ODOT letting results, September 25, 2025
30 contracts let by Ohio DOT on September 25, 2025, $60,197,454 in low bids, a median of 3 bidders per contract. On the 29 with an engineer's estimate, the low bid came in under it 19 times; median low bid -4.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 30
- Low bids, total
- $60,197,454
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250428 | BRO-US 52-12.43 (BRIDGE REPLACEMENT (1 BRIDGE)) | BRO | 1 | Complete General Construction Company | $5,107,112 | -3.0% | ODOT | ||
| 250431 | CLA-PAVE-FY26 (B) (FOUR LANE RESURFACING) | CLA | 3 | Shelly Company | $4,772,559 | $5,469,036 | +15% | -9.0% | ODOT |
| 250443 | UNI-SR 38-03.21 (BRIDGE REPAIR) | UNI | 4 | Complete General Construction Company | $4,332,873 | $4,386,824 | +1.0% | +39% | ODOT |
| 250426 | ADA-SR 32-00.00 | ADA | 2 | Shelly Company | $4,018,510 | $4,425,635 | +10% | ODOT | |
| 250442 | TRU-W Reserve Greenway Phase 4 (BIKEWAYS) | TRU | 3 | Marucci & Gaffney Excavating Co | $3,566,662 | $3,916,687 | +10% | 0.0% | ODOT |
| 250438 | HEN-/LUC-US 24-15.86/-0.00 CPR (SPOT PATCHING / PAVEMENT REPAIR) | HEN | 8 | DOT Diamond Core Drilling Inc | $3,428,026 | $3,535,739 | +3.0% | -4.0% | ODOT |
| 250435 | DEL-SR 315-05.00/06.40/08.10 (SLIDE REPAIR) | DEL | 6 | George J Igel & Co Inc | $3,329,777 | $4,016,815 | +21% | -14% | ODOT |
| 250439 | MIA-SR 41-11.32 (INTERSECTION) | MIA | 6 | R B Jergens Contractors Inc | $3,326,915 | $3,483,569 | +5.0% | -5.0% | ODOT |
| 250440 | MUS-SR 60-08.03 (FOUR LANE RESURFACING) | MUS | 3 | Shelly & Sands Inc | $3,239,033 | $3,945,069 | +22% | -14% | ODOT |
| 250427 | ALL-/HAN-IR 75-00.00/14.10 (MICROSURFACING) | ALL | 2 | Pavement Maintenance Systems LLC | $3,185,151 | $5,874,364 | +84% | +10% | ODOT |
| 250434 | D08-Bridge Maintenance FY2026 (BRIDGE REPAIR) | District 8 | 2 | Complete General Construction Company | $2,785,148 | $3,892,942 | +40% | +14% | ODOT |
| 250430 | BUT-SR 503-00.00 (TWO LANE RESURFACING) | BUT | 2 | John R Jurgensen Company | $2,642,217 | $2,697,287 | +2.0% | +7.0% | ODOT |
| 250432 | CLI-Davids Drive Reconstruction (TWO LANE RESURFACING) | CLI | 3 | Fillmore Construction | $1,578,400 | $1,893,720 | +20% | -15% | ODOT |
| 250450 | D11-PM-FY2026(B) (PAVEMENT MARKING) | District 11 | 4 | Alpha Space Control LLC | $1,536,822 | $1,748,581 | +14% | -28% | ODOT |
| 250445 | WOO-MR 746-00.05 Pemberville Brdg (BRIDGE REPLACEMENT (1 BRIDGE)) | WOO | 7 | E S Wagner Company | $1,515,460 | $1,587,120 | +5.0% | -22% | ODOT |
| 250444 | WAS-SR 339-08.57 (TWO LANE RESURFACING) | WAS | 1 | Shelly & Sands Inc | $1,484,484 | -1.0% | ODOT | ||
| 250436 | GEA-SR 87-02.73 (TWO LANE RESURFACING) | GEA | 6 | Ronyak Paving Inc | $1,361,400 | $1,584,401 | +16% | -13% | ODOT |
| 250433 | COL-SR 39/SR 45-13.06/00.37 (TWO LANE RESURFACING) | COL | 4 | NLS Paving, Inc | $1,348,480 | $1,390,170 | +3.0% | +1.0% | ODOT |
| 250441 | POR-SR 305-02.43/02.58 (BRIDGE REPAIR) | POR | 9 | A P O'Horo Company | $1,212,000 | $1,264,867 | +4.0% | -21% | ODOT |
| 250448 | D08-Mowing FY2026 (A) (MOWING) | District 8 | 2 | Opterra Solutions, Inc | $805,540 | $886,720 | +10% | -3.0% | ODOT |
| 250453 | BEL-SR 7-18.24 (BRIDGE REPAIR) | BEL | 2 | Evers Steel Construction LLC | $789,515 | $829,994 | +5.0% | +58% | ODOT |
| 250447 | D05-CS FY2026 (CRACK SEALING) | District 5 | 1 | Scodeller Construction Inc | $771,929 | -1.0% | ODOT | ||
| 250429 | BRO-SR 131-00.07 (CULVERT REPLACEMENT) | BRO | 6 | Coopers Excavating LLC | $764,901 | $779,496 | +2.0% | -9.0% | ODOT |
| 254026 | SAN-SR 523-03.07 Brdg Rehab (BRIDGE REPAIR) | SAN | 4 | Great Lakes Demolition Company | $691,224 | $771,018 | +12% | -6.0% | ODOT |
| 250437 | LOG-US 33-20.86 (SLIDE REPAIR) | LOG | 4 | Eagle Bridge Co | $596,094 | $632,711 | +6.0% | +19% | ODOT |
| 254025 | NOB-SR 147-16.82 (CULVERT REPLACEMENT) | NOB | 4 | Buds Inc | $572,949 | $591,089 | +3.0% | -8.0% | ODOT |
| 250449 | D11-PM-FY2026(A) (PAVEMENT MARKING) | District 11 | 3 | Alpha Space Control LLC | $558,257 | $789,153 | +41% | -21% | ODOT |
| 254024 | GRE-CLI Culverts FY26 (CULVERT REPLACEMENT) | GRE | 2 | Axis Civil Construction LLC | $382,916 | $486,307 | +27% | +7.0% | ODOT |
| 250451 | ERI-Sheldon Marsh SNP FY2026 (PARKING AREAS) | ERI | 2 | Erie Blacktop Inc | $282,956 | $471,182 | +67% | +10% | ODOT |
| 250446 | D03-TSG Radar FY2026 (SIGNALIZATION) | District 3 | 6 | Perram Electric Inc | $210,145 | $231,000 | +10% | -43% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.