ODOT contract 250435 bid tabulation
DEL-SR 315-05.00/06.40/08.10 (SLIDE REPAIR). Let by Ohio DOT on September 25, 2025, DEL. 6 bids received; low bid $3,329,777 by George J Igel & Co Inc, -14% against the engineer's estimate of $3,861,000.
- Owner
- Ohio DOT
- Letting
- 25 SEP 2025
- Pay items
- 121
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | George J Igel & Co Inc | $3,329,777 | Low | -14% |
| 2 | Shelly & Sands Inc | $4,016,815 | +21% | +4.0% |
| 3 | Complete General Construction Company | $4,170,042 | +25% | +8.0% |
| 4 | Alan Stone Co Inc | $4,190,735 | +26% | +9.0% |
| 5 | Rietschlin Construction Inc | $4,267,515 | +28% | +11% |
| 6 | Trucco Construction Co Inc | $5,270,152 | +58% | +36% |
Engineer's estimate: $3,861,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. George J Igel & Co Inc | 2. Shelly & Sands Inc | 3. Complete General Construction Company | 4. Alan Stone Co Inc | 5. Rietschlin Construction Inc | 6. Trucco Construction Co Inc |
|---|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing, as per plan (201E11001) | LS | 1 | $90,000 | $124,676 | $100,000 | $260,000 | $110,000 | $92,000 |
| 2 | Structure removed (202E11004) | EACH | 4 | $2,550.00 | $9,000.00 | $6,000.00 | $2,000.00 | $10,000 | $21,400 |
| 3 | Headwall removed (202E20010) | EACH | 13 | $385.00 | $1,500.00 | $600.00 | $500.00 | $3,000.00 | $4,460.00 |
| 4 | Walk removed (202E30000) | SF | 43 | $11.25 | $7.00 | $12.00 | $10.00 | $9.00 | $6.60 |
| 5 | Steps removed (202E30204) | LS | 1 | $1,455.00 | $90.00 | $1,200.00 | $1,800.00 | $1,900.00 | $2,090.00 |
| 6 | Curb and gutter removed (202E32500) | FT | 32 | $15.00 | $6.00 | $18.00 | $20.00 | $25.00 | $16.20 |
| 7 | Pipe removed, 24" and under (202E35100) | FT | 311 | $25.00 | $45.00 | $30.00 | $20.00 | $55.00 | $43.00 |
| 8 | Pipe removed, over 24" diameter (202E35200) | FT | 138 | $24.75 | $60.00 | $90.00 | $20.00 | $55.00 | $100.00 |
| 9 | Guardrail removed (202E38000) | FT | 2,538 | $2.00 | $2.00 | $2.00 | $2.50 | $5.00 | $2.00 |
| 10 | Anchor assembly removed, type E (202E42010) | EACH | 1 | $195.00 | $195.00 | $400.00 | $400.00 | $209.00 | $195.00 |
| 11 | Anchor assembly removed, type T (202E42040) | EACH | 2 | $110.00 | $110.00 | $325.00 | $400.00 | $110.00 | $110.00 |
| 12 | Manhole removed (202E58000) | EACH | 2 | $500.00 | $500.00 | $800.00 | $500.00 | $2,700.00 | $3,390.00 |
| 13 | Catch basin removed (202E58100) | EACH | 1 | $400.00 | $500.00 | $500.00 | $550.00 | $750.00 | $1,190.00 |
| 14 | Fence removed (202E75000) | FT | 1,676 | $5.85 | $5.00 | $3.75 | $6.00 | $7.00 | $3.80 |
| 15 | Gate removed (202E75250) | EACH | 1 | $500.00 | $250.00 | $390.00 | $500.00 | $550.00 | $390.00 |
| 16 | Removal misc.: inspection well (202E98100) | EACH | 4 | $390.00 | $200.00 | $500.00 | $940.00 | $500.00 | $670.00 |
| 17 | Removal misc.: mailbox (202E98100) | EACH | 2 | $115.00 | $75.00 | $25.00 | $340.00 | $200.00 | $250.00 |
| 18 | Removal misc.: conduit (202E98200) | FT | 20 | $32.50 | $20.00 | $30.00 | $85.00 | $26.00 | $27.00 |
| 19 | Removal misc.: stacked stone wall (202E98200) | FT | 262 | $17.50 | $30.00 | $20.00 | $40.00 | $19.00 | $106.00 |
| 20 | Excavation (203E10000) | CY | 4,033 | $40.00 | $50.00 | $34.00 | $40.00 | $32.00 | $58.00 |
| 21 | Embankment (203E20000) | CY | 300 | $17.50 | $18.00 | $38.00 | $32.20 | $17.00 | $39.00 |
| 22 | Embankment, as per plan (203E20001) | CY | 50 | $30.00 | $40.00 | $50.00 | $31.74 | $38.00 | $10.10 |
| 23 | Preparing subgrade for shoulder paving (209E72000) | STA | 37 | $610.00 | $250.00 | $500.00 | $200.00 | $150.00 | $570.00 |
| 24 | Guardrail, type MGS (606E15050) | FT | 862.50 | $18.40 | $18.40 | $18.40 | $20.00 | $26.00 | $18.40 |
| 25 | Guardrail, type MGS half post spacing (606E15150) | FT | 1,737.50 | $26.80 | $26.80 | $26.80 | $27.00 | $40.00 | $27.00 |
| 26 | Guardrail, type MGS, long-span (606E17360) | FT | 375 | $22.40 | $22.40 | $22.40 | $25.00 | $27.00 | $22.40 |
| 27 | Anchor assembly, MGS type E (MASH 2016) (606E26150) | EACH | 7 | $2,525.00 | $2,525.00 | $2,525.00 | $2,500.00 | $2,695.00 | $2,530.00 |
| 28 | Anchor assembly, MGS type T (606E26550) | EACH | 2 | $1,370.00 | $1,370.00 | $1,370.00 | $1,400.00 | $1,342.00 | $1,370.00 |
| 29 | Special - mailbox support system, single (690E50100) | EACH | 5 | $195.00 | $195.00 | $195.00 | $200.00 | $165.00 | $195.00 |
| 30 | Special - mailbox support system, multiple (690E50300) | EACH | 1 | $380.00 | $380.00 | $380.00 | $400.00 | $429.00 | $380.00 |
| 31 | Riprap, type D (601E11000) | SY | 30 | $515.00 | $450.00 | $500.00 | $395.10 | $492.00 | $700.00 |
| 32 | Rock channel protection, type B with geotextile fabric (601E32104) | CY | 20 | $225.00 | $275.00 | $100.00 | $200.00 | $195.00 | $188.00 |
| 33 | Rock channel protection, type C with geotextile fabric (601E32204) | CY | 33 | $245.00 | $275.00 | $105.00 | $200.00 | $175.00 | $311.00 |
| 34 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $135.00 | $75.00 | $180.00 | $150.00 | $135.00 |
| 35 | Topsoil (659E00300) | CY | 1,002 | $21.25 | $42.00 | $45.00 | $25.00 | $45.00 | $66.00 |
| 36 | Seeding and mulching (659E10000) | SY | 8,498 | $1.25 | $0.80 | $0.50 | $2.00 | $1.00 | $0.80 |
| 37 | Repair seeding and mulching (659E14000) | SY | 426 | $1.25 | $0.80 | $1.80 | $2.00 | $1.00 | $1.80 |
| 38 | Inter-seeding (659E15000) | SY | 426 | $1.25 | $0.80 | $1.80 | $1.00 | $1.00 | $1.80 |
| 39 | Commercial fertilizer (659E20000) | TON | 1.30 | $1,250.00 | $816.00 | $750.00 | $700.00 | $900.00 | $820.00 |
| 40 | Lime (659E31000) | ACRE | 2 | $150.00 | $156.00 | $10.00 | $900.00 | $200.00 | $156.00 |
| 41 | Water (659E35000) | MGAL | 24 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 42 | Mowing (659E40000) | MSF | 19 | $100.00 | $100.00 | $18.45 | $120.00 | $110.00 | $18.50 |
| 43 | Slope erosion protection (670E00500) | SY | 8,498 | $2.50 | $1.50 | $2.75 | $2.50 | $1.75 | $2.75 |
| 44 | Ditch erosion protection (670E00700) | SY | 639 | $2.50 | $1.60 | $2.00 | $3.50 | $1.75 | $2.00 |
| 45 | Ditch erosion protection mat, type A (670E00710) | SY | 328 | $2.50 | $1.50 | $2.00 | $2.00 | $1.75 | $2.00 |
| 46 | Storm water pollution prevention plan (832E15000) | LS | 1 | $5,000.00 | $5,000.00 | $4,000.00 | $5,000.00 | $3,300.00 | $2,950.00 |
