ODOT contract 250555 bid tabulation
FAY-US 22-06.21 (INTERSECTION). Let by Ohio DOT on December 18, 2025, FAY. 5 bids received; low bid $2,247,017 by John R Jurgensen Company, +6.1% against the engineer's estimate of $2,118,000.
- Owner
- Ohio DOT
- Letting
- 18 DEC 2025
- Pay items
- 128
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | John R Jurgensen Company | $2,247,017 | Low | +6.0% |
| 2 | Fillmore Construction | $2,248,937 | 0.0% | +6.0% |
| 3 | R B Jergens Contractors Inc | $2,249,408 | 0.0% | +6.0% |
| 4 | Complete General Construction Company | $2,254,979 | 0.0% | +6.0% |
| 5 | Axis Civil Construction LLC | $2,260,844 | +1.0% | +7.0% |
Engineer's estimate: $2,118,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. John R Jurgensen Company | 2. Fillmore Construction | 3. R B Jergens Contractors Inc | 4. Complete General Construction Company | 5. Axis Civil Construction LLC |
|---|---|---|---|---|---|---|---|---|
| 1 | Clearing and grubbing (201E11000) | LS | 1 | $2,576.98 | $10,000 | $10,315 | $13,000 | $20,000 |
| 2 | Pavement removed (202E23000) | SY | 445 | $14.00 | $8.00 | $17.49 | $15.00 | $20.00 |
| 3 | Concrete median removed (202E30600) | SY | 20 | $33.41 | $25.00 | $65.14 | $60.00 | $50.00 |
| 4 | Curb removed (202E32000) | FT | 560 | $11.39 | $10.00 | $8.09 | $10.00 | $16.00 |
| 5 | Removal misc.: (wood post) (202E98100) | EACH | 5 | $272.89 | $100.00 | $127.44 | $80.00 | $150.00 |
| 6 | Excavation (203E10000) | CY | 868 | $20.15 | $30.00 | $17.89 | $35.00 | $30.00 |
| 7 | Embankment (203E20000) | CY | 2,543 | $26.35 | $50.00 | $21.32 | $7.00 | $36.00 |
| 8 | Embankment, as per plan (203E20001) | CY | 58 | $95.21 | $200.00 | $66.35 | $250.00 | $140.00 |
| 9 | Subgrade compaction (204E10000) | SY | 6,708 | $2.14 | $5.00 | $3.88 | $4.50 | $3.00 |
| 10 | Excavation of subgrade (204E13000) | CY | 400 | $50.11 | $30.00 | $27.37 | $35.00 | $30.00 |
| 11 | Granular material, type B (204E30010) | CY | 400 | $111.39 | $100.00 | $55.35 | $60.00 | $125.00 |
| 12 | Proof rolling (204E45000) | HR | 3 | $251.95 | $150.00 | $321.32 | $300.00 | $300.00 |
| 13 | Geotextile fabric (204E50000) | SY | 1,547 | $3.17 | $3.00 | $3.73 | $3.00 | $3.00 |
| 14 | Detectable warning (608E53020) | SF | 96 | $50.00 | $30.00 | $355.74 | $40.00 | $50.00 |
| 15 | Inspection and compaction testing of unbound materials (878E25000) | LS | 1 | $15,730 | $10,000 | $33,517 | $27,500 | $22,000 |
| 16 | Tied concrete block mat with type 2 underlayment (601E21060) | SY | 73 | $189.24 | $30.00 | $101.59 | $120.00 | $110.00 |
| 17 | Soil analysis test (659E00100) | EACH | 1 | $150.00 | $500.00 | $76.80 | $75.00 | $150.00 |
| 18 | Topsoil (659E00300) | CY | 662 | $43.13 | $50.00 | $30.21 | $65.00 | $48.00 |
| 19 | Seeding and mulching (659E10000) | SY | 5,108 | $1.35 | $1.25 | $1.95 | $1.90 | $1.00 |
| 20 | Repair seeding and mulching (659E14000) | SY | 256 | $1.35 | $2.20 | $1.95 | $1.90 | $1.00 |
| 21 | Inter-seeding (659E15000) | SY | 256 | $1.00 | $2.20 | $1.95 | $1.90 | $1.00 |
| 22 | Commercial fertilizer (659E20000) | TON | 0.69 | $925.00 | $1,400.00 | $778.26 | $760.00 | $1,250.00 |
