ODOT letting results, October 9, 2025
30 contracts let by Ohio DOT on October 9, 2025, $107,250,318 in low bids, a median of 3 bidders per contract. On the 30 with an engineer's estimate, the low bid came in under it 15 times; median low bid -3.0% against the estimate.
- Owner
- Ohio DOT
- Contracts
- 30
- Low bids, total
- $107,250,318
- Data through
- 12 NOV 2026
Contracts let that day
| Contract | Project | County | Bids | Low bidder | Low bid | Second bid | Gap | Against estimate | Source |
|---|---|---|---|---|---|---|---|---|---|
| 250404 | HAM-IR 75-01.05 (MAJOR RECONSTRUCTION) | HAM | 3 | Great Lakes Construction Co | $46,773,940 | $48,182,235 | +3.0% | +22% | ODOT |
| 250454 | MER-/AUG-PAVE-FY26 (TWO LANE RESURFACING) | MER | 1 | Shelly Company | $9,390,445 | +7.0% | ODOT | ||
| 250465 | HOL-/TUS-US 62/US 39-VAR (TWO LANE RESURFACING) | HOL | 3 | Melway Paving Co Inc | $5,093,502 | $5,875,000 | +15% | -6.0% | ODOT |
| 250472 | WOO-/SAN-US 20/US 65-00.00/19.38 Res (FOUR LANE RESURFACING) | WOO | 4 | Shelly Company | $4,392,762 | $4,708,181 | +7.0% | -13% | ODOT |
| 250475 | VAN-/PAU-US 127-12.34/00.00 (PART 1 AND PART 2) (TWO LANE RESURFACING) | VAN | 2 | Shelly Company | $4,080,769 | $4,806,279 | +18% | -7.0% | ODOT |
| 250457 | BUT-SR 73-09.90 (TWO LANE RESURFACING) | BUT | 2 | Barrett Paving Materials Inc | $2,772,578 | $2,799,578 | +1.0% | +16% | ODOT |
| 250470 | MOT-BP FY26 (BRIDGE PAINTING) | MOT | 7 | Euro Paint LLC | $2,614,391 | $2,777,851 | +6.0% | -16% | ODOT |
| 250468 | MAR-SR 37-08.44 (BRIDGE REPLACEMENT (1 BRIDGE)) | MAR | 4 | Miller Bros Const Inc | $2,572,669 | $2,989,969 | +16% | -20% | ODOT |
| 250482 | D12-PM FY2026 (PAVEMENT MARKING) | District 12 | 3 | Oglesby Construction Inc | $2,534,308 | $2,557,311 | +1.0% | -9.0% | ODOT |
| 250464 | HAM-SR 4/SR 747-06.13/00.00 (TWO LANE RESURFACING) | HAM | 2 | John R Jurgensen Company | $2,464,808 | $2,477,120 | 0.0% | +12% | ODOT |
| 250467 | MAH-US 422-03.13 (BRIDGE REPAIR) | MAH | 4 | A P O'Horo Company | $2,084,000 | $2,580,727 | +24% | -29% | ODOT |
| 250484 | HIG-SR 753-13.03 (BRIDGE REPAIR) | HIG | 5 | Double Z Construction Company | $2,056,474 | $2,078,467 | +1.0% | +10% | ODOT |
| 250474 | VAN-SR 116/SR 117/SR 697-Var. (TWO LANE RESURFACING) | VAN | 1 | Shelly Company | $2,029,205 | +8.0% | ODOT | ||
| 250473 | TUS-SR 39-02.96 (TWO LANE RESURFACING) | TUS | 3 | Shelly Company | $1,964,603 | $1,987,645 | +1.0% | +34% | ODOT |
| 250466 | LAW-SR 141-00.98 (TWO LANE RESURFACING) | LAW | 1 | Shelly Company | $1,792,210 | 0.0% | ODOT | ||
| 250469 | MED-US 224-15.27 (SPOT PATCHING / PAVEMENT REPAIR) | MED | 4 | Smith Paving & Excavating Inc | $1,776,129 | $2,030,000 | +14% | -18% | ODOT |
| 250479 | D06-BR-FY26 (BRIDGE REPAIR) | District 6 | 1 | Vimas Painting Company Inc | $1,630,261 | +81% | ODOT | ||
| 250476 | VIN-Moonville Trail 144/48 & 70 (BRIDGE REPLACEMENT (1 BRIDGE)) | VIN | 3 | Complete General Construction Company | $1,534,885 | $1,984,274 | +29% | -9.0% | ODOT |
| 250477 | WYA-SR 53-15.36 (TWO LANE RESURFACING) | WYA | 3 | Kokosing Construction Company Inc | $1,467,872 | $1,670,670 | +14% | -14% | ODOT |
| 250483 | GUE-Flat Sheet Signs 2026 (SIGNING) | GUE | 3 | M P Dory Co | $1,420,663 | $1,515,420 | +7.0% | +2.0% | ODOT |
| 250463 | GRE-MCRO FY2026 (MICROSURFACING) | GRE | 1 | Strawser Construction Inc | $1,012,250 | +5.0% | ODOT | ||
| 254028 | DAR-SR 47/US 127-03.16/30.53 (BRIDGE REPAIR) | DAR | 1 | BCC Ohio Inc | $989,068 | +2.0% | ODOT | ||
| 250455 | AUG-SR 219-09.27 (BRIDGE REPLACEMENT (1 BRIDGE)) | AUG | 5 | Jutte Excavating Inc | $949,688 | $952,134 | 0.0% | -25% | ODOT |
| 250481 | D12-MOW FY2026 (MOWING) | District 12 | 1 | Linkel Company | $945,000 | -5.0% | ODOT | ||
| 254027 | CUY-IR 480-21.61 Ramp Slope (SLIDE REPAIR) | CUY | 2 | Shook Company LLC | $752,957 | $829,816 | +10% | +25% | ODOT |
| 250471 | ROS-US 35-23.67 (SLIDE REPAIR) | ROS | 7 | Shelly & Sands Inc | $590,369 | $711,565 | +21% | -25% | ODOT |
| 250478 | D06-ELEC FY26 (LIGHTING) | District 6 | 4 | Perram Electric Inc | $489,159 | $583,070 | +19% | -5.0% | ODOT |
| 250458 | CLI-Culverts FY26 (CULVERT REPLACEMENT) | CLI | 2 | Madex Construction Co | $479,556 | $582,173 | +21% | +29% | ODOT |
| 250480 | D09-RPM FY2026 (RAISED PAVEMENT MARKERS) | District 9 | 5 | Eaton Construction Co Inc | $299,462 | $302,281 | +1.0% | +1.0% | ODOT |
| 250461 | D03-TSG FY2026 (M) (SIGNALIZATION) | District 3 | 6 | Greenwich Electric Inc | $296,336 | $303,579 | +2.0% | -22% | ODOT |
Gap is the second bid over the low bid. Where a contract shows fewer bids than ODOT received, the others did not match their published totals and are left out. Each contract number opens its full bid tabulation.