ODOT contract 264030 bid tabulation
CUY-SR 43-04.80 Replace (BRIDGE REPLACEMENT (1 BRIDGE)). Let by Ohio DOT on November 12, 2026, CUY. 4 bids received; low bid $1,494,618 by J D Williamson Construction Co Inc, -3.6% against the engineer's estimate of $1,550,000.
- Owner
- Ohio DOT
- Letting
- 12 NOV 2026
- Pay items
- 86
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | J D Williamson Construction Co Inc | $1,494,618 | Low | -4.0% |
| 2 | Shook Company LLC | $1,888,889 | +26% | +22% |
| 3 | Alan Stone Co Inc | $2,204,420 | +47% | +42% |
| 4 | Madex Construction Co | $2,449,538 | +64% | +58% |
Engineer's estimate: $1,550,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. J D Williamson Construction Co Inc | 2. Shook Company LLC | 3. Alan Stone Co Inc | 4. Madex Construction Co |
|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $9,000.00 | $10,000 | $5,500.00 | $8,005.80 |
| 2 | Walk removed (202E30000) | SF | 1,613 | $2.40 | $10.00 | $3.00 | $5.79 |
| 3 | Curb removed (202E32000) | FT | 14 | $16.00 | $10.00 | $35.00 | $46.32 |
| 4 | Guardrail removed (202E38000) | FT | 403 | $6.00 | $3.00 | $15.00 | $11.58 |
| 5 | Excavation (203E10000) | CY | 220 | $60.00 | $50.00 | $30.00 | $70.53 |
| 6 | Embankment (203E20000) | CY | 110 | $30.00 | $70.00 | $50.00 | $75.26 |
| 7 | Subgrade compaction (204E10000) | SY | 394 | $8.00 | $5.00 | $15.00 | $4.63 |
| 8 | Guardrail, type MGS (606E15050) | FT | 195 | $22.00 | $50.00 | $25.00 | $34.74 |
| 9 | Anchor assembly, MGS type E (606E26150) | EACH | 1 | $2,500.00 | $3,750.00 | $3,100.00 | $4,052.63 |
| 10 | Anchor assembly, MGS type T (606E26550) | EACH | 3 | $1,400.00 | $2,000.00 | $1,800.00 | $1,968.42 |
| 11 | MGS bridge terminal assembly, type 1, as per plan (606E35003) | EACH | 2 | $3,200.00 | $3,500.00 | $4,000.00 | $4,631.58 |
| 12 | MGS bridge terminal assembly, type 2, as per plan (606E35103) | EACH | 2 | $950.00 | $1,500.00 | $1,200.00 | $1,852.63 |
| 13 | 4" concrete walk (608E10000) | SF | 2,995 | $10.50 | $10.00 | $8.50 | $23.16 |
| 14 | Curb ramp (608E52000) | SF | 209 | $32.00 | $50.00 | $40.00 | $40.53 |
| 15 | Monument assembly reconstructed to grade (623E39600) | EACH | 2 | $1,250.00 | $1,000.00 | $2,200.00 | $1,736.84 |
| 16 | Soil analysis test (659E00100) | EACH | 2 | $150.00 | $50.00 | $1,500.00 | $89.47 |
| 17 | Topsoil (659E00300) | CY | 25 | $70.00 | $75.00 | $150.00 | $75.26 |
| 18 | Seeding and mulching (659E10000) | SY | 221 | $5.00 | $7.00 | $15.00 | $11.58 |
| 19 | Repair seeding and mulching (659E14000) | SY | 11 | $1.00 | $1.00 | $65.00 | $5.79 |
| 20 | Inter-seeding (659E15000) | SY | 11 | $1.00 | $1.00 | $35.00 | $5.79 |
| 21 | Commercial fertilizer (659E20000) | TON | 0.05 | $500.00 | $1,000.00 | $700.00 | $1,800.00 |
| 22 | Lime (659E31000) | ACRE | 0.05 | $50.00 | $1,000.00 | $1,000.00 | $1,157.80 |
| 23 | Water (659E35000) | MGAL | 1.79 | $2.00 | $1.00 | $130.00 | $7.53 |
| 24 | Erosion control (832E30000) | EACH | 20,000 | $1.00 | $1.00 | $1.00 | $1.00 |
| 25 | 6" conduit, type C (611E01100) | FT | 5 | $70.00 | $20.00 | $110.00 | $115.79 |
| 26 | 12" conduit, type C (611E04600) | FT | 15 | $90.00 | $40.00 | $150.00 | $144.74 |
| 27 | 15" conduit, type C (611E06100) | FT | 26 | $100.00 | $60.00 | $280.00 | $173.68 |
| 28 | 18" conduit, type C (611E07600) | FT | 8 | $100.00 | $100.00 | $490.00 | $231.58 |
| 29 | 30" conduit, type C (611E13600) | FT | 20 | $120.00 | $200.00 | $290.00 | $260.53 |
| 30 | Catch basin, misc.: vertical curb inlet ST-5B (cit (611E98690) | EACH | 1 | $4,500.00 | $10,000 | $6,100.00 | $5,210.53 |
| 31 | Inlet adjusted to grade (611E99150) | EACH | 1 | $1,200.00 | $2,000.00 | $2,000.00 | $1,736.84 |
| 32 | Inlet reconstructed to grade (611E99154) | EACH | 1 | $1,500.00 | $3,000.00 | $3,700.00 | $2,315.79 |
| 33 | Manhole adjusted to grade (611E99654) | EACH | 2 | $1,400.00 | $3,000.00 | $1,400.00 | $1,852.63 |
| 34 | Manhole reconstructed to grade (611E99660) | EACH | 1 | $1,700.00 | $4,000.00 | $1,400.00 | $2,663.16 |
| 35 | Manhole, misc.:standard type "C" eccentric pre-cas (611E99690) | EACH | 4 | $4,100.00 | $10,000 | $6,300.00 | $6,368.42 |
| 36 | Special - miscellaneous metal (611E99820) | LB | 500 | $3.00 | $10.00 | $6.50 | $4.63 |
| 37 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 133 | $590.00 | $600.00 | $890.00 | $318.42 |
| 38 | Aggregate base (304E20000) | CY | 61 | $125.00 | $150.00 | $140.00 | $133.16 |
| 39 | Tack coat (407E10000) | GAL | 105 | $4.00 | $5.00 | $4.50 | $46.32 |
| 40 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 51 | $775.00 | $800.00 | $870.00 | $1,736.84 |
| 41 | Asphalt concrete surface course, type 1, (449), as per plan (441E70101) | CY | 10 | $1,150.00 | $1,200.00 | $930.00 | $1,736.84 |
| 42 | Curb, type 6 (609E26000) | FT | 443 | $40.00 | $50.00 | $70.00 | $70.53 |
| 43 | Longitudinal joint adhesive (875E10000) | LB | 60 | $15.00 | $25.00 | $70.00 | $28.95 |
| 44 | Ground mounted support, no. 2 post (630E02100) | FT | 19.50 | $50.00 | $35.00 | $65.00 | $40.53 |
| 45 | Sign, flat sheet (630E80100) | SF | 52.50 | $20.00 | $40.00 | $25.00 | $42.84 |
| 46 | Removal of ground mounted sign and disposal (630E84900) | EACH | 4 | $15.00 | $20.00 | $20.00 | $70.53 |
| 47 | Removal of ground mounted post support and disposal (630E86002) | EACH | 4 | $15.00 | $25.00 | $20.00 | $70.53 |
| 48 | Edge line, 6", type 1 (642E00104) | MI | 0.24 | $3,300.00 | $4,500.00 | $4,100.00 | $5,789.46 |
| 49 | Center line, type 1 (642E00300) | MI | 0.24 | $5,000.00 | $4,500.00 | $6,300.00 | $5,905.25 |
| 50 | Lane arrow, type 1 (642E01300) | EACH | 2 | $225.00 | $100.00 | $280.00 | $128.53 |
| 51 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 40 | $100.00 | $75.00 | $190.00 | $115.79 |
| 52 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 8 | $2,100.00 | $3,000.00 | $2,600.00 | $2,778.95 |
| 53 | Asphalt concrete for maintaining traffic (614E13000) | CY | 10 | $300.00 | $500.00 | $750.00 | $578.95 |
| 54 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,400.00 | $1,200.00 | $1,300.00 | $1,273.68 |
| 55 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.22 | $17,500 | $13,000 | $22,000 | $15,053 |
| 56 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 1.49 | $7,500.00 | $7,000.00 | $9,400.00 | $8,105.26 |
| 57 | Work zone channelizing line, class I, 8", 740.06, type I (614E23400) | FT | 196 | $5.00 | $3.00 | $6.50 | $3.47 |
| 58 | Work zone dotted line, class I, 4", 740.06, type I (614E24400) | FT | 65 | $3.50 | $2.00 | $4.50 | $2.32 |