| 23 | Lime (659E31000) | ACRE | 1.06 | $100.00 | $450.00 | $51.20 | $50.00 | $150.00 |
| 24 | Water (659E35000) | MGAL | 28 | $1.00 | $100.00 | $51.20 | $50.00 | $1.00 |
| 25 | Mowing (659E40000) | MSF | 2 | $200.00 | $1,000.00 | $184.33 | $180.00 | $100.00 |
| 26 | Slope erosion protection (670E00500) | SY | 842 | $3.20 | $2.00 | $4.46 | $4.35 | $2.50 |
| 27 | Storm water pollution prevention plan (832E15000) | LS | 1 | $2,500.00 | $3,500.00 | $2,457.68 | $2,500.00 | $2,500.00 |
| 28 | Storm water pollution prevention inspections (832E15002) | LS | 1 | $3,880.00 | $5,000.00 | $8,601.87 | $10,000 | $7,350.00 |
| 29 | Storm water pollution prevention inspection software (832E15010) | LS | 1 | $9,934.04 | $10,000 | $10,240 | $10,000 | $10,000 |
| 30 | Erosion control (832E30000) | EACH | 40,000 | $1.00 | $1.00 | $1.00 | $1.00 | $1.00 |
| 31 | 6" unclassified pipe underdrains (605E13300) | FT | 531 | $56.17 | $20.00 | $25.08 | $21.00 | $25.00 |
| 32 | 6" base pipe underdrains (605E14000) | FT | 1,786 | $37.78 | $12.00 | $19.85 | $20.00 | $20.00 |
| 33 | 6" conduit, type F (611E01500) | FT | 100 | $89.38 | $50.00 | $33.53 | $22.00 | $25.00 |
| 34 | Precast reinforced concrete outlet (611E99710) | EACH | 10 | $750.23 | $500.00 | $1,103.26 | $250.00 | $500.00 |
| 35 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 1,818 | $5.15 | $5.00 | $5.64 | $7.85 | $8.00 |
| 36 | Asphalt concrete base, PG64-22, (449) (301E56000) | CY | 974 | $240.00 | $240.00 | $263.02 | $201.25 | $215.00 |
| 37 | Aggregate base (304E20000) | CY | 1,118 | $110.52 | $80.00 | $59.39 | $90.00 | $125.00 |
| 38 | Non-tracking tack coat (407E20000) | GAL | 1,287 | $5.00 | $5.00 | $5.48 | $4.10 | $4.00 |
| 39 | Asphalt concrete surface course, type 1, (449), (driveways) (441E70500) | CY | 3 | $2,000.00 | $500.00 | $2,191.88 | $525.00 | $1,500.00 |
| 40 | Asphalt concrete surface course, 12.5 MM, type A (446) (442E10000) | CY | 291 | $318.00 | $280.00 | $348.51 | $274.25 | $274.00 |
| 41 | Asphalt concrete intermediate course, 12.5 MM, type A (446) (442E10080) | CY | 250 | $450.00 | $260.00 | $493.17 | $277.25 | $280.00 |
| 42 | 7" non-reinforced concrete pavement, class QC 1P with QC/QA (452E11020) | SY | 358 | $114.39 | $103.00 | $131.89 | $105.00 | $175.00 |
| 43 | Combination curb and gutter, type 3 (609E18000) | FT | 1,017 | $45.97 | $40.00 | $32.83 | $37.00 | $39.00 |
| 44 | Curb, type 4-C (609E24510) | FT | 558 | $35.29 | $30.00 | $20.76 | $45.00 | $39.00 |
| 45 | Curb, type 6 (609E26000) | FT | 484 | $38.36 | $32.00 | $23.37 | $35.00 | $35.00 |
| 46 | Combination curb and gutter, type 9 (609E31000) | FT | 290 | $45.02 | $40.00 | $26.08 | $45.00 | $40.00 |
| 47 | Concrete median (609E71000) | SF | 5,386 | $16.05 | $15.00 | $11.54 | $14.00 | $17.00 |
| 48 | Connection, fused pull apart (625E00450) | EACH | 20 | $275.00 | $105.26 | $281.61 | $145.00 | $125.00 |
| 49 | Connection, unfused permanent (625E00480) | EACH | 21 | $225.00 | $74.32 | $230.41 | $115.00 | $125.00 |
