ODOT contract 250484 bid tabulation
HIG-SR 753-13.03 (BRIDGE REPAIR). Let by Ohio DOT on October 9, 2025, HIG. 5 bids received; low bid $2,056,474 by Double Z Construction Company, +10% against the engineer's estimate of $1,865,000.
- Owner
- Ohio DOT
- Letting
- 09 OCT 2025
- Pay items
- 54
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Double Z Construction Company | $2,056,474 | Low | +10% |
| 2 | Complete General Construction Company | $2,078,467 | +1.0% | +11% |
| 3 | BCC Ohio Inc | $2,111,418 | +3.0% | +13% |
| 4 | Sunesis Construction Co | $2,174,744 | +6.0% | +17% |
| 5 | Eagle Bridge Co | $2,340,534 | +14% | +25% |
Engineer's estimate: $1,865,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Double Z Construction Company | 2. Complete General Construction Company | 3. BCC Ohio Inc | 4. Sunesis Construction Co | 5. Eagle Bridge Co |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $7,500.00 | $5,500.00 | $2,064.00 | $2,183.35 | $250.00 |
| 2 | Pavement planing, asphalt concrete 1.5" deep (254E01000) | SY | 489 | $16.00 | $7.00 | $9.83 | $7.00 | $8.30 |
| 3 | Tack coat (407E10000) | GAL | 44 | $4.50 | $4.50 | $1.05 | $4.50 | $1.00 |
| 4 | Asphalt concrete surface course, type 1, (449), PG64-22 (441E70000) | CY | 21 | $775.00 | $775.00 | $630.00 | $775.00 | $600.00 |
| 5 | Guardrail removed (202E38000) | FT | 400 | $9.00 | $8.00 | $2.52 | $6.37 | $2.80 |
| 6 | Guardrail, type MGS (606E15050) | FT | 400 | $22.86 | $22.86 | $23.31 | $22.86 | $20.50 |
| 7 | MGS bridge terminal assembly, type 1 (606E35002) | EACH | 4 | $2,100.00 | $2,100.00 | $2,961.00 | $2,100.00 | $2,500.00 |
| 8 | Curb, type 4-C (609E24510) | FT | 73 | $58.00 | $125.00 | $32.29 | $59.97 | $75.00 |
| 9 | RPM (621E00100) | EACH | 4 | $450.00 | $450.00 | $354.00 | $450.00 | $600.00 |
| 10 | Raised pavement marker removed (621E54000) | EACH | 14 | $15.00 | $50.00 | $20.64 | $6.51 | $25.00 |
| 11 | Barrier reflector, type 1 (two-way) (626E00102) | EACH | 6 | $11.00 | $11.00 | $13.13 | $11.00 | $10.00 |
| 12 | Barrier reflector, type 3 (two-way) (626E00112) | EACH | 12 | $10.00 | $10.00 | $15.75 | $10.00 | $12.00 |
| 13 | Edge line, 6", type 1 (642E00104) | MI | 0.09 | $16,687 | $7,250.00 | $17,521 | $7,250.00 | $17,500 |
| 14 | Center line, type 1 (642E00300) | MI | 0.04 | $29,225 | $22,500 | $30,686 | $22,500 | $35,000 |
| 15 | Pavement repair (253E02000) | CY | 30 | $500.00 | $650.00 | $525.00 | $500.00 | $500.00 |
| 16 | Tack coat (407E10000) | GAL | 30 | $4.50 | $4.50 | $1.05 | $4.50 | $1.00 |
| 17 | Asphalt concrete surface course, type 1, (448), PG64-22 (441E50000) | CY | 30 | $450.00 | $450.00 | $414.75 | $450.00 | $395.00 |
| 18 | Detour signing (614E12420) | LS | 1 | $9,000.00 | $9,000.00 | $6,090.00 | $8,740.03 | $8,500.00 |
| 19 | Asphalt concrete for maintaining traffic (614E13000) | CY | 30 | $200.00 | $550.00 | $525.00 | $491.58 | $380.00 |
| 20 | Water (616E10000) | MGAL | 1 | $50.00 | $80.00 | $11.55 | $197.72 | $10.00 |
| 21 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $300,000 | $378,000 | $145,187 | $316,849 | $350,000 |
| 22 | Approach slab removed (202E22900) | SY | 122 | $60.00 | $95.00 | $92.03 | $122.72 | $70.00 |
| 23 | Epoxy coated steel reinforcement (509E10000) | LB | 43,481 | $4.89 | $4.00 | $4.25 | $5.42 | $4.65 |
| 24 | No. 4 deformed GFRP reinforcement (509E30020) | FT | 12,296 | $1.25 | $1.50 | $1.84 | $1.93 | $1.75 |
| 25 | Dowel holes with nonshrink, nonmetallic grout, as per plan (510E10001) | EACH | 136 | $27.00 | $35.00 | $29.69 | $19.96 | $30.00 |