| 59 | Work zone stop line, class I, 740.06, type I (614E26400) | FT | 20 | $25.00 | $3.00 | $30.00 | $3.47 |
| 60 | Pavement for maintaining traffic, class A (615E20000) | SY | 663 | $140.00 | $140.00 | $180.00 | $231.58 |
| 61 | Portable barrier, anchored (622E41110) | FT | 1,370 | $45.00 | $50.00 | $55.00 | $57.89 |
| 62 | Portions of structure removed, over 20 foot span, as per plan (202E11203) | LS | 1 | $145,000 | $200,000 | $222,000 | $266,892 |
| 63 | Cofferdams and excavation bracing, as per plan (503E11101) | LS | 1 | $80,000 | $200,000 | $183,000 | $289,474 |
| 64 | Unclassified excavation (503E21100) | CY | 500 | $44.00 | $100.00 | $85.00 | $75.26 |
| 65 | Epoxy coated steel reinforcement (509E10000) | LB | 8,036 | $2.10 | $3.00 | $2.50 | $4.63 |
| 66 | Concrete reinforcement, replacement of existing concrete reinforcement, as per plan (509E20001) | LB | 100 | $4.00 | $50.00 | $45.00 | $11.58 |
| 67 | Class QC1 concrete, retaining/wingwall not including footing (511E46000) | SY | 19 | $2,000.00 | $2,500.00 | $2,800.00 | $2,656.51 |
| 68 | Class QC2 concrete, sidewalk (511E51510) | CY | 18 | $1,600.00 | $2,500.00 | $1,300.00 | $1,157.89 |
| 69 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 75 | $54.00 | $50.00 | $65.00 | $92.63 |
| 70 | Sealing of concrete surfaces (epoxy-urethane), as per plan (512E10101) | SY | 39 | $35.00 | $100.00 | $100.00 | $173.68 |
| 71 | Type 2 waterproofing (512E33000) | SY | 70 | $43.00 | $50.00 | $140.00 | $104.21 |
| 72 | Type 3 waterproofing (512E33010) | SY | 246 | $45.00 | $50.00 | $60.00 | $92.63 |
| 73 | 1" preformed expansion joint filler (516E13600) | SF | 50 | $9.00 | $10.00 | $2.00 | $11.58 |
| 74 | Railing, concrete, as per plan (517E74501) | FT | 70 | $300.00 | $300.00 | $920.00 | $694.74 |
| 75 | Porous backfill with geotextile fabric (518E21050) | SY | 29 | $135.00 | $200.00 | $190.00 | $173.68 |
| 76 | 6" perforated corrugated plastic pipe (518E40000) | FT | 51 | $22.00 | $25.00 | $30.00 | $63.68 |
| 77 | 6" non-perforated corrugated plastic pipe, including specials (518E40010) | FT | 13 | $44.00 | $25.00 | $120.00 | $104.21 |
| 78 | Special - form liner (530E13000) | SF | 487 | $20.00 | $50.00 | $75.00 | $46.32 |
| 79 | Rock channel protection, type C with filter, as per plan (601E32201) | CY | 98 | $150.00 | $225.00 | $250.00 | $478.95 |
| 80 | Conduit, type A, precast reinforced concrete three sided flat topped culvert, as per plan (611E70001) | FT | 60 | $6,000.00 | $5,274.00 | $7,500.00 | $8,860.70 |
| 81 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $15,000 | $28,000 | $15,000 | $91,918 |
| 82 | Maintaining traffic (614E11000) | LS | 1 | $65,000 | $120,000 | $224,000 | $57,895 |
| 83 | Field office, type B, as per plan (619E16011) | MNTH | 3 | $5,000.00 | $2,500.00 | $2,400.00 | $2,315.79 |
| 84 | Construction layout stakes and surveying (623E10000) | LS | 1 | $20,000 | $25,000 | $19,000 | $46,316 |
| 85 | Mobilization (624E10000) | LS | 1 | $73,000 | $75,001 | $58,000 | $87,740 |
| 100 | Roads for maintaining traffic (615E10000) | LS | 1 | $25,000 | $40,000 | $41,000 | $18,947 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of November 12, 2026. Compiled by Mirage Metrics.