| 50 | Light pole, conventional, AT15B40 (625E10490) | EACH | 10 | $3,973.13 | $4,108.29 | $4,068.61 | $3,000.00 | $4,000.00 |
| 51 | Light pole foundation, 24" X 8' deep (625E14100) | EACH | 10 | $1,750.00 | $2,000.00 | $1,792.06 | $2,400.00 | $2,600.00 |
| 52 | No. 4 AWG 2400 volt distribution cable (625E23200) | FT | 1,845 | $1.85 | $3.75 | $1.89 | $3.75 | $5.00 |
| 53 | No. 10 AWG pole and bracket cable (625E23400) | FT | 1,650 | $0.51 | $1.32 | $0.52 | $2.50 | $0.50 |
| 54 | Conduit, 3", 725.04 (625E25500) | FT | 1,066 | $2.54 | $22.01 | $2.60 | $30.00 | $36.00 |
| 55 | Conduit, jacked or drilled, 725.04 (3") (625E25902) | FT | 221 | $55.00 | $75.97 | $56.32 | $51.00 | $60.00 |
| 56 | Luminaire, conventional, solid state (LED), as per plan (625E26253) | EACH | 10 | $476.01 | $284.00 | $487.45 | $540.00 | $478.00 |
| 57 | Trench (625E29000) | FT | 1,039 | $20.00 | $11.37 | $20.48 | $9.00 | $14.00 |
| 58 | Pull box, 725.08, 18" (625E30700) | EACH | 5 | $643.37 | $1,356.66 | $658.83 | $1,300.00 | $1,200.00 |
| 59 | Pull box, 725.08, 24" (625E30706) | EACH | 1 | $846.35 | $1,500.00 | $866.69 | $1,500.00 | $1,500.00 |
| 60 | Pull box removed (625E31510) | EACH | 2 | $575.00 | $401.00 | $588.82 | $250.00 | $350.00 |
| 61 | Ground rod (625E32000) | EACH | 10 | $125.00 | $225.00 | $128.00 | $325.00 | $265.00 |
| 62 | Power service, as per plan (625E34001) | EACH | 1 | $2,575.00 | $13,500 | $2,636.88 | $9,500.00 | $10,500 |
| 63 | Underground warning marking tape (625E36010) | FT | 1,260 | $1.75 | $2.20 | $1.79 | $1.25 | $3.00 |
| 64 | Temporary lighting (625E39000) | LS | 1 | $21,175 | $8,500.00 | $21,684 | $17,000 | $10,000 |
| 65 | Special - maintain existing lighting (625E40000) | LS | 1 | $15,000 | $2,000.00 | $15,360 | $1,700.00 | $8,000.00 |
| 66 | Light pole removed for storage, as per plan (625E75403) | EACH | 2 | $1,250.00 | $401.00 | $1,280.04 | $375.00 | $400.00 |
| 67 | Disconnect circuit, as per plan (625E75801) | EACH | 1 | $750.00 | $251.00 | $768.02 | $350.00 | $125.00 |
| 68 | Arc flash calculations and label, fay-22-6.21 (625E76000) | EACH | 1 | $3,500.00 | $5,000.00 | $3,584.11 | $3,650.00 | $3,450.00 |
| 69 | Conduit riser, 2" diameter (632E70400) | EACH | 1 | $1,750.00 | $1,511.00 | $1,792.06 | $1,100.00 | $725.00 |
| 70 | Controller work pad (633E67200) | EACH | 1 | $1,275.00 | $2,600.00 | $1,305.64 | $1,200.00 | $750.00 |
| 71 | RPM (621E00100) | EACH | 69 | $89.00 | $89.00 | $91.14 | $78.00 | $89.00 |
| 72 | Ground mounted support, no. 2 post (630E02100) | FT | 248 | $17.00 | $17.00 | $21.28 | $16.00 | $17.00 |
| 73 | Ground mounted support, no. 3 post (630E03100) | FT | 178 | $18.00 | $18.50 | $23.09 | $17.50 | $18.00 |
| 74 | Ground mounted support, no. 4 post (630E04100) | FT | 59 | $25.00 | $25.00 | $30.31 | $20.00 | $25.00 |
| 75 | Ground mounted structural beam support, S4X7.7 (630E06400) | FT | 26 | $30.00 | $30.00 | $30.72 | $74.00 | $30.00 |
| 76 | Sign post reflector (630E08600) | EACH | 15 | $50.00 | $50.00 | $67.09 | $45.00 | $50.00 |
| 77 | Breakaway structural beam connection (630E09000) | EACH | 2 | $200.00 | $200.00 | $204.81 | $645.00 | $200.00 |
| 78 | Sign, flat sheet (630E80100) | SF | 220 | $25.00 | $25.00 | $24.89 | $18.00 | $25.00 |
| 79 | Sign, ground mounted extrusheet (630E80200) | SF | 27 | $30.00 | $30.00 | $30.72 | $29.00 | $30.00 |
| 80 | Removal of ground mounted sign and disposal (630E84900) | EACH | 30 | $20.00 | $22.00 | $16.96 | $10.00 | $20.00 |
| 81 | Removal of ground mounted post support and disposal (630E86002) | EACH | 26 | $20.00 | $22.00 | $22.61 | $15.00 | $20.00 |
| 82 | Removal of ground mounted structural beam support (630E86102) | EACH | 3 | $500.00 | $500.00 | $22.53 | $365.00 | $500.00 |
| 83 | Edge line, 6" (644E00104) | MI | 0.74 | $8,085.00 | $8,085.00 | $8,279.30 | $5,395.00 | $5,395.00 |
| 84 | Center line (644E00300) | MI | 0.14 | $10,770 | $10,770 | $11,029 | $8,305.00 | $8,305.00 |
| 85 | Transverse/diagonal line (644E00700) | FT | 45 | $12.25 | $12.25 | $12.54 | $10.40 | $10.40 |
| 86 | Railroad symbol marking (644E01000) | EACH | 1 | $750.00 | $750.00 | $768.02 | $525.00 | $525.00 |
| 87 | Dotted line, 12" (644E01520) | FT | 203 | $3.65 | $3.65 | $3.74 | $6.20 | $6.20 |
| 88 | Yield line (644E20800) | FT | 73 | $15.75 | $15.75 | $16.13 | $41.50 | $41.50 |
| 89 | Traffic compacted surface, type A or B (410E12000) | CY | 50 | $195.18 | $50.00 | $71.91 | $70.00 | $75.00 |
| 90 | Traffic compacted surface, type C (410E13000) | CY | 50 | $195.18 | $200.00 | $71.91 | $80.00 | $75.00 |
| 91 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 20 | $143.53 | $120.00 | $155.32 | $90.00 | $75.00 |
| 92 | Increased barrier delineation (614E11630) | FT | 200 | $2.00 | $3.00 | $2.19 | $3.00 | $2.20 |
| 93 | Work zone impact attenuator, 24" wide hazards, (unidirectional) (614E12380) | EACH | 7 | $2,000.00 | $2,000.00 | $1,911.80 | $2,500.00 | $2,400.00 |
| 94 | Detour signing (614E12420) | LS | 1 | $11,825 | $20,000 | $17,395 | $30,000 | $18,000 |
| 95 | Asphalt concrete for maintaining traffic (614E13000) | CY | 50 | $246.87 | $400.00 | $136.99 | $250.00 | $250.00 |
| 96 | Barrier reflector, type 1, (BI-directional) (614E13310) | EACH | 37 | $10.00 | $12.00 | $9.41 | $7.00 | $9.00 |
| 97 | Barrier reflector, type 1, (one-way) (614E13310) | EACH | 49 | $10.00 | $10.00 | $9.41 | $6.00 | $9.00 |
| 98 | Object marker, one way (614E13350) | EACH | 49 | $20.00 | $20.00 | $19.13 | $10.00 | $18.00 |
| 99 | Object marker, two way (614E13360) | EACH | 37 | $20.00 | $21.00 | $21.24 | $12.00 | $20.00 |
| 100 | Work zone lane line, class I, 6" (614E20010) | MI | 0.04 | $1,115.00 | $1,115.00 | $1,141.75 | $610.00 | $1,115.00 |
| 101 | Work zone lane line, class III, 4", 642 paint (614E20550) | MI | 0.01 | $1,340.00 | $1,340.00 | $1,372.00 | $520.00 | $1,340.00 |
| 102 | Work zone center line, class I (614E21000) | MI | 0.58 | $2,850.00 | $2,850.00 | $2,918.48 | $2,255.00 | $2,850.00 |
| 103 | Work zone center line, class I, 740.06, type I (614E21200) | MI | 0.22 | $12,273 | $12,273 | $12,568 | $15,745 | $12,500 |
| 104 | Work zone center line, class III, 642 paint (614E21550) | MI | 0.08 | $1,860.00 | $1,860.00 | $1,904.75 | $1,500.00 | $1,860.00 |
