Work zone channelizing line, class III, 8", 642 paint, ODOT 614E23680

Low bidders on ODOT contracts carried a median of $0.80 per FT for this item, over the 24 months to 12 NOV 2026, across 103 low bids. Half of all 320 bids fell between $0.60 and $1.00.

Owner
Ohio DOT
Item
614E23680
Unit
FT
Data through
12 NOV 2026

ODOT prints this item as “WORK ZONE CHANNELIZING LINE, CLASS III, 8", 642 PA”.

$0.80Low bidder's median, per FT
$0.75Median of all bids, per FT
103Contracts in the window

By year of letting

Work zone channelizing line, class III, 8", 642 paint, ODOT: unit prices by year
YearContractsLow bidsLow-bid medianAll bidsMedian, all bids
20205959$0.60201$0.55
20216467$0.55237$0.55
20227376$0.78215$0.75
20236564$0.85182$0.85
20245252$0.75151$0.85
20255353$0.70171$0.70
20264646$0.88137$0.75

Bid prices as published, not adjusted for inflation.

By county

CountyLow bidsLow-bid medianAll bidsMedian, all bids
POR7$0.6028$0.57
LAK4$0.6220$0.62
MOT5$0.8015$0.80
FRA4$0.6814$0.75
CUY4$1.0214$1.00
SUM3$0.5013$0.60
HAM4$0.7013$0.70
MAH3$0.7512$0.75
GEA3$0.5711$0.60
COL3$1.0010$0.70
KNO3$0.909$0.90
ROS3$0.628$0.58
Work zone channelizing line, class III, 8", 642 paint, ODOT: unit prices by county, last 24 months

Countys with at least three low bids, over the last 24 months.

By quantity

Quantity (FT)Low bidsLow-bid median
60 to 42325$1.00
523 to 1,13626$1.00
1,138 to 3,01326$0.65
3,041 to 18,06026$0.66
Work zone channelizing line, class III, 8", 642 paint, ODOT: low bidder's median by quantity band

The low bids split into four bands of equal count by the quantity on the contract. Larger quantities usually carry lower unit prices.

Who is lowest on this line

BidderLines bidLowest on the line
Kokosing Construction Company Inc11394 (83%)
Shelly Company15792 (59%)
Karvo Companies Inc11690 (78%)
Shelly & Sands Inc13776 (55%)
John R Jurgensen Company7668 (89%)
Barrett Paving Materials Inc8867 (76%)
Work zone channelizing line, class III, 8", 642 paint, ODOT: bidders most often lowest on this line

The lowest unit price on each line, whoever won the contract, over all lettings in the data, for firms with five lines or more.

Latest contracts with this item

LetContractCountyQuantityLow bidder's priceMedianBidsLow bidderSource
29 OCT 2026260399CUY3,494$1.00$0.724Tri-Mor CorpODOT
15 OCT 2026260426LAK1,365$0.65$0.665Geauga Highway CoODOT
15 OCT 2026260462HAM541$0.75$0.752Barrett Paving Materials IncODOT
15 OCT 2026260470MOT3,674$1.00$1.002Barrett Paving Materials IncODOT
15 OCT 2026260472ROS7,412$0.62$0.663Fillmore ConstructionODOT
15 OCT 2026260482District 11268$1.50$11.624Aad Contracting IncODOT
01 OCT 2026260432POR725$0.60$0.604Shelly & Sands IncODOT
17 SEP 2026260400ASD5,952$0.75$0.572Shelly & Sands IncODOT
17 SEP 2026260410MAR18,060$1.00$0.972Shelly & Sands IncODOT
27 AUG 2026260378AUG4,560$1.00$0.972Shelly CompanyODOT
27 AUG 2026260380CLA1,150$0.55$0.552A & B Asphalt CorporationODOT
13 AUG 2026260364KNO793$1.00$1.004Complete General Construction CompanyODOT
30 JUL 2026260347FAY1,550$1.00$1.002John R Jurgensen CompanyODOT
30 JUL 2026260350HAS201$1.50$1.504Saorsa Construction Ohio, Inc.ODOT
30 JUL 2026260354MAH12,570$0.66$0.684Marucci & Gaffney Excavating CoODOT
Latest ODOT contracts carrying Work zone channelizing line, class III, 8", 642 paint

Filter this item by your own quantity, county and period, or check your price against it, in the ODOT explorer.

How these prices were read

ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.

  • Statistics leave out bids over three times the low bid, zero or negative prices and token prices under 5% of the median.
  • Item codes and units are ODOT's own: this item is compared with ODOT contracts only.
  • Prices are bid prices, not paid prices. Use them as a reference range, never as a quote.
  • The data runs to the ODOT letting of 12 NOV 2026 and was rebuilt on 26 NOV 2026.

Your own bid history, read the same way

Mirage deploys AI agents for heavy civil estimating teams: quantities from the plan set, specs and addenda read, and bid tabs compared, inside your systems and your rules.

We use your email to reply to you and, now and then, to tell you about Mirage. You can opt out at any time. Privacy policy