ODOT contract 260472 bid tabulation
ROS-SR 159-03.47 (TWO LANE RESURFACING). Let by Ohio DOT on October 15, 2026, ROS. 3 bids received; low bid $2,378,318 by Fillmore Construction, +15% against the engineer's estimate of $2,069,000.
- Owner
- Ohio DOT
- Letting
- 15 OCT 2026
- Pay items
- 57
- Data through
- 12 NOV 2026
Bidders
| Rank | Bidder | Total bid | Against the low bid | Against the estimate |
|---|---|---|---|---|
| 1 | Fillmore Construction | $2,378,318 | Low | +15% |
| 2 | Shelly & Sands Inc | $2,476,766 | +4.0% | +20% |
| 3 | Shelly Company | $2,583,382 | +9.0% | +25% |
Engineer's estimate: $2,069,000.
Bid tabulation
| Line | Pay item | Unit | Quantity | 1. Fillmore Construction | 2. Shelly & Sands Inc | 3. Shelly Company |
|---|---|---|---|---|---|---|
| 1 | Partial depth pavement repair (441), as per plan (251E01001) | SY | 1,070 | $64.00 | $65.00 | $128.00 |
| 2 | Pavement planing, asphalt concrete, 1.5" (254E01000) | SY | 110,569 | $2.50 | $2.50 | $2.80 |
| 3 | Patching planed surface (254E01600) | SY | 21,217 | $3.00 | $2.00 | $2.55 |
| 4 | Full depth pavement removal and rigid replacement, type 1, class QC RS, as per plan (255E19001) | SY | 160 | $300.00 | $1,050.00 | $730.00 |
| 5 | Full depth pavement sawing (255E20000) | FT | 600 | $5.40 | $5.40 | $7.60 |
| 6 | Non-tracking tack coat (407E20000) | GAL | 10,501 | $4.00 | $4.00 | $4.30 |
| 7 | Asphalt concrete surface course, type 1, (448), as per plan (441E50101) | CY | 4,204 | $234.50 | $235.00 | $219.25 |
| 8 | Asphalt concrete surface course, 12.5 MM, type A (449), as per plan (442E22101) | CY | 403 | $268.00 | $300.00 | $312.25 |
| 9 | RPM (621E00100) | EACH | 790 | $28.96 | $33.65 | $28.96 |
| 10 | RPM reflector (621E00300) | EACH | 38 | $20.00 | $20.00 | $20.00 |
| 11 | Raised pavement marker removed (621E54000) | EACH | 673 | $10.00 | $7.50 | $23.50 |
| 12 | Edge line, 6" (644E00104) | MI | 8.60 | $4,000.00 | $4,110.00 | $4,000.00 |
| 13 | Lane line, 6" (644E00204) | MI | 1.70 | $1,710.00 | $2,140.00 | $1,710.00 |
| 14 | Center line (644E00300) | MI | 4.26 | $4,350.00 | $5,315.00 | $4,350.00 |
| 15 | Channelizing line, 8" (644E00400) | FT | 3,503 | $2.10 | $1.25 | $2.10 |
| 16 | Channelizing line, 12" (644E00404) | FT | 698 | $2.75 | $1.50 | $2.75 |
| 17 | Stop line (644E00500) | FT | 448 | $9.50 | $5.50 | $9.50 |
| 18 | Transverse/diagonal line (644E00700) | FT | 1,597 | $7.90 | $5.25 | $7.90 |
| 19 | Island marking (644E00900) | SF | 141 | $3.00 | $5.00 | $3.00 |
| 20 | Lane arrow (644E01300) | EACH | 52 | $110.00 | $125.00 | $110.00 |
| 21 | Word on pavement, 96" (644E01410) | EACH | 6 | $190.00 | $150.00 | $190.00 |
| 22 | Dotted line, 6" (644E01510) | FT | 1,465 | $2.00 | $1.40 | $2.00 |
| 23 | Yield line (644E20800) | FT | 108 | $18.00 | $7.50 | $18.00 |
| 24 | Edge line, 6" (646E10010) | MI | 0.20 | $19,500 | $13,570 | $19,500 |
| 25 | Lane line, 6" (646E10110) | MI | 0.21 | $1,000.00 | $10,080 | $1,000.00 |
| 26 | Center line (646E10200) | MI | 0.21 | $30,000 | $15,320 | $30,000 |
| 27 | Channelizing line, 8" (646E10300) | FT | 355 | $4.50 | $2.00 | $4.50 |
| 28 | Transverse/diagonal line (646E10600) | FT | 2,111 | $9.00 | $10.25 | $9.00 |
| 29 | Island marking (646E10800) | SF | 100 | $4.50 | $6.50 | $4.50 |
| 30 | Lane arrow (646E20300) | EACH | 3 | $160.00 | $250.00 | $160.00 |
| 31 | Wet reflective spray thermoplastic pavement marking, edge line, 6" (807E13010) | MI | 1.64 | $7,150.00 | $6,275.00 | $7,150.00 |