| 47 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $5,400.00 | $18,000 | $12,000 | $15,000 | $8,500.00 | $10,700 |
| 48 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $10,000 | $12,500 | $12,500 | $14,000 | $13,750 | $16,500 |
| 49 | Erosion control (832E30000) | EACH | 70,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 50 | Seeding and erosion control with turf reinforcing mat, type 1 (836E10000) | SY | 321 | $6.00 | $5.30 | $4.75 | $9.00 | $6.00 | $4.75 |
| 51 | Concrete masonry (602E20000) | CY | 70 | $1,250.00 | $3,000.00 | $1,900.00 | $2,500.00 | $2,030.00 | $5,000.00 |
| 52 | 12" conduit, type C (611E04600) | FT | 46 | $117.50 | $110.00 | $150.00 | $70.00 | $105.00 | $87.00 |
| 53 | 12" conduit, type D (611E04900) | FT | 199 | $112.50 | $85.00 | $145.00 | $70.00 | $65.00 | $78.00 |
| 54 | 24" conduit, type A (611E10200) | FT | 44 | $202.50 | $290.00 | $300.00 | $125.00 | $220.00 | $237.00 |
| 55 | 24" conduit, type C (611E10600) | FT | 6 | $250.00 | $350.00 | $265.00 | $245.00 | $360.00 | $370.00 |
| 56 | 36" conduit, type A (611E16200) | FT | 102 | $275.00 | $350.00 | $335.00 | $240.00 | $300.00 | $371.00 |
| 57 | 36" conduit, type A (611E16200) | FT | 51 | $275.00 | $350.00 | $330.00 | $210.00 | $300.00 | $240.00 |
| 58 | 48" conduit, type A, 706.02, 60" 707.03 (2") (0.18 (611E20700) | FT | 47 | $400.00 | $540.00 | $630.00 | $400.00 | $515.00 | $380.00 |
| 59 | 48" conduit, type A, 706.02, 707.01 (1/2") (alumin (611E20700) | FT | 46 | $405.00 | $630.00 | $500.00 | $400.00 | $400.00 | $475.00 |
| 60 | 48" conduit, type B (611E20900) | FT | 55 | $390.00 | $575.00 | $640.00 | $325.00 | $500.00 | $670.00 |
| 61 | 48" conduit, type C (611E21100) | FT | 6 | $405.00 | $535.00 | $540.00 | $400.00 | $790.00 | $820.00 |
| 62 | 60" conduit, type A, 706.02, 707.02 (1") (aluminiz (611E23600) | FT | 53 | $525.00 | $760.00 | $645.00 | $400.00 | $410.00 | $600.00 |
| 63 | 60" conduit, type A, 706.02, 707.02 (1") (0.168) ( (611E23600) | FT | 58 | $540.00 | $650.00 | $620.00 | $380.00 | $420.00 | $575.00 |
| 64 | 34" X 53" conduit, type A, 706.04 (611E52900) | FT | 58 | $475.00 | $580.00 | $500.00 | $400.00 | $500.00 | $550.00 |
| 65 | Conduit, misc.:type B for drainage discharge conti (611E97400) | FT | 20 | $70.00 | $32.00 | $75.00 | $529.62 | $70.00 | $120.00 |
| 66 | Conduit, misc.:type C for drainage discharge conti (611E97400) | FT | 20 | $60.00 | $25.00 | $75.00 | $529.62 | $50.00 | $70.00 |
| 67 | Conduit, misc.:type E for drainage discharge conti (611E97400) | FT | 20 | $55.00 | $25.00 | $75.00 | $529.62 | $50.00 | $50.00 |
| 68 | Conduit, misc.:type F for drainage discharge conti (611E97400) | FT | 20 | $65.00 | $25.00 | $75.00 | $529.62 | $50.00 | $50.00 |
| 69 | Catch basin, no. 2-2B (611E98470) | EACH | 5 | $3,000.00 | $3,750.00 | $2,100.00 | $2,288.11 | $2,225.00 | $3,630.00 |
| 70 | Manhole, no. 3 (611E99574) | EACH | 1 | $10,000 | $9,000.00 | $9,000.00 | $4,957.06 | $14,900 | $13,400 |
| 71 | Inspection well (611E99720) | EACH | 4 | $4,200.00 | $850.00 | $1,600.00 | $831.30 | $1,600.00 | $1,800.00 |
| 72 | Pavement repair (253E02000) | CY | 321 | $265.00 | $300.00 | $300.00 | $332.62 | $300.00 | $240.00 |
| 73 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 4,884 | $5.50 | $3.50 | $4.75 | $6.50 | $7.25 | $4.75 |
| 74 | Asphalt concrete base, PG64-22, (449), (driveways) (301E56100) | CY | 21 | $515.00 | $450.00 | $600.00 | $600.00 | $616.00 | $560.00 |
| 75 | Aggregate base (304E20000) | CY | 6 | $112.50 | $225.00 | $240.00 | $103.74 | $184.00 | $172.00 |
| 76 | Tack coat (407E10000) | GAL | 1,279 | $7.00 | $3.50 | $3.25 | $4.72 | $2.75 | $3.25 |
| 77 | Non-tracking tack coat (407E20000) | GAL | 451 | $10.00 | $3.50 | $4.50 | $5.15 | $4.75 | $4.50 |
| 78 | Stabilized crushed aggregate, as per plan (411E10001) | CY | 245 | $72.50 | $100.00 | $120.00 | $70.00 | $88.00 | $80.00 |
| 79 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 657 | $275.00 | $250.00 | $245.00 | $290.00 | $297.00 | $245.00 |
| 80 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 10 | $700.00 | $750.00 | $375.00 | $1,300.00 | $820.00 | $375.00 |
| 81 | Combination curb and gutter, type 2 (609E12000) | FT | 32 | $135.00 | $165.00 | $60.00 | $135.00 | $172.00 | $187.00 |
| 82 | Compacted aggregate (617E10100) | CY | 41 | $125.00 | $105.00 | $140.00 | $110.00 | $110.00 | $311.00 |
| 83 | Barrier reflector, type 2, bidirectional (626E00110) | EACH | 46 | $11.50 | $11.50 | $11.50 | $20.00 | $13.25 | $11.50 |
| 84 | Ground mounted support, no. 2 post (630E02100) | FT | 70 | $15.80 | $15.80 | $15.80 | $20.00 | $16.50 | $15.00 |
| 85 | Ground mounted support, no. 3 post (630E03100) | FT | 65 | $19.20 | $19.20 | $19.20 | $19.90 | $19.00 | $17.00 |
| 86 | Street name sign support, no. 2 post (630E08510) | FT | 32 | $17.50 | $17.50 | $17.50 | $25.00 | $19.00 | $17.00 |
| 87 | Sign, flat sheet (630E80100) | SF | 89 | $19.00 | $19.00 | $19.00 | $20.00 | $27.50 | $25.00 |
| 88 | Removal of ground mounted sign and disposal (630E84900) | EACH | 16 | $10.00 | $10.00 | $10.00 | $30.00 | $22.00 | $20.00 |
| 89 | Removal of ground mounted post support and disposal (630E86002) | EACH | 14 | $15.00 | $15.00 | $15.00 | $35.00 | $22.00 | $20.00 |
| 90 | Edge line, 4", type 1 (642E00100) | MI | 1.82 | $690.00 | $1,067.00 | $690.00 | $890.00 | $800.00 | $1,620.00 |
| 91 | Center line, type 1 (642E00300) | MI | 0.91 | $1,400.00 | $1,205.00 | $1,400.00 | $1,800.00 | $1,600.00 | $2,230.00 |
| 92 | Edge line, 4" (644E00100) | MI | 0.68 | $5,290.00 | $4,360.25 | $5,290.00 | $6,800.00 | $6,000.00 | $5,500.00 |
| 93 | Center line (644E00300) | MI | 0.33 | $9,380.00 | $5,393.00 | $9,380.00 | $12,000 | $10,400 | $8,300.00 |
| 94 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 120 | $100.00 | $104.00 | $55.00 | $100.00 | $94.00 | $110.00 |
| 95 | Detour signing (614E12420) | LS | 1 | $12,950 | $12,500 | $30,000 | $15,000 | $14,500 | $14,000 |
| 96 | Asphalt concrete for maintaining traffic (614E13000) | CY | 25 | $440.00 | $365.00 | $300.00 | $380.00 | $297.00 | $365.00 |
| 97 | Portable changeable message sign (614E18600) | SNMT | 18 | $575.00 | $575.00 | $900.00 | $1,200.00 | $640.00 | $620.00 |
