ODOT contract 250469 bid tabulation

MED-US 224-15.27 (SPOT PATCHING / PAVEMENT REPAIR). Let by Ohio DOT on October 9, 2025, MED. 4 bids received; low bid $1,776,129 by Smith Paving & Excavating Inc, -18% against the engineer's estimate of $2,176,000.

Owner
Ohio DOT
Letting
09 OCT 2025
Pay items
42
Data through
12 NOV 2026

Bidders

RankBidderTotal bidAgainst the low bidAgainst the estimate
1Smith Paving & Excavating Inc$1,776,129Low-18%
2Perk Company Inc$2,030,000+14%-7.0%
3Karvo Companies Inc$2,275,000+28%+5.0%
4Shelly & Sands Inc$2,490,504+40%+14%
ODOT contract 250469: bids by rank

Engineer's estimate: $2,176,000.

Bid tabulation

LinePay itemUnitQuantity1. Smith Paving & Excavating Inc2. Perk Company Inc3. Karvo Companies Inc4. Shelly & Sands Inc
1Excavation, as per plan (203E10001)CY192$24.00$10.00$20.00$35.00
2Erosion control (832E30000)EACH1,000$1.00$1.00$1.00$1.00
3Full depth pavement removal and rigid replacement, type 1, class QC MS (255E15000)SY2,720$175.00$205.00$190.00$220.00
4Full depth pavement removal and rigid replacement, type 1, class QC MS (255E15000)SY2,703$175.00$260.00$310.00$350.00
5Full depth pavement removal and rigid replacement, type 1, class QC RS (255E19000)SY240$360.00$335.00$340.00$455.00
6Full depth pavement removal and rigid replacement, type 1, class QC RS (255E19000)SY110$380.00$400.00$375.00$765.00
7Full depth pavement sawing (255E20000)FT38,765$3.00$3.50$2.75$4.25
8Diamond grinding portland cement concrete pavement (257E10000)SY17,392$6.00$5.75$5.00$6.71
9Aggregate base, as per plan (304E20001)CY192$70.00$40.00$25.00$53.00
10RPM (621E00100)EACH80$93.50$41.00$45.00$215.00
11Raised pavement marker removed (621E54000)EACH80$75.00$25.00$1.00$11.00
12Edge line, 6" (646E10010)MI0.24$9,000.00$3,400.00$9,000.00$9,700.00
13Lane line, 6" (646E10110)MI0.05$20,000$11,000$20,000$21,500
14Center line (646E10200)MI0.24$10,000$4,500.00$10,000$10,700
15Channelizing line, 8" (646E10300)FT1,386$2.25$2.00$2.25$2.40
16Stop line (646E10400)FT189$13.50$12.00$13.50$14.50
17Transverse/diagonal line (646E10600)FT455$12.50$12.00$12.50$13.50
18Island marking (646E10800)SF42$17.50$9.00$17.50$19.00
19Lane arrow (646E20300)EACH45$225.00$150.00$225.00$242.00
20Dotted line, 6" (646E20504)FT470$2.00$1.75$2.00$2.15
21Removal of pavement marking (646E50100)FT3,086$0.75$0.53$0.75$0.81
22Removal of pavement marking (646E50300)MI2.07$2,650.00$2,401.59$2,650.00$2,850.00
23Wet reflective epoxy pavement marking, edge line, 6" (807E12010)MI1.04$7,250.00$5,700.00$7,250.00$7,800.00
24Wet reflective epoxy pavement marking, lane line, 6" (807E12110)MI0.96$2,750.00$2,100.00$2,750.00$2,950.00
25Wet reflective epoxy pavement marking, channelizing line, 8" (807E12300)FT2,556$2.50$3.00$2.50$2.70
26Grooving for 6" recessed pavement marking, (concrete) (850E20010)MI2$2,500.00$3,200.00$2,500.00$2,700.00
27Grooving for 8" recessed pavement marking, (concrete) (850E20120)FT2,556$1.00$2.50$1.00$1.10
28Law enforcement officer with patrol car for assistance (614E11110)HR400$125.00$125.00$125.00$105.00
29Detour signing (614E12420)LS1$7,500.00$8,015.24$10,000$8,000.00
30Portable changeable message sign, as per plan (614E18601)SNMT12$900.00$1,266.55$1,000.00$1,000.00
31Work zone lane line, class I, 6", 740.06, type I (614E20210)MI0.25$5,000.00$4,676.16$5,000.00$5,400.00
32Work zone center line, class I, 740.06, type I (614E21200)MI0.13$30,000$14,221$30,000$32,000
33Work zone edge line, class I, 6", 740.06, type I (614E22210)MI3.10$14,500$10,938$14,500$15,500
34Work zone channelizing line, class I, 8", 740.06, type I (614E23400)FT2,556$5.00$2.51$5.00$5.40
35Work zone dotted line, class I, 6", 740.06, type I (614E24402)FT4,267$1.50$1.05$1.50$1.60
36Work zone stop line, class I, 740.06, type I (614E26400)FT222$15.00$6.85$15.00$16.00
37Work zone arrow, class I, 740.06, type I (614E30400)EACH25$275.00$285.73$275.00$300.00
38Premium for contract performance bond and for payment bond (103E05000)LS1$20,000$20,000$25,000$15,300
39Maintaining traffic (614E11000)LS1$110,000$103,405$200,000$64,000
40Field office, type C (619E16020)MNTH3$1,500.00$2,050.00$3,000.00$6,300.00
41Construction layout stakes and surveying (623E10000)LS1$2,800.00$5,000.00$1,000.00$6,500.00
42Mobilization (624E10000)LS1$100,000$73,500$143,407$118,000
ODOT contract 250469: unit prices by line

The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.

Source

Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

Every contract let that day: ODOT letting of October 9, 2025. Compiled by Mirage Metrics.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy