A P O'Horo Company submitted 24 bids on Ohio DOT contracts in the data, from 23 JAN 2020 to 12 NOV 2026, and was the low bidder on 14 of them (58%). When it was not low, its total sat a median +6.0% above the low bid.
- Owner
- Ohio DOT
- Low bid volume
- $28,154,000
- Latest bid
- 12 NOV 2026
- Data through
- 12 NOV 2026
By year
| Year | Bids | Low bids | Win rate |
|---|---|---|---|
| 2020 | 5 | 4 | 80% |
| 2021 | 2 | 0 | 0% |
| 2022 | 3 | 0 | 0% |
| 2023 | 6 | 4 | 67% |
| 2024 | 2 | 2 | 100% |
| 2025 | 4 | 2 | 50% |
| 2026 | 2 | 2 | 100% |
By county
| County | Bids | Low bids | Win rate |
|---|---|---|---|
| COL | 5 | 3 | 60% |
| TRU | 5 | 2 | 40% |
| MAH | 4 | 2 | 50% |
| ATB | 3 | 3 | 100% |
| JEF | 3 | 2 | 67% |
| POR | 3 | 2 | 67% |
| LAK | 1 | 0 | 0% |
Pay items where it is most often lowest
| Pay item | Code | Unit | Lines bid | Lowest on the line | Its median price | All bidders' median |
|---|---|---|---|---|---|---|
| Erosion control | 832E30000 | EACH | 27 | 27 (100%) | $1.00 | $1.00 |
| Topsoil | 659E00300 | CY | 24 | 14 (58%) | $30.00 | $45.00 |
| Portable changeable message sign, as per plan | 614E18601 | SNMT | 15 | 14 (93%) | $500.00 | $950.00 |
| Water | 659E35000 | MGAL | 25 | 12 (48%) | $1.00 | $1.00 |
| Guardrail removed | 202E38000 | FT | 18 | 12 (67%) | $2.00 | $2.50 |
| Porous backfill with geotextile fabric | 518E21200 | CY | 17 | 12 (71%) | $85.00 | $125.00 |
| Excavation | 203E10000 | CY | 27 | 11 (41%) | $22.00 | $27.00 |
| Geotextile fabric | 204E50000 | SY | 21 | 11 (52%) | $2.00 | $2.12 |
| Sign, flat sheet | 630E80100 | SF | 18 | 11 (61%) | $22.50 | $24.00 |
| Guardrail, type MGS | 606E15050 | FT | 13 | 11 (85%) | $20.40 | $22.73 |
| Center line | 646E10200 | MI | 13 | 11 (85%) | $15,567 | $12,144 |
| 2" preformed expansion joint filler | 516E13900 | SF | 12 | 11 (92%) | $8.50 | $12.00 |
A line counts when the firm priced it and at least one other bidder did too; the lowest unit price on the line counts whoever won the contract. Token prices and bids over three times the low bid are left out.
Who it meets most
| Firm | Contracts in common | That firm ranked ahead |
|---|---|---|
| Shelly & Sands Inc | 17 | 5 of 17 |
| Marucci & Gaffney Excavating Co | 15 | 2 of 15 |
| Eclipse Co LLC | 8 | 1 of 8 |
| S E T Inc | 7 | 0 of 7 |
| Rudzik Excavating Inc | 6 | 1 of 6 |
| J D Williamson Construction Co Inc | 6 | 0 of 6 |
| Lockhart Concrete Co | 5 | 1 of 5 |
| Great Lakes Construction Co | 4 | 0 of 4 |
| Ohio-West Virginia Excavating Co | 4 | 1 of 4 |
| Mike Pusateri Excavating Inc | 3 | 1 of 3 |
Latest bids
| Let | Contract | County | Project | Rank | Its bid | Against the low bid |
|---|---|---|---|---|---|---|
| 12 NOV 2026 | 260512 | TRU | TRU-SR 534-22.36/26.04 (BRIDGE REPAIR) | 1 of 5 | $1,613,000 | Low, 1.0% under the second |
| 11 JUN 2026 | 260282 | ATB | ATB-/TRU-SR 7/VAR-18.62/VAR (PART 1, 2, 3) (BRIDGE REPAIR) | 1 of 4 | $3,814,000 | Low, 2.0% under the second |
| 23 OCT 2025 | 250490 | COL | COL-SR 164-01.66 (CULVERT REPLACEMENT) | 4 of 9 | $491,000 | +3.0% |
| 09 OCT 2025 | 250467 | MAH | MAH-US 422-03.13 (BRIDGE REPAIR) | 1 of 4 | $2,084,000 | Low, 24% under the second |
| 25 SEP 2025 | 250441 | POR | POR-SR 305-02.43/02.58 (BRIDGE REPAIR) | 1 of 9 | $1,212,000 | Low, 4.0% under the second |
| 28 AUG 2025 | 250398 | TRU | TRU-SR 46-07.81 (PARTS 1-4) (INTERSECTION) | 2 of 6 | $6,417,000 | +3.0% |
| 12 SEP 2024 | 240419 | MAH | MAH-IR 680-09.30 Noise Walls (NOISE WALLS) | 1 of 7 | $3,984,000 | Low, 2.0% under the second |
| 04 APR 2024 | 240168 | COL | COL-US 30-34.07 (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 3 | $3,748,000 | Low, 12% under the second |
| 27 APR 2023 | 230252 | COL | COL-Park Drive Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 2 | $936,000 | Low, 10% under the second |
| 27 APR 2023 | 230261 | JEF | JEF-SR 164-08.80 (SLIDE REPAIR) | 5 of 5 | $598,000 | +40% |
| 23 FEB 2023 | 233001 | ATB | ATB-SR 534-12.06 (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 3 | $1,833,000 | Low, 3.0% under the second |
| 26 JAN 2023 | 230059 | POR | POR-IR 76-20.05 Slide (SLIDE REPAIR) | 1 of 5 | $2,454,000 | Low, 6.0% under the second |
| 26 JAN 2023 | 230061 | TRU | TRU-US 62-07.47 (INTERSECTION) | 1 of 5 | $1,929,000 | Low, 12% under the second |
| 26 JAN 2023 | 230071 | MAH | MAH-IR 76-06.04 (INTERCHANGE) | 2 of 4 | $1,279,000 | +5.0% |
| 12 MAY 2022 | 220299 | MAH | MAH-McGaffney St Extension Ph 2 (NEW CONSTRUCTION) | 2 of 7 | $383,000 | +11% |
| 28 APR 2022 | 220276 | LAK | LAK-SR 2-11.41 Deck (BRIDGE REPAIR) | 2 of 3 | $1,684,000 | +2.0% |
| 13 JAN 2022 | 223001 | TRU | TRU-SR 46-25.07 (BRIDGE REPAIR) | 2 of 5 | $893,893 | +4.0% |
| 11 FEB 2021 | 210100 | TRU | TRU-Warner Rd Bridge (BRIDGE REPLACEMENT (1 BRIDGE)) | 2 of 7 | $1,244,000 | +6.0% |
| 28 JAN 2021 | 210075 | POR | POR-D04 POR IR-76 RA Parking Lots (SPOT SAFETY) | 5 of 12 | $3,620,000 | +12% |
| 30 JUL 2020 | 200411 | JEF | JEF-SR 164-09.40 (SLIDE REPAIR) | 1 of 9 | $209,000 | Low, 19% under the second |
| 18 JUN 2020 | 200351 | JEF | JEF-SR 213-18.43 (BRIDGE REPAIR) | 1 of 5 | $634,000 | Low, 15% under the second |
| 27 FEB 2020 | 200048 | COL | COL-SR 7-26.34 (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 4 | $2,417,000 | Low, 17% under the second |
| 13 FEB 2020 | 200045 | ATB | ATB-US 20/SR 45-19.13/08.28 (BRIDGE REPLACEMENT (1 BRIDGE)) | 1 of 8 | $1,287,000 | Low, 4.0% under the second |
| 23 JAN 2020 | 207002 | COL | COL-US 30-33.26 (SLIDE REPAIR) | 8 of 11 | $676,000 | +102% |
How this record was read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Every bid counted here matched its published total to within one dollar; ODOT's rank decides who was low.
- The gap to the low bid is the firm's total over the low total, minus one, on contracts it did not win, leaving out bids over three times the low bid.
- A record covers the lettings in the data, not every contract the firm ever bid. Coverage by year is on the state page.
A name split in two, or a figure that does not match the owner's tabulation? Write to mehdi@miragemetrics.com and we correct it.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.