| 105 | Work zone edge line, class I, 4" (614E22000) | MI | 1.34 | $1,780.00 | $1,780.00 | $1,822.78 | $1,315.00 | $1,780.00 |
| 106 | Work zone edge line, class I, 6" (614E22010) | MI | 0.64 | $2,340.00 | $2,340.00 | $2,396.23 | $1,575.00 | $2,340.00 |
| 107 | Work zone edge line, class I, 4", 740.06, type I (614E22200) | MI | 1.38 | $7,101.96 | $7,101.96 | $7,272.63 | $10,450 | $7,000.00 |
| 108 | Work zone edge line, class III, 4", 642 paint (614E22350) | MI | 0.48 | $1,565.00 | $1,565.00 | $1,602.60 | $975.00 | $1,565.00 |
| 109 | Work zone channelizing line, class I, 8" (614E23000) | FT | 862 | $1.00 | $1.00 | $1.02 | $0.80 | $1.00 |
| 110 | Work zone channelizing line, class I, 8", 740.06, type I (614E23400) | FT | 99 | $2.43 | $2.43 | $2.49 | $3.00 | $2.50 |
| 111 | Work zone dotted line, class I (614E24000) | FT | 317 | $0.95 | $95.00 | $0.97 | $0.45 | $1.00 |
| 112 | Work zone dotted line, class I, 4", 740.06, type I (614E24400) | FT | 279 | $1.55 | $1.55 | $1.59 | $1.30 | $1.55 |
| 113 | Work zone dotted line, class III, 4", 642 paint (614E24610) | FT | 87 | $0.90 | $9.00 | $0.92 | $0.45 | $0.90 |
| 114 | Work zone transverse/diagonal line, class III, 642 paint (614E25620) | FT | 375 | $3.25 | $3.25 | $3.33 | $0.90 | $3.25 |
| 115 | Work zone arrow, class I (614E30000) | EACH | 4 | $100.00 | $100.00 | $102.40 | $135.00 | $100.00 |
| 116 | Work zone arrow, class I, 740.06, type I (614E30400) | EACH | 1 | $229.05 | $229.05 | $234.55 | $615.00 | $230.00 |
| 117 | Work zone railroad symbol marking, class I (614E32000) | EACH | 1 | $475.00 | $475.00 | $486.41 | $200.00 | $475.00 |
| 118 | Business entrance sign (614E40050) | EACH | 4 | $125.00 | $1,000.00 | $217.83 | $400.00 | $215.00 |
| 119 | Pavement for maintaining traffic, class B (615E25000) | SY | 2,813 | $80.00 | $85.00 | $96.40 | $65.00 | $55.00 |
| 120 | Water (616E10000) | MGAL | 36 | $150.85 | $100.00 | $141.02 | $80.00 | $1.00 |
| 121 | Portable barrier, unanchored (622E41100) | FT | 4,260 | $18.25 | $20.00 | $18.44 | $18.00 | $29.00 |
| 122 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $18,621 | $28,000 | $8,853.24 | $17,500 | $12,950 |
| 123 | Maintaining traffic (614E11000) | LS | 1 | $55,798 | $175,000 | $92,000 | $125,000 | $100,000 |
| 124 | Construction layout stakes and surveying (623E10000) | LS | 1 | $12,945 | $25,000 | $27,751 | $107,500 | $29,000 |
| 125 | Mobilization (624E10000) | LS | 1 | $100,000 | $125,000 | $100,000 | $100,000 | $100,000 |
| 200 | Ground mounted structural beam support foundation (630E84500) | EACH | 2 | $1,200.00 | $1,250.00 | $1,280.04 | $1,650.00 | $1,200.00 |
| 201 | Pavement removed, as per plan (202E23001) | SY | 8,767 | $16.30 | $10.00 | $20.67 | $27.00 | $16.00 |
| 202 | Roads for maintaining traffic (615E10000) | LS | 1 | $67,041 | $5,000.00 | $50,102 | $42,500 | $65,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of December 18, 2025. Compiled by Mirage Metrics.
Your own bid history, read the same way
Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.