ODOT contract 250430 bid tabulation

BUT-SR 503-00.00 (TWO LANE RESURFACING). Let by Ohio DOT on September 25, 2025, BUT. 2 bids received; low bid $2,642,217 by John R Jurgensen Company, +7.4% against the engineer's estimate of $2,460,000.

Owner
Ohio DOT
Letting
25 SEP 2025
Pay items
41
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1John R Jurgensen Company$2,642,217Low+7.0%
2Barrett Paving Materials Inc$2,697,287+2.0%+10%
ODOT contract 250430: bids by rank

Engineer's estimate: $2,460,000.

Bid tabulation

LinePay itemUnitQuantity1. John R Jurgensen Company2. Barrett Paving Materials Inc
1Guardrail removed (202E38000)FT387.50$2.50$2.50
2Anchor assembly removed, type A, as per plan (202E42001)EACH3$400.00$400.00
3Anchor assembly removed, type E (202E42010)EACH1$250.00$250.00
4Bridge terminal assembly removed (202E47000)EACH4$150.00$150.00
5Preparing subgrade for shoulder paving (209E72050)MI12$1,516.91$1,100.00
6Guardrail, type MGS with long posts (606E15100)FT287.50$22.50$22.50
7Anchor assembly, MGS type E, MASH 2016 (606E26150)EACH3$2,500.00$2,500.00
8Anchor assembly, MGS type E, MASH 2016, soft stop (606E26150)EACH1$2,500.00$2,500.00
9Bridge terminal assembly, type 4, as per plan (606E35141)EACH4$1,450.00$1,450.00
10Erosion control (832E30000)EACH1,000$1.00$1.00
11Pavement repair (253E02000)CY220$432.64$515.00
12Pavement planing, asphalt concrete, as per plan, 1 (254E01001)SY298$25.90$70.00
13Pavement planing, asphalt concrete, as per plan, 3 (254E01001)SY82,260$4.00$3.10
14Patching planed surface (254E01600)SY833$4.34$8.00
15Non-tracking tack coat (407E20000)GAL12,366$5.00$4.50
16Asphalt concrete surface course, type 1, (446), PG64-22 (441E10000)CY2,984$232.19$263.00
17Asphalt concrete intermediate course, type 2, (446) (441E10200)CY3,999$218.97$237.00
18Compacted aggregate (617E10100)CY358$138.37$195.00
19Shoulder preparation (617E20000)SY6,665$1.64$2.90
20Water (617E25000)MGAL8$101.10$100.00
21RPM (621E00100)EACH432$46.30$36.00
22Raised pavement marker removed (621E54000)EACH432$16.99$10.00
23Barrier reflector, type 2, BI-directional (626E00110)EACH8$12.00$12.00
24Edge line, 6" (644E00104)MI12.08$3,941.00$3,941.00
25Center line (644E00300)MI6.04$4,302.00$4,302.00
26Stop line (644E00500)FT36$20.00$20.00
27Crosswalk line, 12" (644E00620)FT140$10.00$10.00
28Work zone center line, class I, 642 paint (614E21100)MI6.05$1,900.00$1,900.00
29Work zone center line, class III, 642 paint (614E21550)MI6.05$1,900.00$1,900.00
30Work zone edge line, class I, 6", 642 paint (614E22110)MI12.10$1,113.00$1,113.00
31Work zone edge line, class III, 6", 642 paint (614E22360)MI12.10$1,113.00$1,113.00
32Work zone stop line, class I, 642 paint (614E26200)FT36$5.00$5.00
33Work zone stop line, class III, 642 paint (614E26610)FT36$5.00$5.00
34Work zone crosswalk line, class I, 12", 642 paint (614E27050)FT140$3.00$3.00
35Work zone crosswalk line, class III, 12", 642 paint (614E27250)FT140$3.00$3.00
36Deep beam bridge retrofit railing (517E75600)FT200$110.00$110.00
37Polymer modified asphalt expansion joint system (846E00110)CF28.38$782.64$605.00
38Premium for contract performance bond and for payment bond (103E05000)LS1$8,916.81$4,855.14
39Maintaining traffic (614E11000)LS1$133,173$20,000
40Construction layout stakes and surveying, as per plan (623E10001)LS1$4,976.40$4,000.00
41Mobilization (624E10000)LS1$125,000$169,000
ODOT contract 250430: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of September 25, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy