Work zone channelizing line, class I, 8", 740.06, type I, ODOT 614E23400
Low bidders on ODOT contracts carried a median of $3.39 per FT for this item, over the 24 months to 12 NOV 2026, across 7 low bids. Half of all 24 bids fell between $2.82 and $5.00.
- Owner
- Ohio DOT
- Item
- 614E23400
- Unit
- FT
- Data through
- 12 NOV 2026
ODOT prints this item as “WORK ZONE CHANNELIZING LINE, CLASS I, 8", 740.06,”.
By year of letting
| Year | Contracts | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|---|
| 2020 | 6 | 6 | $2.10 | 29 | $2.00 |
| 2021 | 11 | 11 | $2.50 | 46 | $2.40 |
| 2022 | 7 | 7 | $3.10 | 24 | $3.62 |
| 2023 | 8 | 8 | $3.00 | 27 | $3.00 |
| 2024 | 5 | 5 | $7.00 | 11 | $7.00 |
| 2025 | 2 | 2 | $3.71 | 9 | $2.51 |
| 2026 | 5 | 5 | $3.39 | 15 | $3.39 |
Bid prices as published, not adjusted for inflation.
By county
| County | Low bids | Low-bid median | All bids | Median, all bids |
|---|---|---|---|---|
| CUY | 17 | $2.50 | 71 | $2.40 |
| HAM | 5 | $3.25 | 13 | $2.90 |
| FRA | 3 | $2.90 | 12 | $2.55 |
Countys with at least three low bids, over all lettings.
By quantity
| Quantity (FT) | Low bids | Low-bid median |
|---|---|---|
| 30 to 170 | 11 | $3.95 |
| 180 to 697 | 11 | $3.00 |
| 758 to 2,556 | 11 | $2.70 |
| 2,901 to 35,603 | 11 | $2.58 |
The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.
Who is lowest on this line
| Bidder | Lines bid | Lowest on the line |
|---|---|---|
| Perk Company Inc | 10 | 7 (70%) |
| Ruhlin Company | 8 | 6 (75%) |
| Shelly & Sands Inc | 11 | 5 (45%) |
| Karvo Companies Inc | 10 | 4 (40%) |
| Great Lakes Construction Co | 10 | 4 (40%) |
| Complete General Construction Company | 11 | 3 (27%) |
The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.
Latest contracts with this item
| Let | Contract | County | Quantity | Low bidder's price | Median | Bids | Low bidder | Source |
|---|---|---|---|---|---|---|---|---|
| 12 NOV 2026 | 264030 | CUY | 196 | $5.00 | $4.24 | 4 | J D Williamson Construction Co Inc | ODOT |
| 13 AUG 2026 | 260345 | CUY | 220 | $3.20 | $3.05 | 4 | Great Lakes Construction Co | ODOT |
| 26 MAR 2026 | 260124 | HAM | 9,600 | $3.39 | $3.39 | 2 | Barrett Paving Materials Inc | ODOT |
| 26 MAR 2026 | 260148 | FRA | 2,110 | $2.90 | $2.90 | 3 | Complete General Construction Company | ODOT |
| 29 JAN 2026 | 260064 | POR | 461 | $5.00 | $5.00 | 2 | Karvo Companies Inc | ODOT |
| 18 DEC 2025 | 250555 | FAY | 99 | $2.43 | $2.49 | 5 | John R Jurgensen Company | ODOT |
| 09 OCT 2025 | 250469 | MED | 2,556 | $5.00 | $5.00 | 4 | Smith Paving & Excavating Inc | ODOT |
| 13 JUN 2024 | 240270 | HAM | 480 | $7.35 | $7.35 | 2 | Barrett Paving Materials Inc | ODOT |
| 23 MAY 2024 | 240310 | PUT | 279 | $3.00 | $3.00 | 2 | Vernon Nagel Inc | ODOT |
| 18 APR 2024 | 240231 | BUT | 170 | $3.00 | $3.13 | 2 | Eagle Bridge Co | ODOT |
| 21 MAR 2024 | 240187 | SUM | 140 | $7.00 | $7.00 | 2 | S E T Inc | ODOT |
| 08 FEB 2024 | 240101 | NOB | 30 | $14.00 | $14.00 | 3 | Shelly & Sands Inc | ODOT |
| 09 NOV 2023 | 230543 | LAK | 6,186 | $3.00 | $3.00 | 7 | Ohio-West Virginia Excavating Co | ODOT |
| 28 SEP 2023 | 230468 | HAM | 758 | $2.20 | $2.90 | 4 | Adleta Inc | ODOT |
| 11 MAY 2023 | 230286 | CUY | 180 | $3.00 | $6.00 | 3 | Perk Company Inc | ODOT |
Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.
How these prices were read
ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
- Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
- Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
- Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
- The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.