ODOT contract 250445 bid tabulation
WOO-MR 746-00.05 Pemberville Brdg (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on September 25, 2025, WOO. 7 bids received; low bid $1,515,460 by E S Wagner Company, -22% against the engineer's estimate of $1,954,700.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 75
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | E S Wagner Company | $1,515,460 | Low | -22% |
| 2 | Vernon Nagel Inc | $1,587,120 | +5.0% | -19% |
| 3 | Miller Bros Const Inc | $1,596,201 | +5.0% | -18% |
| 4 | R G Zachrich Construction Inc | $1,652,849 | +9.0% | -15% |
| 5 | R & I Construction Inc | $1,677,592 | +11% | -14% |
| 6 | D2 Excavating LLC | $1,699,196 | +12% | -13% |
| 7 | Great Lakes Demolition Company | $1,775,253 | +17% | -9.0% |
Engineer's estimate: $1,954,700.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. E S Wagner Company | 2. Vernon Nagel Inc | 3. Miller Bros Const Inc | 4. R G Zachrich Construction Inc | 5. R & I Construction Inc | 6. D2 Excavating LLC |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $10,000 | $4,500.00 | $10,000 | $27,000 | $10,000 |
| 2 | Pavement removed (202E23000) | SY | 309 | $10.25 | $16.00 | $8.00 | $10.00 | $8.00 | $15.00 |
| 3 | Walk removed (202E30000) | SF | 674 | $2.25 | $5.00 | $2.14 | $3.50 | $3.00 | $15.00 |
| 4 | Concrete barrier removed, as per plan (202E30701) | FT | 40 | $17.50 | $15.00 | $21.55 | $56.00 | $10.00 | $10.00 |
| 5 | Removal misc.:metal railing (202E98200) | FT | 47 | $5.70 | $10.00 | $8.82 | $12.00 | $15.00 | $10.00 |
| 6 | Excavation (203E10000) | CY | 51 | $55.00 | $20.00 | $31.20 | $25.00 | $20.00 | $25.00 |
| 7 | Embankment (203E20000) | CY | 22 | $105.00 | $20.00 | $50.36 | $25.00 | $20.00 | $25.00 |
| 8 | Guardrail, type MGS (606E15050) | FT | 25 | $23.00 | $23.00 | $23.00 | $23.00 | $23.00 | $25.00 |
| 9 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 | $1,450.00 | $1,500.00 |
| 10 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 1 | $2,350.00 | $2,350.00 | $2,350.00 | $2,350.00 | $2,350.00 | $2,500.00 |
| 11 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 1 | $2,350.00 | $2,350.00 | $2,350.00 | $2,350.00 | $2,350.00 | $2,500.00 |
| 12 | Fence, misc.:temporary orange plastic construction (607E98000) | FT | 500 | $5.85 | $2.19 | $5.19 | $15.00 | $10.00 | $5.00 |
| 13 | Fence, misc.:wood fence (607E98000) | FT | 32 | $72.00 | $170.00 | $170.00 | $170.00 | $170.00 | $250.00 |
| 14 | 4" concrete walk (608E10000) | SF | 510 | $11.00 | $11.00 | $14.13 | $18.00 | $15.00 | $16.00 |
| 15 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 12 | $145.00 | $170.00 | $221.78 | $150.00 | $100.00 | $170.00 |
| 16 | Topsoil furnished and placed (653E10000) | CY | 189 | $67.00 | $30.00 | $18.53 | $50.00 | $50.00 | $65.00 |
| 17 | Seeding and mulching (659E10000) | SY | 1,699 | $1.80 | $1.80 | $1.80 | $1.80 | $3.50 | $7.25 |
| 18 | Repair seeding and mulching (659E14000) | SY | 85 | $1.80 | $1.80 | $1.80 | $1.80 | $0.50 | $1.00 |
| 19 | Inter-seeding (659E15000) | SY | 85 | $1.00 | $1.00 | $1.00 | $1.00 | $0.10 | $1.00 |
| 20 | Commercial fertilizer (659E20000) | TON | 0.25 | $850.00 | $850.00 | $850.00 | $850.00 | $538.00 | $1,000.00 |
| 21 | Water (659E35000) | MGAL | 9 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 22 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 23 | Concrete masonry (602E20000) | CY | 1 | $2,200.00 | $1,200.00 | $1,899.86 | $2,200.00 | $1,500.00 | $1,200.00 |
