ODOT contract 250483 bid tabulation

GUE-Flat Sheet Signs 2026 (SIGNING). Let by Ohio DOT on October 9, 2025, GUE. 3 bids received; low bid $1,420,663 by M P Dory Co, +2.1% against the engineer's estimate of $1,392,000.

Owner
Ohio DOT
Letting
09 OCT 2025
Pay items
18
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1M P Dory Co$1,420,663Low+2.0%
2Lake Erie Construction Company$1,515,420+7.0%+9.0%
3Cleveland Barricading Systems LLC$1,600,782+13%+15%
ODOT contract 250483: bids by rank

Engineer's estimate: $1,392,000.

Bid tabulation

LinePay itemUnitQuantity1. M P Dory Co2. Lake Erie Construction Company3. Cleveland Barricading Systems LLC
1Ground mounted support, no. 3 post, as per plan (630E03101)FT62,290$9.50$10.20$8.15
2Ground mounted support, no. 4 post, as per plan (630E04101)FT2,423$13.50$15.00$15.00
3One way support, no. 3 post, as per plan (630E08005)FT634$10.00$15.00$17.00
4Sign post reflector (630E08600)EACH2,534$34.00$35.00$21.00
5Sign hanger assembly, span wire (630E79000)EACH10$300.00$480.00$420.00
6Sign support assembly, pole mounted (630E79500)EACH57$75.00$175.00$90.00
7Sign, flat sheet (630E80100)SF36,595$14.00$14.00$12.25
8Sign, double faced, mile marker (630E80600)EACH207$30.00$40.00$22.35
9Mainline reference marker (630E81000)EACH99$55.00$75.00$28.65
10Sign backing assembly (630E82000)EACH5$200.00$245.00$163.00
11Removal of ground mounted sign and disposal (630E84900)EACH7,447$8.00$10.00$16.15
12Removal of ground mounted sign and reerection (630E85100)EACH59$150.00$50.00$60.00
13Removal of ground mounted post support and disposal (630E86002)EACH5,320$12.00$15.00$17.00
14Removal of overhead mounted sign and disposal (630E87400)EACH10$100.00$125.00$225.00
15Removal of pole mounted sign and disposal (630E87500)EACH45$15.00$35.00$80.00
16Premium for contract performance bond and for payment bond (103E05000)LS1$10,000$7,237.00$6,286.00
17Maintaining traffic (614E11000)LS1$2,500.00$6,700.00$220,500
18Mobilization (624E10000)LS1$25,000$27,500$80,000
ODOT contract 250483: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy