ODOT contract 250476 bid tabulation
VIN-Moonville Trail 144/48 & 70 (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on October 9, 2025, VIN. 3 bids received; low bid $1,534,885 by Complete General Construction Company, -9.2% against the engineer's estimate of $1,690,000.
- Owner
- Ohio DOT
- Letting
- 09 OCT 2025
- Pay items
- 37
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Complete General Construction Company | $1,534,885 | Low | -9.0% |
| 2 | Alan Stone Co Inc | $1,984,274 | +29% | +17% |
| 3 | Axis Civil Construction LLC | $2,238,790 | +46% | +32% |
Engineer's estimate: $1,690,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Complete General Construction Company | 2. Alan Stone Co Inc | 3. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $10,000 | $82,000 | $195,000 |
| 2 | Excavation (203E10000) | CY | 20 | $35.00 | $160.00 | $60.00 |
| 3 | Embankment (203E20000) | CY | 100 | $45.00 | $65.00 | $60.00 |
| 4 | Subgrade compaction (204E10000) | SY | 151 | $25.00 | $45.00 | $6.00 |
| 5 | Seeding, misc.: seeding and mulching, as per plan (659E98700) | LS | 1 | $6,000.00 | $3,800.00 | $15,000 |
| 6 | Erosion control (832E30000) | EACH | 5,000 | $1.00 | $1.00 | $1.00 |
| 7 | Aggregate base (304E20000) | CY | 25 | $105.00 | $300.00 | $150.00 |
| 8 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $95,000 | $500.00 | $52,000 |
| 9 | Unclassified excavation (503E21300) | LS | 1 | $30,000 | $13,000 | $22,000 |
| 10 | Epoxy coated steel reinforcement (509E10000) | LB | 6,052 | $2.25 | $3.50 | $4.50 |
| 11 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 302 | $32.00 | $65.00 | $32.00 |
| 12 | Class QC2 concrete, pier cap (511E43260) | CY | 29 | $1,750.00 | $3,200.00 | $2,400.00 |
| 13 | Class QC1 concrete, substructure (511E50210) | CY | 48 | $1,300.00 | $1,100.00 | $1,650.00 |
| 14 | Porous backfill with geotextile fabric (518E21200) | CY | 28 | $195.00 | $160.00 | $250.00 |
| 15 | 6" perforated corrugated plastic pipe (518E40000) | FT | 49 | $20.00 | $25.00 | $20.00 |
| 16 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 48 | $20.00 | $50.00 | $20.00 |
| 17 | Patching concrete structure (519E11100) | SF | 250 | $125.00 | $60.00 | $235.00 |
| 18 | Special - structures: pre-engineered superstructur (530E00200) | LS | 1 | $350,000 | $503,000 | $465,000 |
| 19 | Special - structures: non-shrink, non-metallic gro (530E00600) | SF | 28 | $400.00 | $440.00 | $100.00 |
| 20 | Cofferdams and excavation bracing (503E11100) | LS | 1 | $95,000 | $500.00 | $52,000 |
| 21 | Unclassified excavation (503E21300) | LS | 1 | $30,000 | $13,000 | $23,000 |
| 22 | Epoxy coated steel reinforcement (509E10000) | LB | 5,472 | $2.25 | $3.50 | $4.50 |
| 23 | Dowel holes with nonshrink, nonmetallic grout (510E10000) | EACH | 236 | $32.00 | $75.00 | $32.00 |
| 24 | Class QC2 concrete, pier cap (511E43260) | CY | 37 | $1,750.00 | $2,600.00 | $2,200.00 |
| 25 | Class QC1 concrete, substructure (511E50210) | CY | 22 | $1,300.00 | $1,700.00 | $1,950.00 |
| 26 | Porous backfill with geotextile fabric (518E21200) | CY | 16 | $195.00 | $230.00 | $250.00 |
| 27 | 6" perforated corrugated plastic pipe (518E40000) | FT | 38 | $20.00 | $75.00 | $20.00 |
| 28 | 6" non-perforated corrugated plastic pipe (518E40012) | FT | 48 | $20.00 | $50.00 | $20.00 |
| 29 | Patching concrete structure (519E11100) | SF | 250 | $125.00 | $60.00 | $235.00 |
| 30 | Special - structures pre-engineered superstructure (530E00200) | LS | 1 | $350,000 | $505,000 | $498,000 |
| 31 | Special - structures non-shrink, non- metallic gro (530E00600) | SF | 28 | $400.00 | $470.00 | $100.00 |
| 32 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $8,500.00 | $18,000 | $15,000 |
| 33 | Maintaining traffic (614E11000) | LS | 1 | $5,500.00 | $6,100.00 | $20,000 |
| 34 | Construction layout stakes and surveying (623E10000) | LS | 1 | $15,000 | $22,000 | $15,000 |
| 35 | Mobilization (624E10000) | LS | 1 | $76,500 | $259,000 | $60,000 |
| 100 | Portions of structure removed (202E11200) | LS | 1 | $50,000 | $50,000 | $165,000 |
| 101 | Portions of structure removed (202E11200) | LS | 1 | $50,000 | $50,000 | $145,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.