| 24 | 6" unclassified pipe underdrains with geotextile fabric (605E13410) | FT | 102 | $24.00 | $15.00 | $26.22 | $23.00 | $12.00 | $25.00 |
| 25 | 6" conduit, type F for underdrain outlets (611E00510) | FT | 40 | $29.00 | $18.00 | $51.57 | $30.00 | $12.00 | $25.00 |
| 26 | 12" conduit, type B (611E04400) | FT | 42 | $130.00 | $75.00 | $75.69 | $112.00 | $35.00 | $50.00 |
| 27 | 12" conduit, type C (611E04600) | FT | 114 | $115.00 | $65.00 | $62.15 | $95.00 | $35.00 | $50.00 |
| 28 | Catch basin, no. 3A (611E98180) | EACH | 4 | $3,000.00 | $2,600.00 | $3,264.25 | $3,850.00 | $3,000.00 | $2,800.00 |
| 29 | Manhole, no. 3 (611E99574) | EACH | 2 | $3,800.00 | $3,200.00 | $6,107.69 | $7,000.00 | $3,500.00 | $9,000.00 |
| 30 | Subgrade compaction (204E10000) | SY | 257 | $4.75 | $1.00 | $2.72 | $4.00 | $2.00 | $3.00 |
| 31 | Partial depth pavement repair (441) (251E01010) | CY | 13 | $465.00 | $465.00 | $465.00 | $465.00 | $465.00 | $470.00 |
| 32 | Pavement repair (253E02000) | CY | 6 | $575.00 | $575.00 | $575.00 | $575.00 | $575.00 | $600.00 |
| 33 | Pavement planing, asphalt concrete, 3" (254E01000) | SY | 57 | $30.00 | $30.00 | $30.00 | $30.00 | $30.00 | $55.00 |
| 34 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 26 | $380.00 | $380.00 | $380.00 | $380.00 | $380.00 | $395.00 |
| 35 | Aggregate base (304E20000) | CY | 43 | $40.00 | $70.00 | $59.54 | $115.00 | $70.00 | $70.00 |
| 36 | Tack coat (407E10000) | GAL | 33 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $2.00 |
| 37 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 24 | $425.00 | $425.00 | $425.00 | $425.00 | $425.00 | $450.00 |
| 38 | Curb, type 4-C, as per plan (609E24511) | FT | 88 | $56.45 | $35.00 | $41.50 | $55.00 | $50.00 | $95.00 |
| 39 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $22.00 | $50.00 | $50.00 | $50.00 | $25.00 | $50.00 |
| 40 | Removal of ground mounted post support and disposal (630E86002) | EACH | 2 | $22.00 | $50.00 | $50.00 | $50.00 | $25.00 | $50.00 |
| 41 | Water (616E10000) | MGAL | 1 | $45.00 | $10.00 | $64.38 | $50.00 | $1.00 | $1,000.00 |
| 42 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $107,645 | $147,000 | $120,549 | $120,000 | $215,000 | $100,000 |
| 43 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $109,500 | $76,000 | $106,891 | $36,000 | $50,000 | $200,000 |
| 44 | Unclassified excavation, as per plan (503E21101) | CY | 200 | $77.00 | $100.00 | $83.28 | $150.00 | $70.00 | $200.00 |
| 45 | Epoxy coated steel reinforcement (509E10000) | LB | 33,561 | $1.61 | $1.50 | $1.74 | $1.50 | $2.00 | $2.00 |
| 46 | Class QC2 concrete, superstructure (511E31610) | CY | 98 | $1,038.00 | $1,000.00 | $907.82 | $1,159.00 | $1,000.00 | $1,000.00 |
| 47 | Class QC1 concrete, pier above footings (511E41010) | CY | 24 | $1,664.00 | $1,300.00 | $1,773.07 | $2,000.00 | $1,500.00 | $1,200.00 |
| 48 | Class QC1 concrete, abutment including footing (511E43510) | CY | 81 | $777.00 | $650.00 | $775.54 | $830.00 | $1,000.00 | $1,250.00 |
| 49 | Class QC2 concrete, sidewalk (511E51510) | CY | 26 | $702.00 | $550.00 | $491.98 | $715.00 | $1,000.00 | $50.00 |
| 50 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 556 | $28.50 | $26.00 | $22.72 | $35.00 | $35.00 | $30.00 |
