| 1 | Erosion control (832E30000) | EACH | 1,000 | $1.00 | $1.00 |
| 2 | Partial depth pavement repair (442) (251E01020) | SY | 2,000 | $124.00 | $84.76 |
| 3 | Pavement planing, asphalt concrete 1" (254E01000) | SY | 296,505 | $1.57 | $1.41 |
| 4 | Patching planed surface (254E01600) | SY | 61,982 | $3.25 | $3.00 |
| 5 | Non-tracking tack coat (407E20000) | GAL | 26,685 | $4.10 | $4.50 |
| 6 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 8,236 | $250.00 | $312.78 |
| 7 | Water (616E10000) | MGAL | 10 | $8.00 | $54.36 |
| 8 | Rumble strips, shoulder (asphalt concrete) (618E40600) | MI | 26.92 | $775.00 | $775.00 |
| 9 | RPM (621E00100) | EACH | 1,050 | $35.00 | $38.00 |
| 10 | Raised pavement marker removed (621E54000) | EACH | 1,050 | $17.75 | $15.56 |
| 11 | Detector loop, as per plan (632E26501) | EACH | 4 | $2,500.00 | $2,500.00 |
| 13 | Stop line (644E00500) | FT | 603 | $8.95 | $11.00 |
| 14 | Chevron marking (644E00720) | FT | 514 | $8.95 | $9.00 |
| 15 | Island marking (644E00900) | SF | 1,292 | $3.25 | $11.00 |
| 16 | Lane arrow (644E01300) | EACH | 18 | $110.00 | $120.00 |
| 17 | Dotted line, 6" (644E01510) | FT | 5,944 | $0.95 | $1.50 |
| 18 | Speed measurement marking (644E40000) | EACH | 20 | $350.00 | $465.26 |
| 19 | Wet reflective thermoplastic pavement marking, edge line, 6" (807E14010) | MI | 26.92 | $4,320.00 | $4,100.00 |
| 20 | Wet reflective thermoplastic pavement marking, lane line, 6" (807E14110) | MI | 13.46 | $1,855.00 | $1,900.00 |
| 21 | Stop line radar detection, as per plan (809E69101) | EACH | 8 | $9,750.00 | $9,750.00 |
| 22 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 40.38 | $1,523.00 | $1,900.00 |
| 23 | Grooving for 12" recessed pavement marking, (asphalt) (850E10130) | FT | 3,829 | $2.50 | $1.20 |
| 24 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 160 | $95.00 | $127.87 |
| 25 | Work zone increased penalties sign (614E12484) | EACH | 8 | $100.00 | $100.00 |
| 26 | Replacement drum (614E12600) | EACH | 50 | $85.00 | $80.00 |
| 27 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 26.92 | $725.00 | $765.00 |
| 28 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.55 | $12,190 | $11,500 |
| 29 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 53.84 | $905.00 | $925.00 |
| 30 | Work zone channelizing line, class I, 12" (614E23010) | FT | 7,178 | $1.25 | $1.50 |
| 31 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 1,440 | $3.71 | $3.50 |
| 32 | Work zone stop line, class III, 642 paint (614E26610) | FT | 1,206 | $7.00 | $8.00 |
| 33 | Digital speed limit (DSL) sign assembly (808E18700) | SNMT | 12 | $850.00 | $850.00 |
| 34 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 888 | $13.25 | $8.89 |
| 35 | Pavement planing, portland cement concrete, 1" (254E01010) | SY | 178 | $13.25 | $41.34 |
| 36 | Tack coat (407E10000) | GAL | 76 | $4.10 | $4.50 |
| 37 | Tack coat, 702.13 (407E13900) | GAL | 12 | $50.00 | $4.50 |
| 38 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 28 | $250.00 | $310.60 |
| 39 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 50 | $365.00 | $496.42 |
| 40 | Joint sealer, as per plan (516E31001) | FT | 92 | $36.00 | $36.00 |
| 41 | Patching concrete bridge deck - type C (519E12304) | SY | 4 | $1,400.00 | $1,400.00 |
| 42 | Pavement planing, asphalt concrete, 1" (254E01000) | SY | 712 | $13.25 | $10.89 |
| 43 | Pavement planing, portland cement concrete, 1" (254E01010) | SY | 178 | $13.25 | $41.34 |
| 44 | Tack coat (407E10000) | GAL | 60 | $4.10 | $4.50 |
| 45 | Tack coat, 702.13 (407E13900) | GAL | 12 | $50.00 | $4.50 |
| 46 | Fine graded polymer asphalt concrete, type B, (448) (424E14000) | CY | 24 | $250.00 | $310.48 |
| 47 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 40 | $365.00 | $561.25 |
| 48 | Joint sealer, as per plan (516E31001) | FT | 92 | $36.00 | $36.00 |
| 49 | Patching concrete bridge deck - type C (519E12304) | SY | 4 | $1,400.00 | $1,400.00 |
| 50 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $20,874 |
| 51 | Maintaining traffic (614E11000) | LS | 1 | $182,000 | $67,711 |
| 52 | Construction layout stakes and surveying (623E10000) | LS | 1 | $9,500.00 | $4,992.49 |
| 53 | Mobilization (624E10000) | LS | 1 | $100,000 | $175,000 |
| 100 | Wet reflective thermoplastic pavement marking, channelizing line, 12" (807E14310) | FT | 3,829 | $2.00 | $2.00 |