| 32 | Grooving for 6" recessed pavement marking, (asphalt) (850E10010) | MI | 1.64 | $5,600.00 | $6,935.00 | $5,600.00 |
| 33 | Law enforcement officer with patrol car for assistance (614E11110) | HR | 32 | $120.00 | $85.00 | $120.00 |
| 34 | Detour signing (614E12420) | LS | 1 | $4,600.00 | $7,245.00 | $4,600.00 |
| 35 | Work zone marking sign (614E12460) | EACH | 22 | $95.00 | $93.00 | $95.00 |
| 36 | Portable changeable message sign, as per plan (614E18601) | SNMT | 6 | $1,250.00 | $1,072.00 | $1,250.00 |
| 37 | Work zone lane line, class III, 6", 642 paint (614E20560) | MI | 3.66 | $875.00 | $540.00 | $950.00 |
| 38 | Work zone center line, class III, 642 paint (614E21550) | MI | 8.30 | $1,225.00 | $1,215.00 | $1,295.00 |
| 39 | Work zone edge line, class I, 6", 740.06, type I (614E22210) | MI | 0.25 | $10,950 | $2,000.00 | $22,000 |
| 40 | Work zone edge line, class III, 6", 642 paint (614E22360) | MI | 17.94 | $975.00 | $1,015.00 | $1,000.00 |
| 41 | Work zone channelizing line, class III, 8", 642 paint (614E23680) | FT | 7,412 | $0.62 | $0.75 | $0.66 |
| 42 | Work zone channelizing line, class III, 12", 642 paint (614E23690) | FT | 896 | $2.40 | $0.95 | $2.50 |
| 43 | Work zone dotted line, class I, 6", 740.06, type I (614E24402) | FT | 660 | $1.00 | $0.75 | $4.10 |
| 44 | Work zone stop line, class III, 642 paint (614E26610) | FT | 902 | $5.00 | $3.50 | $5.00 |
| 45 | Pavement removed, as per plan (202E23001) | SY | 119 | $50.00 | $175.00 | $86.75 |
| 46 | Reinforced concrete pavement, misc.:9" class RS (451E20000) | SY | 149 | $300.00 | $450.00 | $664.32 |
| 47 | Sealing of concrete surfaces (epoxy-urethane) (512E10100) | SY | 376 | $28.50 | $28.50 | $37.26 |
| 48 | Sealing concrete bridge decks with HMWM resin (512E10300) | SY | 335 | $23.50 | $23.50 | $28.34 |
| 49 | Removal of existing coatings from concrete surfaces (512E74000) | SY | 376 | $32.00 | $32.00 | $26.93 |
| 50 | Armorless preformed joint seal (516E10010) | FT | 268 | $110.00 | $110.00 | $79.66 |
| 51 | Structural joint or joint sealer, misc.: 3" bejs E (516E14600) | FT | 25 | $125.00 | $125.00 | $200.73 |
| 52 | Patching concrete structure (519E11100) | SF | 720 | $185.00 | $185.00 | $138.80 |
| 53 | Polymer modified asphalt expansion joint system (846E00110) | CF | 32 | $725.00 | $550.00 | $606.91 |
| 54 | Premium for contract performance bond and for payment bond (103E05000) | LS | 1 | $10,000 | $13,883 | $7,500.00 |
| 55 | Maintaining traffic (614E11000) | LS | 1 | $133,000 | $124,000 | $196,000 |
| 56 | Construction layout stakes and surveying (623E10000) | LS | 1 | $8,500.00 | $7,500.00 | $5,000.00 |
| 57 | Mobilization (624E10000) | LS | 1 | $120,000 | $85,000 | $115,000 |
The pay item list has one row per line (item, description, unit, quantity, the low bidder's unit price), the flat layout estimating software imports. Pay items with a page of their own open their price history.
Source
Read from ODOT's tabulation for this contract. ODOT Official Bid Tabulation PDFs from its public DigitalPaper bid tab cabinet, January 2020 to November 2026 (the source links open after DigitalPaper starts a guest session). ODOT prints unit prices to two decimals but computes line amounts from the full price, so a few bids miss their total and are left out. Descriptions are cut at about 50 characters, as ODOT prints them.
Every contract let that day: ODOT letting of October 15, 2026. Compiled by Mirage Metrics.