| 98 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.68 | $1,275.00 | $1,275.00 | $1,275.00 | $1,400.00 | $1,500.00 | $1,380.00 |
| 99 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.33 | $830.00 | $830.00 | $830.00 | $950.00 | $1,000.00 | $900.00 |
| 100 | Water (616E10000) | MGAL | 25 | $50.00 | $80.00 | $165.00 | $0.10 | $1.00 | $118.00 |
| 101 | Structure removed, as per plan (202E11001) | LS | 1 | $4,000.00 | $10,000 | $9,000.00 | $12,000 | $25,000 | $2,470.00 |
| 102 | Unclassified excavation (503E21100) | CY | 781 | $32.50 | $65.00 | $100.00 | $35.00 | $155.00 | $129.00 |
| 103 | Steel piles, misc.:12X53, furnished (507E00400) | FT | 6,422 | $45.00 | $42.00 | $48.00 | $47.00 | $58.00 | $63.00 |
| 104 | Steel piles, misc.:12X84, furnished (507E00400) | FT | 62 | $75.00 | $80.00 | $85.00 | $97.00 | $91.00 | $100.00 |
| 105 | Epoxy coated steel reinforcement (509E10000) | LB | 29,243 | $1.70 | $3.00 | $2.70 | $2.50 | $1.75 | $3.00 |
| 106 | Class QC1 concrete with QC/QA, retaining/wingwall not including footing (511E46012) | CY | 217 | $700.00 | $1,085.00 | $1,600.00 | $1,040.00 | $700.00 | $2,500.00 |
| 107 | Concrete, misc.:10'-0" X 2'-0" X 1'-0" precast con (511E81300) | EACH | 2 | $1,500.00 | $1,550.00 | $1,100.00 | $1,500.00 | $2,000.00 | $2,150.00 |
| 108 | Concrete, misc.:10'-0" X 3'-7 1/2" X 1'-0" precast (511E81300) | EACH | 2 | $2,500.00 | $2,050.00 | $1,600.00 | $6,300.00 | $3,000.00 | $2,780.00 |
| 109 | Concrete, misc.:10'-0" X 6'-6" X 1'-0" precast con (511E81300) | EACH | 1 | $3,500.00 | $3,025.00 | $2,400.00 | $7,000.00 | $5,000.00 | $4,300.00 |
| 110 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 1,465 | $23.50 | $23.50 | $23.50 | $24.00 | $26.00 | $23.50 |
| 111 | Porous backfill with geotextile fabric (518E21200) | CY | 313 | $125.00 | $135.00 | $98.00 | $100.00 | $92.00 | $181.00 |
| 112 | 6" perforated corrugated plastic pipe (518E40000) | FT | 496 | $1.50 | $2.00 | $10.00 | $10.00 | $12.00 | $26.00 |
| 113 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 12 | $20.00 | $10.00 | $19.00 | $10.00 | $44.00 | $98.00 |
| 114 | Structure drainage, misc.:weep drains (518E62200) | EACH | 58 | $175.00 | $215.00 | $500.00 | $500.00 | $207.00 | $125.00 |
| 115 | Drilled shafts, 24" diameter, above bedrock, as per plan (524E94503) | FT | 6,791 | $80.00 | $92.50 | $152.00 | $122.00 | $150.00 | $140.00 |
| 116 | Drilled shafts, 24" diameter, into bedrock, as per plan (524E94505) | FT | 2,166 | $280.00 | $290.00 | $160.00 | $270.00 | $265.00 | $312.00 |
| 117 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $30,000 | $24,500 | $25,000 | $45,000 | $45,000 | $30,000 |
| 118 | Maintaining traffic (614E11000) | LS | 1 | $9,000.00 | $17,500 | $20,000 | $45,000 | $25,000 | $75,000 |
| 119 | Field office, type B (619E16010) | MNTH | 10 | $3,500.00 | $4,000.00 | $3,500.00 | $1,500.00 | $1,375.00 | $3,000.00 |
| 120 | Construction layout stakes and surveying (623E10000) | LS | 1 | $25,000 | $46,500 | $60,000 | $80,000 | $40,000 | $75,000 |
| 121 | Mobilization (624E10000) | LS | 1 | $75,000 | $200,000 | $200,000 | $135,000 | $150,000 | $200,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.