| 51 | Prestressed concrete composite box beam bridge members, level 1, CB21-48, as per plan (515E12051) | EACH | 14 | $14,270 | $17,100 | $15,870 | $17,600 | $15,900 | $19,500 |
| 52 | Prestressed concrete composite box beam bridge members, level 1, CB21-48, as per plan (515E12051) | EACH | 7 | $16,146 | $20,500 | $21,397 | $17,600 | $15,900 | $20,000 |
| 53 | Armorless preformed joint seal (516E10010) | FT | 53 | $57.00 | $35.00 | $54.32 | $160.00 | $50.00 | $20.00 |
| 54 | 2" preformed expansion joint filler (516E13900) | SF | 26 | $6.30 | $8.00 | $12.79 | $13.50 | $8.00 | $20.00 |
| 55 | Semi-integral abutment expansion joint seal (516E14020) | FT | 80 | $34.30 | $50.00 | $30.23 | $42.00 | $30.00 | $56.00 |
| 56 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 28 | $577.00 | $750.00 | $650.98 | $725.00 | $600.00 | $660.00 |
| 57 | Elastomeric bearing with internal laminates and load plate, as per plan (516E44101) | EACH | 56 | $586.00 | $750.00 | $660.18 | $655.00 | $600.00 | $700.00 |
| 58 | Railing (concrete parapet with twin steel tube railing) (517E75120) | FT | 162 | $306.00 | $315.00 | $300.62 | $300.00 | $151.00 | $165.00 |
| 59 | Railing (concrete parapet with twin steel tube railing), as per plan (517E75121) | FT | 162 | $277.00 | $315.00 | $300.62 | $300.00 | $151.00 | $165.00 |
| 60 | Porous backfill with geotextile fabric (518E21200) | CY | 60 | $115.00 | $100.00 | $119.06 | $130.00 | $100.00 | $200.00 |
| 61 | 6" perforated corrugated plastic pipe (518E40000) | FT | 97 | $8.00 | $10.00 | $6.60 | $15.00 | $12.00 | $20.00 |
| 62 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 48 | $11.50 | $10.00 | $11.90 | $15.00 | $12.00 | $20.00 |
| 63 | Drilled shafts, 30" diameter, into bedrock (524E94604) | FT | 56 | $1,028.00 | $1,260.00 | $1,331.06 | $1,331.87 | $1,900.00 | $800.00 |
| 64 | Drilled shafts, 36" diameter, above bedrock (524E94702) | FT | 40 | $799.00 | $500.00 | $496.00 | $815.36 | $496.00 | $700.00 |
| 65 | Drilled shafts, 36" diameter, into bedrock (524E94704) | FT | 54 | $1,082.00 | $1,425.00 | $1,416.56 | $1,399.30 | $2,000.00 | $800.00 |
| 66 | Drilled shafts, 42" diameter, above bedrock, as per plan (524E94803) | FT | 42 | $1,217.00 | $800.00 | $803.00 | $1,156.75 | $803.00 | $700.00 |
| 67 | Reinforced concrete approach slabs (T=12"), as per plan (526E10001) | SY | 89 | $338.00 | $275.00 | $380.96 | $482.00 | $300.00 | $325.00 |
| 68 | Type C installation (526E90030) | FT | 53 | $210.00 | $175.00 | $205.97 | $315.00 | $250.00 | $250.00 |
| 69 | Rock channel protection, type B without filter (601E34100) | CY | 217 | $96.00 | $100.00 | $78.61 | $170.00 | $100.00 | $200.00 |
| 70 | Structure grounding system (625E33000) | EACH | 1 | $11,130 | $10,963 | $10,963 | $9,750.00 | $2,600.00 | $10,000 |
| 71 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $7,200.00 | $15,000 | $7,841.65 | $24,000 | $24,000 | $20,000 |
| 72 | CPM progress schedule short duration projects (108E30000) | LS | 1 | $1.00 | $2,500.00 | $5,750.31 | $5,000.00 | $3,400.00 | $4,000.00 |
| 73 | Maintaining traffic (614E11000) | LS | 1 | $3,500.00 | $5,500.00 | $1,499.68 | $8,000.00 | $6,000.00 | $10,000 |
| 74 | Construction layout stakes and surveying (623E10000) | LS | 1 | $10.00 | $12,000 | $16,800 | $20,820 | $10,000 | $10,000 |
| 75 | Mobilization (624E10000) | LS | 1 | $75,772 | $78,000 | $79,810 | $30,000 | $85,000 | $25,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.