT |
| 230052 | LAK-SR 86-01.68 (FOUR LANE RESURFACING) | LAK | 5 | Cole Burton Contractors, LLC | $1,079,980 | $1,150,105 | +6.0% | -2.0% | ODOT |
| 230070 | FRA-MOW FY23 (MOWING) | FRA | 1 | Tom Mayle & Sons Construction Inc | $859,000 | -7.0% | ODOT | ||
| 230053 | LAK-US 20-14.24/VAR (SIGNALIZATION) | LAK | 2 | Perram Electric Inc | $797,240 | $1,153,000 | +45% | +17% | ODOT |
| 230068 | D08-/D07 Mowing FY2023 (B) (MOWING) | District 8 | 1 | Linkel Company | $764,220 | +3.0% | ODOT | ||
| 230044 | CUY-IR 480-05.40/10.54 RampClear (PART 1 AND PART 2) (MINOR WIDENING) | CUY | 3 | Cook Paving & Construction Co Inc | $674,600 | $810,206 | +20% | +26% | ODOT |
| 230042 | AUG-SR 65-10.62 (TWO LANE RESURFACING) | AUG | 2 | Shelly Company | $665,429 | $832,000 | +25% | +3.0% | ODOT |
| 230056 | MUS-TR 49-00.56 (Multiuse Path) (BIKEWAYS) | MUS | 6 | Scioto Valley Paving LLC | $636,782 | $668,278 | +5.0% | -8.0% | ODOT |
| 230048 | FAI-SR 37-27.41 (SLIDE REPAIR) | FAI | 5 | Complete General Construction Company | $569,068 | $798,684 | +40% | -20% | ODOT |
| 230062 | TUS-SR 800-03.82 (DEMOLITION) | TUS | 7 | Dennison Bridge Inc | $545,549 | $679,034 | +24% | -24% | ODOT |
| 230058 | PIK-CR 77-02.07 OBPP (BRIDGE REPLACEMENT (1 BRIDGE)) | PIK | 10 | Allard Excavation LLC | $496,696 | $533,912 | +7.0% | -8.0% | ODOT |
| 230063 | WAS-Front Street-00.33 (TWO LANE RESURFACING) | WAS | 1 | Shelly & Sands Inc | $420,424 | +9.0% | ODOT | ||
| 230072 | SEN-US 23-04.88 Str Replacmnt (CULVERT REPLACEMENT) | SEN | 5 | Adena Corporation | $401,455 | $457,983 | +14% | -9.0% | ODOT |
| 230064 | WYA-Toledo Street Bridge (CULVERT REPLACEMENT) | WYA | 2 | Crawford Construction Company Inc | $364,148 | $396,815 | +9.0% | -11% | ODOT |
| 230069 | D11-CS FY2023 (CRACK SEALING) | District 11 | 4 of 6 | $322,555 | $326,169 | +1.0% | -9.0% | ODOT | |
| 230066 | D03-MOW FY2023 (C) (MOWING) | District 3 | 2 | Linkel Company | $295,150 | $389,080 | +32% | -6.0% | ODOT |
| 230043 | CUY-Bennett Road Path TLCI (BIKEWAYS) | CUY | 6 | Scioto Valley Paving LLC | $278,221 | $293,796 | +6.0% | -8.0% | ODOT |
| 230051 | HIG-SR 73-17.61 & 17.66 Culvert (CULVERT REPLACEMENT) | HIG | 9 | Scioto Valley Paving LLC | $264,264 | $294,156 | +11% | -6.0% | ODOT |
| 230049 | HAM-IR 275-07.50 (CULVERT REPLACEMENT) | HAM | 4 | Sunesis Construction Co | $190,435 | $218,385 | +15% | -26% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out.