| 26 | Class QC2 concrete with QC/QA, superstructure (511E34412) | CY | 79 | $2,500.00 | $1,900.00 | $1,857.14 | $3,006.26 | $3,300.00 |
| 27 | Class QC2 concrete with QC/QA, bridge deck (parapet) (511E34450) | CY | 129 | $925.00 | $750.00 | $1,557.69 | $802.31 | $900.00 |
| 28 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 910 | $27.00 | $26.75 | $29.40 | $35.84 | $26.75 |
| 29 | Surface preparation of existing structural steel (514E00050) | SF | 32,910 | $5.75 | $5.75 | $9.45 | $5.75 | $8.00 |
| 30 | Field painting of existing structural steel, prime coat (514E00056) | SF | 32,910 | $3.00 | $3.00 | $5.25 | $3.00 | $4.00 |
| 31 | Field painting structural steel, intermediate coat (514E00060) | SF | 32,910 | $3.00 | $3.00 | $3.15 | $3.00 | $3.00 |
| 32 | Field painting structural steel, finish coat (514E00066) | SF | 32,910 | $3.00 | $3.00 | $2.36 | $3.00 | $2.15 |
| 33 | Grinding fins, tears, slivers on existing structural steel (514E00504) | MNHR | 51 | $150.00 | $150.00 | $157.50 | $150.00 | $150.00 |
| 34 | Final inspection repair (514E10000) | EACH | 8 | $250.00 | $250.00 | $210.00 | $250.00 | $200.00 |
| 35 | Structural expansion joint including elastomeric strip seal, as per plan (516E11211) | FT | 68 | $960.00 | $800.00 | $1,234.58 | $1,289.26 | $1,000.00 |
| 36 | Refurbish bearing device, as per plan (516E45305) | EACH | 8 | $2,250.00 | $2,100.00 | $2,838.38 | $2,162.83 | $2,000.00 |
| 37 | Jacking and temporary support of superstructure, as per plan (516E47001) | LS | 1 | $20,000 | $25,000 | $22,205 | $19,206 | $40,000 |
| 38 | Reinforced concrete approach slabs with QC/QA (T=1 (526E25010) | SY | 189 | $375.00 | $350.00 | $542.16 | $481.98 | $400.00 |
| 39 | Type A installation, as per plan (526E90011) | FT | 68 | $225.00 | $625.00 | $309.90 | $353.02 | $450.00 |
| 40 | Micro silica modified concrete overlay using hydrodemolition (848E10000) | SY | 1,261 | $90.00 | $75.00 | $83.30 | $96.90 | $90.00 |
| 41 | Surface preparation using hydrodemolition (848E20000) | SY | 1,177 | $70.00 | $85.00 | $62.40 | $56.92 | $90.00 |
| 42 | Micro silica modified concrete overlay (variable thickness), material only (848E30000) | CY | 10 | $300.00 | $450.00 | $420.00 | $446.84 | $310.00 |
| 43 | Hand chipping (848E50000) | SY | 126 | $90.00 | $95.00 | $271.43 | $156.80 | $110.00 |
| 44 | Test slab (848E50100) | LS | 1 | $600.00 | $8,000.00 | $2,598.00 | $1,005.33 | $1,500.00 |
| 45 | Existing concrete overlay REMOVED1.5" (848E50320) | SY | 1,177 | $18.00 | $15.00 | $9.38 | $11.12 | $16.00 |
| 46 | Removal of debonded or deteriorated existing variable thickness concrete overlay (848E50340) | SY | 12 | $125.00 | $50.00 | $271.40 | $141.00 | $100.00 |
| 47 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $12,000 | $13,500 | $26,013 | $12,041 | $50,000 |
| 48 | Maintaining traffic (614E11000) | LS | 1 | $25,000 | $12,000 | $5,118.00 | $7,112.55 | $5,000.00 |
| 49 | Field office, type A (619E16000) | MNTH | 3 | $1,800.00 | $2,000.00 | $3,975.00 | $1,910.00 | $3,000.00 |
| 50 | Construction layout stakes and surveying (623E10000) | LS | 1 | $2,000.00 | $19,000 | $2,550.00 | $3,000.00 | $7,500.00 |
| 51 | Mobilization (624E10000) | LS | 1 | $100,000 | $104,000 | $58,604 | $107,511 | $115,000 |
| 100 | Excavation (203E10000) | CY | 31 | $75.00 | $40.00 | $19.31 | $62.16 | $100.00 |
| 101 | Subgrade compaction (204E10000) | SY | 186 | $10.00 | $30.00 | $3.00 | $4.79 | $12.00 |
| 102 | Aggregate base (304E20000) | CY | 25 | $150.00 | $150.00 | $129.12 | $117.79 | $200.00 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.